Attachment 1_Statement of Work.pdf

PDF 239 KB Posted

Attached to
Design-Build Project - National Malaria Reference Laboratory - Lakka, Sierra Leone
Solicitation number
W912GB23R0007
Issued by

About this file

This is a solicitation announcement for design-build services for a National Malaria Reference Laboratory in Lakka, Sierra Leone. The US Army Corps of Engineers Europe District is seeking proposals to complete 100% design and construction. Offerors must be SAM registered to be considered for award. A pre-proposal site visit is scheduled for 30 November 2022, with registration required. Interested offerors must submit non-price and price proposals by the deadline specified in the solicitation. The project includes design and construction of a new laboratory building, elevated water storage tank support structure, and rainwater catchment tank pad. The location is provided, with relevant codes and standards also specified. Instructions for responding are contained in the solicitation posted with this announcement.

View the file

Other files

File Type Posted
MFA Response to Dip Note.pdf PDF
Dip Note 145-DOD-22.pdf PDF
ProjNet Inquiry Report_24JAN2023.pdf PDF
B.08.01 Attachment 3_Revised Conceptual Site Plan.pdf PDF
ProjNet Inquiry Report 4JAN23.pdf PDF
B.08.02 R230007 Solicitation conformed 7DEC22.pdf PDF
Attachment 9_Bank Letter of Assurance Sample.docx DOCX document
B.08.02 R230007 Solicitation conformed.pdf PDF
Attachment 10_Bank Letter of Guarantee Sample.docx DOCX document
B.08.02 R230007 Solicitation w.TOC.pdf PDF
Attachment 9_Bank Letter of Assurance Sample.docx DOCX document
Attachment 13_Experience Information Sheet.docx DOCX document
Attachment 14_Past Performance Questionnaire.docx DOCX document
Attachment 12_Commitment Letters.docx DOCX document
Attachment 8_Dedication Plaque.pdf PDF
Attachment 10_Bank Letter of Guarantee Sample.docx DOCX document
Attachment 7_WHO Septic guidance.pdf PDF
ATTACHMENT 15 Site Visit Attendee Worksheet.xlsx XLSX spreadsheet
Attachment 3_Conceptual Site Plan.pdf PDF
Attachment 5_Preparation of Structural Calculations AOR AFRICOM with Att.pdf PDF
Attachment 2_Location Map.pdf PDF
B.08.02 R230007 Solicitation.pdf PDF
Attachment 6_Rainwater Tank Example.pdf PDF
Attachment 4_Functional Layout.pdf PDF
Attachment 11_ Specs Binder IAF-23-0007.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers Europe District

APO AE 09049

ar168

Statement of Work Project Number:

SL-HA-2020-00040541

National Malaria Reference Laboratory (NMRL)

Lakka, Sierra Leone

Prepared by:

Design Section

Engineering Branch

25JAN2021

01 10 10 Statement of Work National Malaria Reference Laboratory

11-Feb-21 Page 2 of 55

SECTION 01 10 10

STATEMENT OF WORK

SECTION TABLE OF CONTENTS:

1 GENERAL

2 CIVIL AND GEOTECHNICAL

3 ARCHITECTURAL

4 STRUCTURAL

5 ELECTRICAL & COMMUNICATIONS

6 MECHANICAL & PLUMBING

ATTACHMENTS

Attachment # 1 Location Map Attachment # 2 Conceptual Site Plan Attachment # 3 Functional Layout Attachment # 4 Structural Calculations Guideline Attachment # 5 Rainwater Tank Example Attachment # 6 WHO Septic Tank Guidance Attachment # 7 Dedication Plaque

1.0 GENERAL

1.1 PROJECT DESCRIPTION

The Request for Proposal (RFP) provides parameters for a design-build project for construction of a new National Malaria Reference Laboratory (NMRL)facility in Lakka, Sierra Leone; Latitude 8°23'53.50"N, Longitude 13°15'50.14"W (Refer to the attached Location Map.)

The project is to provide a new structure that will house the NMRL operations. The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:

a. Clear, grub, and grade the site

b. Demolition of the existing structure

c. Construct new National Malaria Reference Laboratory Facility

d. Provide site improvements including a water borehole with a generator and elevated water storage tank, a rain catchment system, septic system, incinerator, and a contaminated water treatment/storage system.

1.2 GENERAL REQUIREMENTS

The Contractor must deliver fully functional, turnkey type facilities (without mobile furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work.

The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.

These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.

1.2.1 BASE ITEMS AND OPTIONAL ITEMS

11-Feb-21 Page 3 of 55

This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to Specification Section 01 22 00 PRICE AND PAYMENT PROCEDURES. The Schedule of Items identifies the breakdown between the individual base items and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base or Optional Items. Consider all items not specifically identified in the Optional Items as part of the Base Items.

1.3 FUNCTIONAL AREAS

Refer to the attached drawings for a depiction of the required functional areas and spatial adjacencies for the site and new facilities/structures.

Provide the following functional areas within the facility:

101 LABORATORY 68.16 sqm 102 WASH. & PREP. 21.60 sqm 103 BREAK 7.56 sqm 104 STOR. 8.64 sqm 105 OFFICE 10.24 sqm 106 PHLEBOTOMY 6.40 sqm 107 REC. /WAIT. 14.52 sqm 108 TOIL. 1.35 sqm 109 TOIL. 1.35 sqm 110 JAN. 2.70 sqm 111 EL. 2.83 sqm

Total usable area to be provided: approximately 141.98 m2 net, (160 m2 approximately gross area).

1.4 SUBMITTALS

Designer of Record approval is required for submittals with a “DA” designation.

Government approval is required for submittals with a “G” or “GA” designation.

Submittals having an “FIO” designation are for Contractor Quality Control approval. Submit the following to the Contracting Officer (KO) in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Demolition Plan; G

SD-05 Design Data

65% Pre-Final Design; DA/GA

95% Final Design; DA/GA

100% Corrected Final Design; DA/GA

SD-06 Test Reports

Test Results and Reports; FIO

1.4.1 DESIGN SUBMITTALS

Provide a complete design package at each milestone, as described in RFP Section 01 33 16-DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.

11-Feb-21 Page 4 of 55

1.4.2 TEST REPORTS

Provide all test results and reports identified in this SOW to the Government as a submittal in accordance with RFP Section 01 33 00-SUBMITTAL PROCEDURES. Submittals will be considered for information only (FIO) submittals unless specifically identified as a submittal requiring government approval. Coordinate with the KO after award for the specific items to be included in the submittal register.

1.5 MATERIALS AND EQUIPMENT

Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.

Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the KO.

1.5.1 LIFE-SPAN

The facility and the installed equipment must be permanent construction with an expected lifespan of more than 25 years.

1.5.2 MAINTAINABILITY

Provide low maintenance materials and systems appropriate for the project climate and location.

1.5.3 OPERABILITY

Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.

1.5.4 STANDARDIZATION

Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.

1.6 DESIGN DIMENSIONS

Develop the design using the metric system.

1.7 DESIGN CRITERIA

Project design, site facilities, utility systems and material standards must be in accordance with Host Nation building codes (current versions as of the date of RFP, unless otherwise indicated). In the absence of Host Nation building codes, use the International Building Code (IBC) and the codes, technical standards, and regulations referenced in this RFP.

While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the KO. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.

Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.

11-Feb-21 Page 5 of 55

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

1.8.1 DEMOLITION

The Contractor is responsible for all required demolition as indicated in this scope.

Submit a Demolition Plan to be tracked via the submittal register indicating all demolition, abatement, and disposal methods.

1.8.1.1 ABATEMENT AND DISPOSAL

All demolished materials, including hazardous materials identified below, must be abated and disposed of in accordance with local laws, codes and regulations. The Contractor is responsible for all required testing before, during and after demolitions as well as for all required compliance with safety standards.

1.8.1.2 LOCATION OF HAZARDOUS MATERIAL

The Contractor is responsible to survey the site and determine if hazardous materials exist. If hazardous materials are found to exist, immediately notify the KO and provide the results of the relevant sampling and testing. Provide the hazardous material report no later than 30 days after Notice to Proceed (NTP) for information and approval.

END OF SECTION

11-Feb-21 Page 6 of 55

2.0 CIVIL AND GEOTECHNICAL

Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional and usable project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.

2.1 SCOPE SUMMARY

Civil works for this project include, but are not limited to, site survey, geotechnical investigation, site layout, demolition, earthwork, storm system, sanitary system, water system, and landscaping. Refer to the bid schedule for which of these are base bid or optional.

2.2 EXISTING CONDITIONS

2.2.1 TOPOGRAPHY

There is no known topographic survey for the project site. The existing site contains buildings, assumed abandoned utilities, and vegetation as shown on the attached Conceptual Site Plan. The existing information shown on the Conceptual Site Plan was compiled from Google Earth and site photos.

2.2.2 UTILITIES

There is no available information on the storm system within the site. However, it is assumed that there is no storm system at the site.

There is no existing water system available for this building at the site.

There is no known existing sanitary system for this building at the site.

Power, gas, communications, and district heat are not available on site. Refer to the other sections of this SOW for requirements about these existing utilities.

Contractor must verify all utility locations (surface and subsurface) in the field prior to the first design submittal.

2.2.3 GEOTECHNICAL

There is no geotechnical information available for the project site.

The Contractor must perform a Geotechnical Investigation and submit a Geotechnical Report as part of the Design Analysis. Refer to other sections of this SOW for the requirements of the Geotechnical Investigations and Report.

2.2.4 ENVIRONMENTAL

There are no known environmental protection areas or archeological preservation areas on the project site.

There is no prior knowledge of any hazardous or contaminated materials in the site’s soil.

2.2.5 EXISTING CONDITIONS INVESTIGATION

Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:

a. Weather, river stages, tides, or similar physical conditions at the site.

b. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research of as-built drawings, geotechnical reports, environmental reports, and publicly available information on the site.

c. Mobilization and staging constraints.

2.3 DESIGN SUBMITTALS

11-Feb-21 Page 7 of 55

Provide civil design submittals in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and in compliance with SOW Section 1.0 – GENERAL.

65% Design Submittal:

a. Pre-Final Design Analysis of civil features.

b. Final Site Survey (include in the Design Analysis).

c. Final Geotechnical Report (include in the Design Analysis).

d. Final Existing Conditions Plan.

e. Pre-Final Demolition Plan

f. Pre-Final Grading Profiles, Cross Sections, and Details. Include spot grades and slopes in Grading Plan. Include retaining wall profiles, cross sections, and details. Include erosion control design.

g. Pre-Final Utility (Storm, Sanitary, and Water) Profiles, Cross Sections, and Details.

h. Preliminary Landscape Plan and Details, including seed mix and seed coverage rate

i. Preliminary Civil Specifications

95% Design Submittal:

Update all items from the 65% Design Submittal to 95% (Final) Design. Incorporate all 65% design comments.

100% Submittal:

The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal. Address all previous government review comments before submitting.

As Built Drawing Submittal:

In addition to the as-built requirements discussed in RFP Section 01 78 00- CLOSEOUT SUBMITTALS, provide a topographical survey of the site per requirements of SOW Section 2.6-SITE SURVEY. Include existing utility lines or structures (both modified and unmodified) encountered in the construction footprint that were not located on the original Site Survey.

2.3.1 DESIGN ANALYSIS

Submit a Design Analysis in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD. Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval. Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.

The Design Analysis includes but is not limited to:

a. Discussion of Site Layout constraints and design decisions, including but not limited to, land use, vehicle and pedestrian access, orientation of features on-site, setbacks from site features, minimizing utility lengths, minimizing earthwork and tree removal, and future expansion.

b. Discussion of Demolition constraints and design decisions. Include discussion on how access will be provided during construction, and how each utility will be maintained and operated during construction.

c. Discussion of Earthwork and Site Grading constraints and design decisions.

Provide cut and fill calculations. Provide retaining wall calculations.

Provide slope stability calculations for slopes steeper than 2H:1V or slopes supporting proposed structures. Include pertinent geotechnical information that affects earthwork.

11-Feb-21 Page 8 of 55

d. Discussion of Storm system constraints and design decisions. Provide a hydrologic and hydraulic analysis of the storm system, including offsite areas that contribute to and influence the project’s storm system. Provide drainage basin map(s), rainfall data, and coefficients used. For each section of pipe, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity. Provide calculations for sizing of structures, including detention, infiltration, and LID features. Provide documentation for the 100 year flood elevation determination. Provide Pre and Post Development comparisons for detention/retention facilities. Use the Rational Method or TR-55 for analysis and design. In the absence of Host Nation or Installation requirements, use a minimum 10-year storm frequency for analysis and design. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities. Include pertinent geotechnical information that affects the storm system. Confirm that the existing receiving system has adequate capacity to receive the additional stormwater flow generated by the project.

e. Discussion of Sanitary system constraints and design decisions. For each section of pipe, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity. Provide calculations for sizing of structures, including septic tanks, infiltration structures, and pumps. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10- Utilities. Include pertinent geotechnical information that affects the sanitary system. Confirm that the existing receiving system has adequate capacity to receive the additional sanitary flow generated by the project.

f. Discussion of Water system constraints, design decisions and source. Provide calculations to demonstrate water system meets project requirements, including demand, water pipe sizing, design water pressure and flow rates at buildings and fire hydrants, as applicable). Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10- Utilities. Provide well and water tank calculations.

g. Discussion of incinerator design decisions and constraints. Discussions for civil section must include, but are not limited to: location of incinerator relative to building, foundation discussion, and power requirements.

h. Discussion of Landscaping constraints and design decisions.

i. Site Survey as an appendix.

j. Geotechnical Investigation and Report as an appendix.

2.3.2 DESIGN DRAWINGS

Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of Civil features for the project. Civil drawings also include temporary construction plans/methods that affect the design and construction of the project.

These temporary plans include mobilization, traffic control, erosion control, dewatering, shoring, construction sequence, etc. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features.

Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. Reference USACE A/E/C Graphics Standard for graphic requirements.

2.3.3 SPECIFICATIONS

Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, 11-Feb-21 Page 9 of 55 allow for complete understanding and constructability of all proposed Civil features.

2.4 DESIGN CRITERIA

Provide civil design in accordance with Host Nation codes. In the absence of Host Nation codes, use the latest release of the International Building Code (IBC) and the following codes and technical standards:

a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering

b. UFC 3-220-01, Geotechnical Engineering

c. USACE A/E/C Graphics Standard (ERDC/ITL TR-12-1)

d. UFC 3-230-01, Water Storage, Distribution, and Transmission

e. UFC 3-240-01, Wastewater Collection

f. UFC 3-600-01, Fire Protection Engineering for Facilities

World Health Organization (WHO) Guidelines for Drinking-water Quality ANSI/AWWA A100-06, Water Wells TB MED 577/NAVMED P-5010-10/AFMAN 48-138_IP, Sanitary Control and Surveillance of

Field Water Supplies NTRP 4-04.2.13/FM 3-34.469/AFMAN 32-1072, Water-Well Drilling Operations USACE AED Design Requirements: Sanitary Sewer & Septic System WHO Technical Notes on Drinking-Water, Sanitation and Hygiene in Emergencies WHO Fact Sheet 3.9 – Septic Tanks.

UFGS SECTION 11 82 19 Packaged Incinerators – Guide spec for determining incinerator criteria for design.

2.5 GEOTECHNICAL INVESTIGATION AND REPORT

Perform a geotechnical investigation and assessment of the project site to determine the subsurface conditions and geotechnical parameters for foundation, grading, and utility design. Perform the necessary amount of testing, borings and test pits at depths suitable for the project improvements. Include geotechnical investigation in areas where borrow material will be used. The Geotechnical work must be performed under the supervision of a professional geotechnical engineer registered with the jurisdiction having authority, and the report must be signed by the Geotechnical Engineer. In the absence of Host Nation codes, perform the geotechnical investigation and report per UFC 3-220-01, Geotechnical Engineering and IBC.

Coordinate testing locations with the KO to avoid impact to existing utilities and facility operations. Utility locates, permits, pavement removal and vegetation clearing is the Contractor’s responsibility. Repair disturbed areas with compacted soil in non-paved areas. The repaired area must be flush with the adjacent surface. Following restoration, stake and flag each of the hole locations with boring identification numbers. Provide a map indicating the borehole and test pit locations.

2.5.1 REPORT

Include, as a minimum, the following information:

a. Description of field work completed and equipment used; names, signatures and stamps of licensed professionals involved; name of drilling company.

b. A description of site subsurface conditions, regional geology, and seismic conditions at the site.

c. Site map of borehole and test pit locations.

d. High resolution color digital photographs of each borehole and test pit location.

e. Test pit logs with classification of all subsurface materials. The logs must distinguish fill materials from native materials, include all in-situ test

11-Feb-21 Page 10 of 55 results, and include groundwater depth information, if groundwater is encountered. Distinguish between bedrock and rock boulders.

f. Reports of all the field and laboratory testing.

g. Recommendations for allowable bearing capacity, expected settlement, type of foundation, minimum footing and grade beam dimensions, lateral earth pressure parameters, and minimum depth of foundation for footing and grade beams.

h. Recommendations for preparation, placement, and compaction of onsite soils, borrow material, soil replacement, soil amendment/treatment, structural fill, topsoil, and trench backfill. Include dewatering and temporary retaining structure needs.

i. Soil Resistivity.

j. Frost Depth (if applicable).

k. Recommendations for the storm and septic systems involving infiltration.

l. Recommendations for the water well.

m. Calculations to support conclusions and recommendations.

2.5.2 DESIGN DRAWINGS AND SPECIFICATIONS

On the design drawings and/or specifications, include geotechnical information that affect the design of the project, including but is not limited to, boring locations, boring logs, groundwater and frost depths, and any details that convey requirements for site preparation.

Perform all geotechnical investigations necessary for the design and construction of project features. Provide any geotechnical investigations and reports to the Government that are performed. Provide geotechnical information and assumptions in the Design Analysis to support design decisions. In the absence of geotechnical investigations performed on-site, an allowable soil bearing pressure is discussed in STRUCTURAL section 4.0. Perform geotechnical work required for construction (i.e. compaction tests, inspection of structure foundation excavations). In the absence of Host Nation standards, perform the geotechnical scope of work per UFC 3-220-01, Geotechnical Engineering and IBC.

2.6 SITE SURVEY

Conduct and provide a topographic survey from a licensed surveyor that includes all existing site information needed to design and construct the project. Survey must be conducted prior to the first design submittal. Include x, y, and z coordinates to the nearest 0.005 meters, dimensions, material, and basic characteristics of all features within the project site limits, as well as all features outside of the project site limits that will affect the design and construction of the project. Research record drawings to obtain utility and pavement information that is not visible from the surface. Provide notes indicating the sources and any limitations or assumptions of the data. Provide a copy of the survey in CAD, in addition to the paper/electronic requirements of the Design Analysis. Locate and show on the topographic survey the following information:

a. Property boundary, public right of way, and easements. Include the address numbers, street names, and easement records.

b. Survey monuments. Include description.

c. Spot elevations covering the entire survey limits showing high points, low points, grade changes, and at sufficient intervals to represent the general character of the terrain.

d. Contours in intervals of 0.25 meters.

e. Buildings and other miscellaneous structures. Provide finish floor elevation.

f. Pavements. Include pavement type, thicknesses, joint patterns, and pavement markings. Include top of curb and gutter elevations.

g. Surface Drainage Features. Indicate normal water level for water bodies.

11-Feb-21 Page 11 of 55

h. Utility lines and structures. Include rim elevations and invert elevations for utility structures; identification of lines as underground or aboveground;

pipe sizes and materials.

i. Signs. Include sign text.

j. Trees: In areas that trees are to be protected, locate outside drip line of wooded area, include general density and type of trees. For areas with proposed tree removal, identify trees per Host Nation permitting requirements.

Where selective clearing will be proposed, locate trees over 150 millimeter diameter at chest height, and include tree species, diameter at chest height, and dripline diameter.

k. Geotechnical boring locations.

l. Locate environmentally sensitive areas (determined and marked by others).

m. North arrow and scale of drawing.

n. Legend depicting the symbols and abbreviations used on the drawing.

o. Horizontal and vertical coordinate systems, date of survey, licensed surveyor name and license number.

Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information. Utility field locates and as-built research are the responsibility of the Contractor.

Upon completion of construction, update the original survey with an As-built survey of the site as constructed, including underground utility locations and depths. Submit the As-built survey to the KO for approval.

Reference UFC 3-201-01, Civil Engineering, Section 2-2.2-SURVEYING for survey requirements. Use the Universal Transverse Mercator (UTM) coordinate system. The vertical coordinate system must be based on sea level.

2.7 SITE LAYOUT

Locate the proposed building and other improvements as indicated on the attached Conceptual Site Plan. Amend the site layout as determined by the site-specific constraints, the owner’s preferences, accessibility, future expansion, and opportunities that are identified and evaluated as part of the Contractor’s scope of work. Locate the proposed building a minimum of 3 meters away from existing buildings. Locate the proposed building outside the dripline of existing trees.

The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.

2.8 DEMOLITION

Remove existing structures and foundations, any existing abandoned utilities, vegetation, and any other features to construct the proposed improvements. Remove trees with driplines within the footprint of the proposed improvements. All contaminated soils discovered require special testing and disposal per Host Nation requirements.

2.8.1 CONSTRUCTION LIMITS

Do not disturb the project site beyond necessary for installation of proposed construction. Do not disturb any areas past the site’s property line. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.

2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as required by the KO. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide

11-Feb-21 Page 12 of 55 new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the KO prior to performing said work.

2.8.3 TREES

Unless otherwise noted on, protect trees which might be damaged during construction, with a 1.8 meter high fence around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots. Trees are defined as larger than 150mm diameter at 1.3 meters above existing grade. Mitigate for tree removal per Host Nation requirements.

2.8.4 UTILITIES

Any existing utilities encountered that are impacted by this project must be protected, or relocated if protection is not feasible. Remove existing and abandoned utilities under or within 3.0 m of the foundation of any proposed facility or building foundation. Reroute existing utilities to remain in accordance with SOW Section 2.10-UTILITIES. Abandoned utilities must be removed up to the utility main (or next utility main junction) and capped. Manholes or underground structures to be abandoned must be removed to a minimum depth of 50 centimeters below finish grade. Fill abandoned manhole or structure per Section 2.9-EARTHWORK requirements.

2.8.5 DUST, DEBRIS, AND EROSION CONTROL

Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily.

Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

2.8.7 ADDITIONAL REQUIREMENTS

Reference RFP Section 00 74 01-SPECIAL CONDITIONS and 01 30 01-GENERAL REQUIREMENTS for additional demolition, protection, and permitting requirements.

2.9 EARTHWORK

Perform all earth work necessary for the installation of the proposed improvements.

2.9.1 PLANS AND SPECIFICATIONS

Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems.

2.9.2 UNEXPLODED ORDNANCE (UXO) CLEARANCE

UXO survey is not required.

2.9.3 CONTAMINATED SOIL

Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the KO for further guidance.

2.9.4 CULTURAL RESOURCES

11-Feb-21 Page 13 of 55

Cultural resources, such as archaeological remains, may be uncovered during excavation operations. If suspected cultural remains are found, cease excavation, secure the area, and notify the KO for further guidance.

2.9.5 TOPSOIL

Remove and save topsoil (approximately first 20 centimeters of excavation), if applicable. Separate out subsoil, brush, litter, weeds, roots, stones larger than 25 mm in diameter, and other materials that would interfere with planting and maintenance operations. When restoring the site to finish grade, place topsoil back in excavated areas that do not include proposed paving or structures.

2.9.6 SATISFACTORY MATERIAL

Excavated material (below topsoil), if satisfactory for reuse per the Contractor’s Geotechnical Engineer, may be used on the project site where fill is required.

Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified clean.

2.9.7 BACKFILL COMPACTION

In the absence of Host Nation requirements and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and 1 test per 30 meters of road and utility trench. Round up to nearest whole number (i.e. a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s geotechnical engineer, and copies of all test results must be furnished to the KO. All structure foundation excavations must be inspected and approved by the Contractor’s Geotechnical Engineer prior to placing concrete. Repair earthwork areas as recommended by the Contractor’s Geotechnical Engineer, and approved by the KO.

2.9.8 ENGINEERED SOIL SUPPORT SYSTEMS

Provide engineered soil support systems (i.e. shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.

2.9.9 SITE GRADING

Provide site grading that directs storm water runoff away from buildings and structures either by drainage systems or by grading as follows:

a. Finished grades of earth/grass/gravel surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 5% for the first 2 meters.

b. Finished grades of paved surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 2% for the first 2 meters.

c. Finished grades must not create stagnating water or ponding anywhere on the project site, nor create ponding on adjacent properties. Provide storm improvements if ponding is unavoidable.

d. In accordance with requirements of UFC 3-201-01, Chapter 2-8 Grading

Site grading around the building must meet ABA and Host Nation accessibility guidelines. The Contractor must limit proposed landscape slopes to a maximum 4H:1V for grass areas requiring mowing and 2H:1V for non-grass areas, which require non-erodible surface (i.e. rock, shrubs with mulch).

11-Feb-21 Page 14 of 55

2.10 UTILITIES

This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, storm drainage, electrical, and communications. See Sections 5.0-ELECTRICAL & COMMUNICATIONS, Section 6.0-MECHANICAL, and Section 7.0-FIRE PROTECTION for additional utility requirements.

Proposed utility main alignments must be at least 3.0 meters from facility or building foundations, except for building connections. Provide horizontal and vertical separation between new and existing utilities for rehabilitation, maintenance, repair or replacement. Provide utility line depths, bedding, and backfill as required by applicable requirements and geotechnical recommendations.

Minimum cover over pipes is 0.6 meters; greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used;

whichever is more stringent. Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.

Coordinate all required installation, relocation, improvement and protection of utilities held by third party (e.g. public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials and products for utility installation must be coordinated with the utility owner (customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.

Provide utility materials per IBC requirements. Provide corrosion protection for utilities that provides the minimum life expectancy specified in Section 1.0- GENERAL. Any piping or equipment exposed to sunlight must be coated with protective coatings suitable for UV exposure with a minimum expected coating life of 10 years before recoating.

2.10.1 STORM SYSTEM

Provide a gravity storm drainage system to direct runoff away from improvements, eliminate ponding, and prevent erosion. A pump system is not allowed. If using an infiltration or detention system, locate infiltration/detention facilities a minimum of 3 meters away and downhill from structures. Provide an overflow to the infiltration/detention system that will not damage improvements or cause erosion.

Storm structures must be concrete, with traffic rated cast iron or ductile iron frames and covers. In the absence of Host Nation standards, design the storm drainage system per UFC 3-201-01, Civil Engineering Chapter 3-Storm Drainage Systems.

Provide a storm drainage system to direct runoff away from improvements and eliminate ponding. Connect building roof gutters and downspouts to two rainwater tanks (5000 liter each) as shown on the attached Conceptual Site Plan and attached Rainwater Tank Example. Locate tanks out of pathways and windows. For each rainwater tank, provide a spigot at the bottom of each tank. Below the spigot, provide a splash block that will drain water away from building foundations a minimum of 3 meters per site grading requirements. Provide an overflow system from the tanks to the “Grey Water” gutter system or splash blocks that drain away from foundations a minimum of 3 meters per site grading requirements. Reroute existing “Grey Water” system as necessary. Provide insect screens to all open orifices to the tank system. Provide UV resistant tanks. Provide concrete foundation to support rainwater collection tank, and install the bottom of the tank a minimum of 45 centimeters above finish grade. Provide structural tie downs for the tank.

Provide an opening for cleaning and allow access into the tanks. Provide system in order to divert first flush from the roofs that may be contaminated with dust, animal droppings and dirt so that it does enter the tank. Provide sign next to tap

11-Feb-21 Page 15 of 55 that shows a pictogram “not for drinking”. Sign must be firmly fastened aluminum or other durable weather resistive material (no adhesive sticker allowed).

After installation, test storm lines and structures for leakage and deflection per local codes. Provide test results to the KO. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.

2.10.2 SANITARY SYSTEM

Provide a septic system with tank, drainfield, piping, and all appurtenances. Size the system based on the occupancy and a 5 year maintenance schedule of pumping of the septic tank. Provide geotechnical fabric between soil and drainfield to prevent clogging of the drainfield. Locate the sanitary system to allow for maintenance and cleaning. The system must have the ability to be monitored, pumped out, and have an alarm system when the capacity is being reached that reports to the building. Locate the septic tank a minimum of 10 meters from buildings. Locate the drainfield a minimum of 3 meters from the septic tank, structures, and outside the dripline of trees. The system must work by gravity. A pump system is not allowed. If the Geotechnical Investigation determines that the soil percolation rate is less than 15 millimeter/hr, provide a holding tank with 10 day capacity instead a septic system. In the absence of Host Nation standards, design the sanitary system per UFC 3-240-01, Wastewater Collection and WHO Fact Sheet 3.9 and USACE AED Design Requirements: Sanitary Sewer & Septic System.

Drains from the main lab and prep area must connect to a reservoir to treat contaminated water. Provide a small on-site packaged treatment plant to treat and discharge laboratory waste fluids. Plant must be able to treat effluent to acceptable contamination levels on site. Treated effluent must be discharged into the new septic and drain field system.

Allowable sanitary pipe materials include polyvinyl chloride (PVC), high density polyethylene (HDPE), or ductile iron. Sanitary structures must be concrete, with traffic rated cast iron or ductile iron frames and covers. In the absence of Host Nation standards, design the sanitary system per UFC 3-240-01, Wastewater Collection.

After installation, test sanitary lines and structures for leakage and deflection per local codes. Provide test results to the KO. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.

See SOW Section 6.0 – MECHANICAL for indoor sanitary scope.

2.10.3 WATER SYSTEM

Provide a water system to connect the proposed building to the proposed well and water tank as shown in the attached Conceptual Site Plan. Design the system to meet all flow requirements of the facility, including potable water and fire flows. Provide a meter at the water connection point that is accessible by a third party utility.

All new water distribution piping must have a minimum horizontal separation of 3 m from all new or existing storm sewers, septic tanks, and pit latrines.

Assume a well depth of 50m for bidding purposes. The well pump must be powered by a generator, and must have sufficient performance to fill the elevated water storage tank in the amount of time required for proper operation of the water supply system. Provide a locked access to the pump with 2 sets of keys. Provide a manual pump option to the well if the electric pump fails. New wells must be

11-Feb-21 Page 16 of 55 located a minimum of 30 m, but 50 m is preferable, from all septic systems or pit latrines.

To provide a reliable pressure and flow rate to the building, provide an elevated water tank between the well and the building. Provide a water storage tank size and elevation for the operational requirements of the facility. Tanks must be designed, fabricated and constructed for drinking water use. The water tank and piping must be UV resistant and include appropriate features (i.e. shading, insulation) to ensure water temperatures stay at an acceptable level for facility use. The water tank must have the ability to be filled by truck delivery, and include an access ladder and man-way for interior access for cleaning. The location of the fill connection must be convenient and labeled. The fill point and cleaning access must be secured and locked.

In the absence of Host Nation standards, design the well system per ANSI/AWWA A100-06, Water Wells, NTRP 4-04.2.13/FM 3-34.469/AFMAN 32-1072, Water-Well Drilling Operations, and the IBC.

In the absence of Host Nation standards, design the water system per the IBC. UFC 3-230-01, Water Storage, Distribution, and Transmission and UFC 3-600-01, Fire Protection Engineering for Facilities.

After installation, test water supply lines according to local codes for leakage.

Before the water supply line is put into final operation, disinfect the line, and then flush the line to remove traces of the sterilization agent. Test treated line for coliform bacteria. Provide test results to the KO. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.

See SOW Section 6.0 – MECHANICAL for indoor water scope, water tank, and well scope of work.

2.11 PAVEMENT

Provide PCC slabs for generators and other proposed outdoor features that serve the proposed facility. Provide medium broom finish on PCC concrete.

Provide minimum 1 meter wide concrete building apron around the entire building.

Install concrete over minimum 15 centimeters aggregate. Install the top of the apron a minimum of 10 centimeters above the adjacent ground. Provide a minimum of 5 centimeters of bury on the concrete. Provide expansion joint between building and apron. Provide expansion joints within the building apron spaced at 1 meter maximum to prevent cracking.

In the absence of Host Nation standards, design pavements per UFC 3-201-01, Civil Engineering.

2.12 OUTDOOR FURNISHINGS

2.12.1 BOLLARDS

Provide bollards to protect the generator, well, and water storage tank. Locate bollards 30cm away from the structures. Consistently space bollards 1 meter apart (+/- 0.2 meters) around generator, fuel storage, well, and water storage tank.

Bollards must be a minimum 1.22 meter high above ground level, 10 centimeters diameter steel pipe filled with concrete, painted yellow, and embedded in a Portland cement concrete foundation. Steel pipe wall must be minimum 6 millimeter thick. The foundation must not be attached to the building foundation or the slab.

11-Feb-21 Page 17 of 55

2.12.2 SIGNS

Provide facility signage in accordance with the Host Nation standards. Size messages and graphics on signs according to the functional viewing distance.

Typically, at least 25 millimeter of letter height per 7.62 meters of viewing distance is required for readability.

2.13 LANDSCAPING

Provide 15 centimeters of compacted gravel with a maximum particle size of 3 centimeters in areas that do not have pavement or a building within the limits of disturbance. Refer to 2.9 EARTHWORK section for minimum compaction requirements.

Before using chemicals during landscaping work, including for use on plants and on site features, the Contractor must submit to the KO, in the form of brochures, certificates and other technical material, information about the chemicals proposed, including about their environmental compatibility. Their use is only permitted with approval of the KO.

11-Feb-21 Page 18 of 55

3.0 ARCHITECTURAL

3.1 PROJECT DESCRIPTION

Provide and perform architectural design and construction services to provide a complete, accessible, functional, and usable National Malaria Reference Laboratory in Lakka, Sierra Leone.

Provide a new single-story, solid masonry / concrete building that will serve as National Malaria Reference Laboratory.

Extensive coordination is required between the architectural work and the civil, geotechnical, structural, fire protection, mechanical, and electrical requirements of this project.

3.1.1 DESIGN

Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the KO. A functional layout has been attached for reference. The functional layout is provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.

3.1.2 DESIGN SUBMITTALS

Provide all architectural submittals after contract award in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and 01 33 00-SUBMITTAL PROCEDURES. Prepare and submit the documents listed below at the submittals indicated.

3.1.2.1 65% DESIGN SUBMISSION

Include the following drawings and reports as applicable to the project:

a. Code Summary – Provide a tabular code compliance summary indicating Host Nation and/or IBC life safety requirements for all new facilities.

b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.

c. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.

d. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.

e. Building Elevations – Provide all building elevations indicating all exterior materials.

f. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

g. Building Section – Indicate heights of critical building elements.

h. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.

i. Interior Elevations – Provide interior elevations of all bathrooms and built-in casework and kitchenettes, indicate critical heights of surfaces and plumbing fixtures and describe all materials and finishes.

j. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.

k. Pre-Final Specifications – Provide detailed explanations of requirements for all performed work or provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

11-Feb-21 Page 19 of 55

3.1.2.2 95% DESIGN SUBMISSION

The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include the following drawings and reports as applicable to the project:

a. All documents from the 65% submittal updated to incorporate 65% review comments.

b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.

c. Building Elevations – Provide all building elevations indicating all exterior materials.

d. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

e. Building Section – Indicate heights.

f. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.

g. Section and Plan Details – Provide details of critical building intersections.

h. Window and Door Schedule –…