Attachment 1 - Statement of Work.pdf
PDF 134 KB Posted
- Attached to
- Paxton Access Control/ Secure Comm Rooms Federal contract opportunity
- Solicitation number
- FA460823QC112
About this file
This statement of work outlines requirements for installing a Paxton access control system at multiple buildings located at Barksdale Air Force Base in Louisiana. The contractor must install Paxton Net-2 access control units, power over Ethernet keypads, electric strikes, lever locks, door wraps, and wiring at 20 building locations. The contractor must be Paxton certified with three years' experience and provide references. Materials will be delivered within 90 days of award and installation completed at all sites. The contractor is responsible for labor, transportation, materials, equipment, and any facility damage. The warranty period is 12 months. The related federal contract opportunity is solicitation number FA460823QC112 for Paxton access control and secure communications rooms issued by the Department of the Air Force Global Strike Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 4 - Question Answers.pdf | ||
| FA460823QC112 - Amendment 02.pdf | ||
| Attachment 1 - Statement of Work (Amended).pdf | ||
| FA460823QC112 - Amendment 01.pdf | ||
| Attachment 3 - Site Survey.pdf | ||
| 23QC112 - SAM Combo Synopsis.pdf | ||
| Attachment 2 - Brand Name Justification.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
2 CS
Barksdale AFB
OBJECTIVE
1. Install turn-key Paxton Access Control System throughout the CCF as outlined below. All parts shall be new, used or refurbished strictly prohibited. Parts and pieces must be compatible with existing Paxton system.
QUALIFICATIONS
1. Paxton certified installer with minimum 3-years’ experience.
2. Provide (3) references from recently completed similar jobs.
SCOPE OF WORK:
1. Install Paxton Access Control Units (ACU’s) and Net2 Plus POE keypads at door locations Indicated below.
2. Install door wrap or plates as needed.
3. Install new lever lock with new cores master keyed to existing system.
4. Remove existing mechanical hardware.
MATERIALS
1. Parts to be used:
Nomenclature/Part# UI Qty Net 2 Plus in US MTL Enclosure EA 20 Net 2 KP75 Key Pad EA 20 HES Electric Strike EA 20 GLS Grade 2 Storeroom Lever IC EA 20 BEST SFIC keyed to master EA 20 GLS Door Wraps EA 20 Wiring, mounting, tracking, and supplies. EA 1
2. Submittals required on all parts and pieces.
3. An area will be provided on or near work site as required to store contractors LOM.
SPECIFICS
1. Facility ceilings are suspended type.
2. No computers required.
3. No UPS’s required.
4. No CAD design required.
5. Bond & Insurance Per 2 CONS requirement.
INSTALLATION
1. Each ACU installation location shall be discussed and approved by SCOI prior to install.
2. Installation will be done in a neat and professional manner, to include but not limited to the use of mounting hardware and cable management.
3. Any damage to the facility caused by the contractor will be repaired per 2 CS in conjunction with
2 CONS
INSPECTION, TESTING and CERTIFICATION
1. Spot checks will be performed by SCOI on a daily basis.
2. Each install location will be tested by 2 CS to verify 100 percent serviceability.
WORKSITE LOCATION
1. Different Buildings located at Barksdale AFB, LA 71110
2. Contractor Working Days/Hours:
a. Normal duty time M-F, 0700-1630
b. Days and hours can be adjusted as required with prior approval from 2 CONS and 2 CS 48HRS prior to a proposed change.
2 CS Shall
1. Coordinate contractor base access as required to complete project.
2. Program network switch ports for connectivity and assign required IP’s.
PERMITS
1. No permits required for this project.
PERIOD OF PERFORMANCE
1. 2 CONS and contractor will determine award date based on the onsite start and completion date identified.
2. The facility beneficial occupancy date (BOD) and the dates above will be monitored monthly and any required adjustment will be coordinated with 2 CONS as necessary.
ACRONYMS
1. POE - Power over Ethernet
2. ES - Electrified Strike
3. EL - Electrified Lock
4. ET - Electrified Trim
5. MLR - Motorized Latch Retraction
PAXTON Access Control System
1. General Requirements
1.1. Contractor will assemble/setup on site and will be responsible for all labor, transportation, materials, and equipment for the Paxton Net-2 system.
1.2. Contractor liable for any damage caused by or due to setup. To include building facilities.
1.3. Paxton must be compatible to existing Paxton Net-2 systems currently installed.
2. System Requirements
2.1. Install/provide all wiring to get from door(s) to building access node. Must be in conduit.
2.2. Purchase/Install door electric latch retraction to include door frame hardware
2.3. Purchase/install, Paxton Net-2 system with Power over Ethernet (PoE)
3. Building 7055
3.1. Purchase/install, Exterior Keypad
3.2. Purchase/install, ACU/Control panel-PoE
3.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
3.4. Connect to building access node.
3.5. Verify Operational Capability
4. Building 7201
4.1. Purchase/install, Exterior Keypad
4.2. Purchase/install, ACU/Control panel-PoE
4.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
4.4. Connect to building access node.
4.5. Verify Operational Capability
5. Building 7236
5.1. Purchase/install, Exterior Keypad
5.2. Purchase/install, ACU/Control panel-PoE
5.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
5.4. Connect to building access node.
5.5. Verify Operational Capability
6. Building 7242
6.1. Purchase/install, Exterior Keypad
6.2. Purchase/install, ACU/Control panel-PoE
6.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
6.4. Connect to building access node.
6.5. Verify Operational Capability
7. Building 7251
7.1. Purchase/install, Exterior Keypad
7.2. Purchase/install, ACU/Control panel-PoE
7.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
7.4. Connect to building access node.
7.5. Verify Operational Capability
8. Building 7500
8.1. Purchase/install, Exterior Keypad
8.2. Purchase/install, ACU/Control panel-PoE
8.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
8.4. Connect to building access node.
8.5. Verify Operational Capability
9. Building 7625
9.1. Purchase/install, Exterior Keypad
9.2. Purchase/install, ACU/Control panel-PoE
9.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
9.4. Connect to building access node.
9.5. Verify Operational Capability
10. Building 7678
10.1. Purchase/install, Exterior Keypad
10.2. Purchase/install, ACU/Control panel-PoE 27
10.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
10.4. Connect to building access node.
10.5. Verify Operational Capability
11. Building 4713 (2)
11.1. Purchase/install, Exterior Keypad
11.2. Purchase/install, ACU/Control panel-PoE
11.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
11.4. Connect to building access node.
11.5. Verify Operational Capability
12. Building 4714 (3)
12.1. Purchase/install, Exterior Keypad
12.2. Purchase/install, ACU/Control panel-PoE
12.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
12.4. Connect to building access node.
12.5. Verify Operational Capability
13. Building 4845 (4)
13.1. Purchase/install, Exterior Keypad
13.2. Purchase/install, ACU/Control panel-PoE
13.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
13.4. Connect to building access node.
13.5. Verify Operational Capability
14. Building 5155
14.1. Purchase/install, Exterior Keypad
14.2. Purchase/install, ACU/Control panel-PoE
14.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
14.4. Connect to building access node.
14.5. Verify Operational Capability
15. Building 5441
15.1. Purchase/install, Exterior Keypad
15.2. Purchase/install, ACU/Control panel-PoE
15.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
15.4. Connect to building access node.
15.5. Verify Operational Capability
16. Building 5676
16.1. Purchase/install, Exterior Keypad
16.2. Purchase/install, ACU/Control panel-PoE
16.3. Purchase/install door electric latch retraction-including any door frame hardware necessary
16.4. Connect to building access node.
16.5. Verify Operational Capability
17. Delivery Information:
17.1. Delivery No Later Than 90 days After Contract Award
17.2. Delivery to include installation:
2 CS/SCOI Bldg. 3458 105 Barksdale Blvd East Barksdale AFB, LA 71110
18. Removal & Installation
18.1. Contactor shall remove all shipping and packaging materials from location.
19. Warranty
19.1. Contractor shall include a minimum 12-month warranty of all parts and services on doors and wiring.