This is a Statement of Work (SOW) for the BLM Monitoring Well Plugging Phase III project, managed by the Bureau of Land Management's Buffalo Field Office in the High Plains District of Wyoming.
The primary objective is to plug existing monitoring wellbores and reclaim disturbed surfaces according to landowner requirements or BLM standards. The project encompasses 12 well locations across Wyoming containing approximately 40 individual wells requiring plugging. Well locations include Durham Ranch (4 wells across 2 sites), Kingsbury MW, Napier MW (2 wells), Skewed MWs (13 wells at one location), Sasquatch MW, Carr Draw MW (2 wells), Timar Stock Well, Coal Gulch MW, Petrified Tree MW, Remington MW (3 wells), and Ford Ranch II POD (2 components). The contractor must pull all existing tubing, airlines, wire, and equipment from wellbores; haul tubing from BLM surface wells to the BLM Welch Ranch property for stacking; and plug wellbores using Class G cement mixed at minimum 13.5+ ppg with at least 50% cement by weight. For Skewed wells with PVC casing, non-slurry bentonite grout with minimum 20% bentonite by weight solids must be used. Contractors must retrieve tension-set packers with up to 30,000 pounds of tension capability and may need to mill out packers if they do not release. All displaced fluids must be transported to Wyoming DEQ-approved disposal facilities. Surface reclamation includes removing infrastructure, stripping topsoil, and broadcast seeding disturbed areas with BLM-approved seed mix containing 18.38 PLS per acre. The Skewed well area requires additional reclamation with waterbars constructed minimum 18 inches deep and mulch applied at 1,000 pounds per acre minimum. Well identification markers must be permanently welded to cut-off casings except for Skewed wells, which require removal of surrounding concrete and steel posts. Access roads require repair to pre-existing or better conditions, and the Remington site requires removal of power drop infrastructure. Contact for the project is Zach Nicholson, Project Inspector and Contracting Officer Representative, at 307-684-1160 or znicholson@blm.gov.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BLM Monitoring Well Plugging
Phase III
STATEMENT OF WORK & SITE LOCATION
BUFFALO FIELD OFFICE
HIGH PLAINS DISTRICT OFFICE
W yom ing - H igh P lains D istrict O ffice
O ffice N am e and S tate goes here
BLM Monitoring Well Plugging SOW Phase III Bureau of Land Management, High Plains District, Wyoming Field Office: Buffalo Field Office (BFO)
Statement of Work and Specifications
Project Name BLM Monitoring Well Plugging Phase III & Ford Ranch Orphan
Objectives - Plug the existing wellbores and reclaim the surface to landowner requirements or BLM standards.
Location 1. Durham Ranch 14 MW T44N R72W Sec. 14 SENE Surface owner and contact info: Durham Ranches, Inc., Ranch manager Pat Thompson 307-257-3813
a. Durham Ranch Sec. 14 Wyodak Coal SEO(Wyoming State Engineer's Office) #:P106973.0W
b. Durham Ranch Sec. 14 Wasatch Sand
SEO#: P106972.0W
2. Durham Ranch 6 MW T45N R71W Sec. 6 SWNE Surface owner and contact info: Durham Ranches, Inc., Ranch manager Pat Thompson 307-257-3813
c. Durham Ranch Sec. 6 Wyodak Coal
SEO#: P106975.0W
d. Durham Ranch Sec. 6 Wasatch Sand
SEO#: P106974.0W
3. Kingsbury MW T46N R78W Sec. 25 NWSE Surface Owner and contact info: Bureau of Land Management
a. KU 33-25-4678S-MON API (American Petroleum Institute) #:49-019-06445
SEO#: P179493.0W
4. Napier MW T48N R76W Sec. 24 SESE Contact: Bureau of Land Management
a. Napier MW Big George Coal
API#:49-005-07914 SEO#: P133775.0W
b. Napier MW Wasatch Sand
API#:49-005-07915 SEO#: P133776.0W
5. Skewed MW’s T48N R77W Sec. 21 SENW Surface Owner and contact info: Bureau of Land Management
a. SK1
b. SK2S
c. SK2D
d. SK3
e. SK4S
f. SK4D
g. SK5
h. SK6
i. SK7
j. SK8
k. SK9
l. SK10
m. SK11
Skewed MW’s T48N R77W Sec. 21 SENW Contact: Anschutz Corporation, PRB Regulatory Cindy Vue – (303) 299-1578
a. SK12
b. SK13
c. SK14
d. SK15
e. SK16
f. SK17
g. SKS18
6. Sasquatch MW T48N R78W Sec. 26 NWNE Surface Owner and contact info: Bureau of Land Management
a. Sasquatch MW
API#:49-019-20920
7. Carr Draw MW T50N R75W Sec. 29 NENE Surface Owner & Contact Information: Billy C. Maycock 307-682-3977
a. Carr Draw MW Gates/Werner Coals
API#:49-005-07636, SEO#: P177450.0W
b. Carr Draw MW Overburden Sand/Big George Coal
API#:49-005-07635, SEO#: P177448.0W
8. Timar Stock Well T50N R80W Sec. 6 SENE Surface Owner and Contact information: Bureau of Land Management
a. Stock Water Well
9. Coal Gulch MW T51N R78W Sec. 26 SWSW
Surface owner and contact info: Bureau of Land Management
a. Coal Gulch MW Dual Completion
API#:49-019-24209, SEO#: P159720.0W
10. Petrified Tree MW T51N R80W Sec. 31 SWNE
Surface Owner & Contact Information: Bureau of Land Management
a. Petrified Tree MW
11. Remington MW T58N R79W Sec. 30 SWNE Surface owner and contact info: Padlock Ranch Inc., Contact: Trey Patterson 307- 655-2264
a. Remington 30-07A
API#:49-033-23127, SEO#:P139658.0W
b. Remington 30-07CK
API#:49-033-23107, SEO#:P139652.0W
c. Remington 30-07C
API#:49-033-23126, SEO#:P139649.0W
12. Ford Ranch II POD T58N R75W Sec. 27, 32 Ford Ranch Trust Representative & Contact: Ryan Fieldgrove 307-684-2211
a. Ford Ranch II Fed 13CW-32
API#:49-005-59912,
b. Ford Ranch Playa Outfall
Prescription All Wells:
A. BLM makes no guarantee of the condition of the wellbore. Contractor may encounter tubing, airlines, wire, pumps, and other related well equipment in wellbore.
B. Contractor shall pull all tubing, airlines, wire, pumps, and all related well equipment from wellbore, if present.
C. Contractor shall haul all tubing pulled from the wellbores on BLM surface and transport the tubing to the BLM Welch Ranch property, and unload/stack the tubing at the Welch Ranch Property. Legal location is as follows T57N R84W Sec. 1
SWNE.
D. Bentonite chips shall be poured into the wellbore in manner that keeps the potential for bridging at a minimum. Contractor shall pour bentonite chips into the wellbore across a coarse mesh screen to prevent bridging. Pour rate shall be no less than 3 minutes per 50-pound bag of bentonite.
E. Plugging rig shall have the ability to retrieve tension set packers set at up to 30,000 pounds of tension.
F. If packer does not release from wellbore, contractor may have to mill out packer/tubing to get to prescribed plugging depth.
G. Bit and scraper shall be run on a tubing work string for all steel cased wells. No bit and scraper shall be ran in PVC cased wells.
H. Plug the wellbores per the provided plugging specifications and reclaim all disturbed surfaces per the provided reclamation plan.
I. All displaced fluids shall be captured and transported to a Wyoming DEQ approved Produced Water Disposal & Treatment facility.
J. An earthen pit may be excavated to capture any cement circulated to surface and to clean cementing equipment.
K. If the casing test fails or no test is conducted, all balanced plugs shall be tagged after a minimum wait on cement time of 4 hours. A casing test shall consist of pressuring up casing to 500 pounds per square inch (psi) for 30 minutes with no more than a 10% bleed off in pressure. This casing test applies for steel cased wells only.
L. Contractor shall have cementing equipment capable of operating in an inner diameter annulus 4 inches and greater.
M. Cement wait time shall be at least 4 hours.
N. If a cement plug or grout plug is tagged below the prescribed depth, remedial cementing or grouting shall occur until cement or grout plug can be tagged at prescribed depth.
O. Bentonite Grout Slurry: means an inorganic mixture of a minimum 20 percent by weight solids bentonite, with polymers, water, or other additives for the yield/rate control, which forms a low permeability seal (not greater than 1 x 10^-7 centimeters/second) and is mixed to the manufacturer’s specifications.
P. Tremie pipe (grout pipe) – A small diameter conductor pipe, hose or tubing used in down hole placement of well construction material (cement, grout mixture, gravel pack, etc.).
Q. Non-Slurry bentonite grouts must be in place before significant hydration occurs.
R. Water used for plugging operations shall be from a municipal source.
S. Contractor shall remove all infrastructure on the pad then re-seed the disturbed areas with BLM seed mix in figure 1.
T. Removal of pipe: Excavate approximately 3 to 5 feet deep, cut pipe from valve or riser (typically up to 2 inch or 3-inch diameter and black HDPE), fuse cap to existing pipe, remove and dispose of valve, backfill with existing material and compact in one-foot lifts. Valve sets may be up to 8-inch diameter.
U. Strip 6 inches of topsoil from a 10-foot radius around the well head and store in a pile adjacent to the work site for final reclamation. Excavate around the well casing to a depth adequate to cut and cap the well casing a minimum of 3 feet below ground surface.
V. Contractor shall supply and erect identification markers on all wells in this contract.
Permanently weld a well identification marker to the cut off well casing. The well identification marker shall be a metal plate at least ¼-inch thick. The following information shall be permanently placed on the marker by beading-on with a welding torch or engraving: 1) BLM 2) Lease serial number, 3) well name and number 4) legal location – Qtr/Qtr Section TXXN, RXXW. Bury the marker with native material. This applies to all wells except Skewed wells. See the part below regarding Skewed wells.
W. All Skewed wells all have 2-inch PVC casing extending to total depth. Cemented inside a 5-inch steel casing that is set approximately 6 feet into the ground.
Contractor shall pull 5-inch steel casing, cut 2-inch PVC casing at pull depth, and fill the resultant hole with native material.
1. Durham Ranch 14 MW T45N R71W Sec. 6 SWNE
a. Durham Ranch Wyodak Coal -This well has 5.5-inch outer diameter steel casing set at 720 feet and cemented to surface. This well was drilled to a TD (Total depth) of 820 feet with at 9.875-inch drill bit. Casing pound per foot weight is unknow. Contractor will have to measure casing inner diameter to ensure proper down-hole tool sizing.
-Plugging Procedure:
i. Run bit and scraper to 700 feet.
ii. Set CIBP (Cast Iron Bridge Plug) at 695 feet.
iii. Cement from CIBP to surface.
Well Specific Cement Requirements: All cement shall be Class G cement mixed at 13.5+ pounds per gallon (ppg) and shall consist of at least 50% cement by weight.
b. Durham Ranch Wasatch Sand -This well has 5.5-inch outer diameter steel casing set at 720 feet and cemented to surface. This well was drilled to a TD of 820 feet with at 7.875-inch drill bit. Casing pound per foot weight is unknow. Contractor will have to measure casing inner diameter to ensure proper down-hole tool sizing.
-Plugging Procedure:
i. Run bit and scraper to 700 feet.
ii. Set CIBP at 695 feet.
Well Site: There are (2) wells on this location, the Durham Ranch Sec. 14 Wyodak Coal and the Durham Ranch Sec. 14 Wasatch Coal. Both are single completion. All pipes shall be cut and capped at least 3 feet below surface, associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around hut and wooden platform under well hut, well heads, as well as hut and steel culvert.
After the wells are plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with the BLM approved seed mix listed in Figure 1, or surface owner specified seed mix.
See photos in Appendix 1 and maps in Appendix 2.
Access Road: The access is a primitive 2 track off a main dirt road. Any road damage created during plugging will need to be repaired to a condition similar or better than existing.
Specifications
2. Durham Ranch 6 MW T45N R71W Sec. 6 SWNE
a. Durham Ranch Wyodak Coal -This well has 5.5-inch outer diameter steel casing set at 363 feet and cemented to surface. Casing pound per foot weight is unknow. Contractor will have to measure casing inner diameter to ensure proper down-hole tool sizing.
-Plugging Procedure:
i. Run bit and scraper to 343 feet.
ii. Set CIBP at 338 feet.
b. Durham Ranch Wasatch Sand -This well has 5.5-inch outer diameter steel casing set at 285 feet and cemented to surface. Casing pound per foot weight is unknow. Contractor will have to measure casing inner diameter to ensure proper down-hole tool sizing.
-Plugging Procedure:
i. Run bit and scraper to 265feet.
ii. Set CIBP at 260 feet.
Well Site: There are (2) wells on this location, the Durham Ranch Sec. 6 Wyodak Coal and the Durham Ranch Sec. 6 Wasatch Coal. Both are single completion. All pipes shall be cut and capped at least 3 feet below surface, associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around hut and wooden platform under well hut, well heads, as well as hut and steel culvert.
After the wells are plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with the BLM approved seed mix listed in Figure 1, or surface owner specified seed mix.
See photos in Appendix 1 and maps in Appendix 2.
Access Road: The access is a primitive 2 track off a scoria road. Any road damage created during plugging will need to be repaired to a condition similar or better than
3. Kingsbury MW T46N R78W Sec. 25 NWSE
a. KU 33-25-4678S-MON
- This well has 7-inch, 20 pound per foot steel production casing set at 1644 feet. The production casing is cemented to surface. The surface casing is set at 167 feet and cemented to surface.
- Plugging procedure:
i. Pull 2.375-inch tubing and packer set at 1452 feet.
ii. Run bit and scraper to 1457 feet.
iii. Set CIBP at 1562 feet.
iv. Place 15 feet of cement on top of CIBP.
v. Set CIBP at 1521 feet.
vi. Place 90 feet of cement on top of CIBP.
vii. Set CIBP at 1405 feet.
viii. Place 80 feet of cement on top of CIBP.
ix. Set CIBP at 1248 feet.
x. Place 240 feet on top of CIBP.
xi. Cement from 260 feet to surface
Well Specific Tubing Requirements: All tubing pulled from this well shall be transported to BLM Welch Ranch Property.
Well Site: There is 1 well on this location, KU 33-25-4578S-MON which is a dual completion. No reclamation will need to be done on this location See photos in Appendix 1 and maps in Appendix 2.
Access Road: The access is a faint 2 track off a gravel county road. Any road damage
4. Napier MW T48N R76W Sec. 24 SWSE
a. Napier MW Big George
- This well has a 7-inch diameter, 20 pound per foot steel production casing is set at 1587 feet and is cemented to surface. Surface casing is set at 166 feet and cemented to surface.
-Plugging procedure:
i. Run bit and scraper to 1542 feet.
ii. Set CIBP at 1537
iii. Cement from CIBP to surface.
Well Specific Cement Requirements: All cement shall be Class G cement mixed at 13.5+ pounds per gallon (ppg) and shall consist of at least 50% cement by weight.
b. Napier MW Wasatch
- This well has a 7-inch diameter, 20 pound per foot steel production casing is set at 1530 feet and is cemented to surface. Surface casing is set at 165 feet and cemented to surface.
-Plugging procedure:
i. Run bit and scraper to 1415 feet.
ii. Set CIBP at 1410 feet.
iii. Place 100 feet of cement on top of CIBP.
iv. Place a balanced cement plug from 1260 feet to 1120 feet.
v. Place a cement plug from 215 feet to surface
Well Specific Cement Requirements: All cement shall be Class G cement mixed at 13.5+ pounds per gallon (ppg) and shall consist of at least 50% cement by weight.
Well Site: There are 2 wells on this location. Napier MW Big George and Napier MW Wasatch. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around hut, hut and well heads, as well as steel culverts surrounding wellheads.
After the wells are plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with the BLM approved seed mix listed in Figure 1.
See photos in Appendix 1 and maps in Appendix 2.
Access Road: The location is an eyebrow off main county road. Any damage created during plugging will need to be repaired to a condition similar or better than existing.
5. Skewed MW’s T48N R77W Sec. 21 SENW
Plug Only
a. SK1 MW
- This well has as 2-inch PVC casing set to a TD of 25.34 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
b. SK2S MW
- This well has as 2-inch PVC casing set to a TD of 38.88 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
c. SK2D MW
- This well has as 2-inch PVC casing set to a TD of 55.56 feet.
- Plugging procedure:
iv. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
d. SK3 MW
- This well has as 2-inch PVC casing set to a TD of 124.34 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
e. SK4S MW
- This well has as 2-inch PVC casing set to a TD of 22.40 feet.
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
f. SK4D MW
- This well has as 2-inch PVC casing set to a TD of 63.16 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
g. SK5 MW
- This well has as 2-inch PVC casing set to a TD of 29.80 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
h. SK6 MW
- This well has as 2-inch PVC casing set to a TD of 26.18 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
i. SK7 MW
- This well has as 2-inch PVC casing set to a TD of 38.39 feet.
- Plugging procedure:
varieties that are hydrated to manufacturer’s specifications.
j. SK8 MW
- This well has as 2-inch PVC casing set to a TD of 27.12 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
k. SK9 MW
- This well has as 2-inch PVC casing set to a TD of 30.86 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications
l. SK10 MW
- This well has as 2-inch PVC casing set to a TD of 39.21 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
m. SK11 MW
- This well has as 2-inch PVC casing set to a TD of 34.87 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
Well Site: There are 13 wells on this location, the Skewed MWs are all single completions.
See photos in Appendix 1 and maps in Appendix 2.
Access Road: The access is a 2 track off a main gravel road. Any road damage created during plugging will need to be repaired to a condition similar or better than existing.
5. Skewed MW’s T48N R77W Sec. 21 SENW
a. SK12 MW
- This well has as 2-inch PVC casing set to a TD of 42.47 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
b. SK13 MW
- This well has as 2-inch PVC casing set to a TD of 37.41 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
c. SK14 MW
- This well has as 2-inch PVC casing set to a TD of 41.50 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
d. SK15 MW
- This well has as 2-inch PVC casing set to a TD of 45.89 feet.
- Plugging procedure:
e. SK16 MW
- This well has as 2-inch PVC casing set to a TD of 41.28 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
f. SK17 MW
- This well has as 2-inch PVC casing set to a TD of 28.21 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
g. SKS18 MW
- This well has as 2-inch PVC casing set to a TD of 77.40 feet.
- Plugging procedure:
i. Place non-slurry bentonite grout from TD to surface.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
Well Site: The entire area will need to be reseeding after plugging procedures are complete. See Figure 2 for instructions and seed mix, consult landowner for private land seed mix.
Well SK12 is a poison well, the concrete and steel posts that are surrounding the well need to be removed and hauled to an approved disposal facility.
See photos in Appendix 1 and maps in Appendix 2.
Access Road: The access is a 2 track off a main gravel road. Any road damage
6. Sasquatch MW T48N R78W Sec. 26 NWSE
a. Sasquatch MW
-This well has 7.625-inch, 26.4 pound per foot steel production casing set at 1425 feet.
-This well has a TVD of 1595 feet.
-Plugging Procedure:
i. Pull 2.875 inch tubing set at 1536 feet.
ii. Run bit and scraper to 1380 feet.
iii. Set CIBP at 1375 feet.
iv. Place 100 feet of cement on top of CIBP.
v. Place a balanced cement plug from 1022 feet to 912 feet.
vi. Place a balanced cement plug from 817 feet to 700 feet.
vii. Place a cement plug from 250 feet to surface.
Well Specific Tubing Requirements: All tubing pulled from this well shall be transported to BLM Welch Ranch Property.
Well Site: There is 1 well on this location, the Sasquatch MW. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around location, Ag storage tank, outfall, well head, stock tank remove concrete in the middle of stock tank, as well as reclaim the pit adjacent.
After the well is plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with the BLM approved seed mix listed in Figure 1. See photos in Appendix 1 and maps in Appendix 2.
Access Road: Access is off a main gravel road, any road damage created during plugging will need to be repaired to a condition similar or better than existing. The access off the main road will need to be ripped 18-24 inches and seeded after plugging operations.
7. Carr Draw MW T50N R75W Sec. 29 NENE
a. Carr Draw MW Gates/Werner Coals
- The 7-inch diameter, 20 pound per foot steel production casing is set at 1412 ft and is cemented to surface.
- Plugging procedure:
i. Pull 2.375-inch tubing and packer set at 851 feet.
ii. Run bit and scraper to 1367 feet.
iii. Set CIBP at 1362 feet
iv. Place 100 feet of cement on top of CIBP
v. Place a balanced cement plug from 1260 feet to 1150 feet.
vi. Set a CIBP at 696 feet.
vii. Place 100 feet of cement on top of CIBP.
viii. Cement from 270 feet to surface
Well Specific Cement Requirements: All cement shall be Class G cement mixed at 13.5+ pounds per gallon (ppg) and shall consist of at least 50% cement by weight.
Well Specific Tubing Requirements: All tubing pulled from this well shall be stacked and left on location.
b. Carr Draw MW OB/BG Coals The 7-inch diameter, 20 pound per foot steel production casing is set at 1934 feet and is cemented to surface.
- Plugging procedure:
i. Pull 2.375-inch tubing and packer set at 1865 feet.
ii. Run bit and scraper to 1889 feet.
iii. Set CIBP at 1884 feet.
iv. Place 50 feet of cement on top of CIBP.
v. Set CIBP at 1740 feet.
vi. Place 150 feet of cement on top of CIBP.
vii. Place a balanced cement plug from 1520 feet to 1350 feet.
viii. Place a balanced cement plug from 1250 feet to 1140 feet.
ix. Place a balanced cement plug from 730 feet to 600 feet.
x. Cement from 272 feet to surface
Well Specific Cement Requirements: All cement shall be Class G cement mixed at 13.5+ pounds per gallon (ppg) and shall consist of at least 50% cement by weight.
Well Specific Tubing Requirements: All tubing pulled from this well shall be stacked and left on location.
Well Site: There are 3 well locations on this site, 1 well is a dual completion and 2 are single completions. The Carr Draw MW Big George/Wasatch and Carr Draw MW Gates/Werner. The Big George well is High Pressure. All pipes shall be cut and capped at least 3 feet below surface, associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around huts, steel culverts, well heads, as well as the 3 well huts. Fencing and well huts shall be stacked and left on location.
After the well is plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with the BLM approved seed mix listed in Figure 1, or surface owner specified seed mix.
See photos in Appendix 1 and maps in Appendix 2.
Access Road: The access to this location is an established 2 track, turning into a primitive 2 track accessing the location. The road will need to be ripped 18-24 inches and seeded after plugging operations.
8. Timar Stock well T50N R80W Sec. 6 SENE
a. Timar Stock well
- This well has a 6.625-inch diameter steel casing set to approximately 150 feet TD.
There should be 3.5-inch tubing remaining in the wellbore.
-Plugging procedure:
i. Pull all rods and 3.5-inch tubing from wellbore.
ii. Place bentonite from TD to surface.
TD is estimated to be 150 feet. BLM will reimburse contractor for time and materials that exceed the volume to plug 150 feet of wellbore.
Well Specific Grout requirements:
1. Non-slurry Bentonite Grout must consist of chipped or pelletized bentonite varieties that are hydrated to manufacturer’s specifications.
Well Specific Tubing Requirements: All tubing pulled from this well shall be transported to BLM Welch Ranch Property.
Well Site: There is 1 well on this location, the Timar Stock well. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to well head, remove concrete.
After the well is plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with the BLM approved seed mix listed in Figure 1. See photos in Appendix 1 and maps in Appendix 2.
Access Road: Access is a faint 2 track off a county road. The access off the main road will need to be seeded after plugging operations.
9. Coal Gulch MW T51N R78W Sec. 26 SWSW
a. Coal Gulch MW
- This well has a 7-inch diameter, 20 pounds per foot steel production casing set at 1970 feet, cemented to surface. The surface casing is set at 250 feet and cemented to surface.
- Plugging procedure:
i. Pull 2.375-inch short string tubing at 1511 feet length
ii. Pull 2.375-inch tubing and packer set at 1548 feet.
iii. Run bit and scraper to 1756 feet.
iv. Set CIBP at 1751 feet.
v. Place 50 feet of cement on top of CIBP.
vi. Set CIBP at 1432 feet
vii. Place 100 feet of cement on top of CIBP
viii. Cement from 300 feet to surface.
Well Specific Tubing Requirements: All tubing pulled from this well shall be transported to BLM Welch Ranch Property.
Well Site: There is 1 well on this location, Coal Gulch MW which is a dual completion, under high pressure gas. All pipes shall be cut and capped at least 3 feet below surface, associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around huts and wooden platform under well hut, well head as well as huts.
After the well is plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with the BLM approved seed mix listed in Figure 1.
See photos in Appendix 1 and maps in Appendix 2.
Access Road: The access is a faint 2 track off a gravel road. The access will need to be ripped 18-24 inches and seeded after plugging operations.
10. Petrified Tree MW T51N R80W Sec. 31 SWNE
a. Petrified Tree MW This well has a 3.5-inch steel casing set to a TD of approximately 100 feet.
-Plugging Procedure:
i. Pull any rods or tubing from wellbore.
ii. Place a bentonite grout slurry from total depth to surface
TD is estimated to be 100 feet. BLM will reimburse contractor for time and materials that exceed the volume to plug 100 feet of wellbore.
Bentonite Grout Slurry: shall be pumped via tremie pipe by positive displacement or similar method (pressure grouted) from the bottom of the well to the surface such that an uninterrupted seal may be emplaced to the land surface.
Well Site: There is 1 well on this location. Petrified Tree MW. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to the well head.
After the well is plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with BLM approved seed mix listed in Figure 1.
See photo’s in Appendix 1 and maps in Appendix 2.
Access Road: Access is off main 2 track and has already been reclaimed. Any damage created during plugging will need to be repaired to a condition similar or better than existing.
11. Remington MW T58N R79W Sec. 30 SWNE
a. Remington 30-07A
- This well has a 7-inch diameter, 17 pound per foot steel production casing set at 314 feet and cemented to surface. The surface casing is set at 60 feet and cemented to surface.
- Plugging procedure:
i. Run bit and scraper to 269 feet.
ii. Set CIBP at 264 feet.
iii. Cement from 264 feet to surface.
Well Specific Cement Requirements: All cement shall be Class G cement mixed at 13.5+ pounds per gallon (ppg) and shall consist of at least 50% cement by weight.
b. Remington 30-07CK
- This well has a 7-inch diameter, 17 pound per foot steel production casing set at 625 feet and cemented to surface. The surface casing is set at 80 feet and cemented to surface.
- Plugging procedure:
i. Run bit and scraper to 580 feet.
ii. Set CIBP at 575 feet.
iii. Place 100 feet of cement on top CIBP.
iv. Cement from 390 feet to surface.
Well Specific Cement Requirements: All cement shall be Class G cement mixed at 13.5+ pounds per gallon (ppg) and shall consist of at least 50% cement by weight.
b. Remington 30-07C
- This well has a 7-inch diameter, 17 pound per foot steel production casing set at 787 feet and cemented to surface. The surface casing is set at 87 feet and cemented to surface.
i. Run bit and scraper to 792 feet.
ii. Set CIBP at 737 feet.
iii. Place 160 feet of cement on top CIBP.
iv. Cement from 390 feet to surface.
Well Specific Cement Requirements: All cement shall be Class G cement mixed at 13.5+ pounds per gallon (ppg) and shall consist of at least 50% cement by weight.
Well Site: There are 3 wells on this location, the Remington 30-07A, Remington 30- 07CK and the Remington 30-07C. All pipes shall be cut and capped at least 3 feet below surface, associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around huts well head, as well as the 4 well huts and the power drop and all related infrastructure.
After the well is plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with the BLM approved seed mix listed in Figure 1, or surface owner specified seed mix.
See photos in Appendix 1 and maps in Appendix 2.
Access Road: The access road is a faint 2 track coming off a main ranch road. The road will need to be ripped 18-24 inches and seeded after plugging operations.
12. Ford Ranch II Fed POD T58N R75W Secs. 27, 32
a. Ford Ranch II Fed 13CW-32 T58N R75W Sec. 32 SWSW
Plugging, Removal and Reclamation.
Well Description-This well has 8.625-inch outer diameter steel casing set at 60 feet and cemented to surface. The production casing is 5.5 inches in outer diameter and weighs 15.5 pounds per foot. The production casing is set at a depth of 400 feet.
-Plugging Procedure:
i. Run bit and scraper to 225 feet.
ii. Set CIBP (Cast Iron Bridge Plug) at 220 feet.
iii. Place 50 feet of cement on top of CIBP.
iv. Set second CIBP at 140 feet.
v. Place 50 feet of cement on top of CIBP.
vi. Set third CIBP at 50 feet.
vii. Cement from CIBP to surface.
Well Site: There is 1 well on this location. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to the well head.
After the well is plugged and associated infrastructure is removed, the disturbed area will be broadcast seeded with BLM approved seed mix listed in Figure 1.
See photos in Appendix 1 and maps in Appendix 2.
b. Ford Ranch Playa Outfall T58N R75W Sec. 27 SWNE Playa Outfall Description- Outfall consists of a black poly apron and partially buried black poly corrugated pipe (14” diameter by 100 feet). Large black poly corrugated riser (48” diameter) and a valve set within a 12” smooth poly riser. Riser caps and (2) wooden posts. Access Road to the Playa outfall may require spot upgrades due to erosion in several spots. See Figure 6 Photos.
-Removal and Reclamation Procedure:
A. Contractor shall remove all infrastructure associated with the outfall and recontour to the surrounding topography then re-seed the disturbed areas with BLM seed mix specified in the attached reclamation plan.
B. Removal of pipe: Excavate approximately 3 to 5 feet deep, cut pipe from valve or riser (typically up to 2 inch or 3-inch diameter and black HDPE), fuse cap to existing pipe, remove and dispose of valve, backfill with existing material, and compact in one-foot lifts. Valve sets may be up to 8-inch diameter.
C. Electrical panels – Contractor shall be responsible for locates, verifying conductors are “dead”, excavating approximately 3-feet deep, cutting the wires, backfilling with existing materials, compacting in one-foot lifts.
D. Strip 6 inches of topsoil from a 10-foot radius around the disturbance and store in a pile adjacent to the work site for final reclamation. Excavate around any removed infrastructure to a depth adequate to cut and cap any piping a minimum of 3 feet below ground surface.
Access Road: May require spot upgrade to perform the work. Will not be reclaimed.
Other Notes
Project Contacts Zach Nicholson Project Inspector Office: 307-684-1160
Zach Nicholson Contracting Officer Representative Office: 307-684-1160
Freise, Casey B Need to add from Ford Ranch SOW
Freise, Casey B Need to add from Ford Ranch SOW
Freise, Casey B Haul to where
Cell: 307-670-0163 Email: znicholson@blm.gov
Cell: 307-670-0163 Email: znicholson@blm.gov
FIGURE 1: BLM Approved Seed Mix
Species Common Name PLS lbs/acre Elymus trachycaulus spp. trachycaulus Slender wheatgrass 3.0 Pascopyrum smithii Western Wheatgrass 2.5 Pseudoroegneria spicata ssp. spicata Bluebunch Wheatgrass 1.75 Elymus elymoides Bottlebrush Squirreltail 1.25 Leymus cinerus Basin Wildrye 1.25 Nassella viridula Green Needlegrass 1.0 Calamovifolia longifolia Prairie Sandreed 0.75 Bouteloua dactyloides Sideoats Grama 0.5 Poa Secunda Sandberg Bluegrass 0.15 Festuca saximontana Rocky Mountain Fescue 0.15 Sporobolus contractus Sand Dropseed 0.03 Atriplex canescens Fourwing Saltbush 0.5 Peritoma serrulata Rocky Mountain Beeplant 0.25 Sphaeralcea coccinea Scarlet Globemallow 0.1 Dalea purpurea Purple Prairie Clover 0.2 Artemisia tridentate Wyoming Big Sagebrush 0.1 Triticum aestivum x Secale cereale Quickguard 5.0
Total PLS 18.38 *PLS = pure live seed, Northern Plains adapted species mailto:znicholson@blm.gov mailto:znicholson@blm.gov
FIGURE 2: Reclamation for Skewed well area
Site Description The Skewed Reservoir Reclamation area is located in Johnson County, Wyoming, NWSE Section 21, T48N/R77W; UTMs 410491E/4885436N. It falls within the 10-14-inch Northern Precipitation Zone and a Loamy-Shallow Loamy Ecological Site Description (ESD). The site lies on a south aspect with a slopes ranging from 3-15%.
See photos in Appendix 1 and maps in Appendix 2.
Reseeding Plan Requirements:
-Rip and reseed the reclaimed reservoir location; an area of approximately 7.7 acres.
- Waterbars are to be constructed a minimum of 18 inches deep, on the contour with no more than 2 feet of drop per 100 feet of waterbar to ensure drainage and extended into established vegetation. All waterbars are to be constructed with the berm on the downhill side to prevent the soft material from silting in the trench. The initial waterbar will be constructed at the top of the backslope. See Figures 3 and 4.
-The soil is to be ripped and prepped for seed bed, mulched, and seeded with the seed mix listed below. Mulch and seed are to be from a weed free certified source.
-Drill seed at a depth not to exceed 0.5 inches. If broadcast seeding, double the rate of application.
-Apply mulch at a minimum rate of 1000 pounds per acre. Mulch maybe wood chips or straw.
-Apply seed at the specified rate. See FIGURE 1 BLM approved seed mix.
Area to be seeded with instructions highlighted in green
Figure 3. Water Bar Diagram
Figure 4. Water Bar Example
Field Office: Buffalo Field Office (BFO)
Appendix 1: Access and Location Photos Durham Ranch 14 MW’s Access
Durham Ranch 14 Well location
Durham Ranch wells
Durham Ranch 6 MW’s Access
Durham Ranch 6 MW’s Location
Durham Ranch 6 Sand Well
Durham Ranch 6 Coal Well
Kingsbury Location and well
Napier Access
Napier Location
Napier Coal well
Napier Sand well
Skewed Location
Skewed well example
Access for Skewed wells
Concrete and Steel posts need removed
Sasquatch Access
Sasquatch Location
Sasquatch well
Sasquatch Pit
Sasquatch Outfall
Carr Draw Access
Carr Draw Location
Carr Draw Big George Dual Completion
Carr Draw Werner Dual Completion
Timar Stockwell Access
Timar Wellhead
Timar Well
Coal Gulch Access
Coal Gulch Location
Coal Gulch Wellhead
Petrified Tree Access
Petrified Tree Wellhead
Remington Access
Remington Location
Remington Wells
Remington Power Drops
Appendix 2 Maps
| Cover Page_Monitor Wells Plugging.pdf |
| BLM Monitoring Well Plugging |
| Phase III |
| STATEMENT OF WORK & SITE LOCATION |
| BUFFALO FIELD OFFICE |
| HIGH PLAINS DISTRICT OFFICE |
| SOW_BLM_Monitor_Wells_Plugging Ph 3 & Ford Orphan Final.pdf |
| Well Site: There are (2) wells on this location, the Durham Ranch Sec. 14 Wyodak Coal and the Durham Ranch Sec. 14 Wasatch Coal. Both are single completion. All pipes shall be cut and capped at least 3 feet below surface, associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around hut and wooden platform under well hut, well heads, as well as hut and steel culvert. |
| Access Road: The access is a primitive 2 track off a main dirt road. Any road damage created during plugging will need to be repaired to a condition similar or better than existing. |
| Well Site: There are (2) wells on this location, the Durham Ranch Sec. 6 Wyodak Coal and the Durham Ranch Sec. 6 Wasatch Coal. Both are single completion. All pipes shall be cut and capped at least 3 feet below surface, associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around hut and wooden platform under well hut, well heads, as well as hut and steel culvert. |
| Access Road: The access is a primitive 2 track off a scoria road. Any road damage created during plugging will need to be repaired to a condition similar or better than existing. |
| Well Specific Tubing Requirements: All tubing pulled from this well shall be transported to BLM Welch Ranch Property. |
| Well Site: There is 1 well on this location, KU 33-25-4578S-MON which is a dual completion. No reclamation will need to be done on this location |
| Access Road: The access is a faint 2 track off a gravel county road. Any road damage created during plugging will need to be repaired to a condition similar or better than existing. |
| Well Site: There are 2 wells on this location. Napier MW Big George and Napier MW Wasatch. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around hut, hut and well heads, as well as steel culverts surrounding wellheads. |
| Access Road: The location is an eyebrow off main county road. Any damage created during plugging will need to be repaired to a condition similar or better than existing. |
| Well Site: There are 13 wells on this location, the Skewed MWs are all single completions. |
| Access Road: The access is a 2 track off a main gravel road. Any road damage created during plugging will need to be repaired to a condition similar or better than existing. |
| Well Site: The entire area will need to be reseeding after plugging procedures are complete. See Figure 2 for instructions and seed mix, consult landowner for private land seed mix. |
| Well SK12 is a poison well, the concrete and steel posts that are surrounding the well need to be removed and hauled to an approved disposal facility. |
| Access Road: The access is a 2 track off a main gravel road. Any road damage created during plugging will need to be repaired to a condition similar or better than existing. |
| Well Site: There is 1 well on this location, the Sasquatch MW. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around location, Ag storage tank, outfall, well head, stock tank remove concrete in the middle of stock tank, as well as reclaim the pit adjacent. |
| Access Road: Access is off a main gravel road, any road damage created during plugging will need to be repaired to a condition similar or better than existing. The access off the main road will need to be ripped 18-24 inches and seeded after plugging operations. |
| Access Road: The access to this location is an established 2 track, turning into a primitive 2 track accessing the location. The road will need to be ripped 18-24 inches and seeded after plugging operations. |
| Well Specific Tubing Requirements: All tubing pulled from this well shall be transported to BLM Welch Ranch Property. |
| Well Site: There is 1 well on this location, the Timar Stock well. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to well head, remove concrete. |
| Access Road: Access is a faint 2 track off a county road. The access off the main road will need to be seeded after plugging operations. |
| Well Specific Tubing Requirements: All tubing pulled from this well shall be transported to BLM Welch Ranch Property. |
| Well Site: There is 1 well on this location, Coal Gulch MW which is a dual completion, under high pressure gas. All pipes shall be cut and capped at least 3 feet below surface, associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around huts and wooden platform under well hut, well head as well as huts. |
| Access Road: The access is a faint 2 track off a gravel road. The access will need to be ripped 18-24 inches and seeded after plugging operations. |
| Well Site: There is 1 well on this location. Petrified Tree MW. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to the well head. |
| Well Site: There are 3 wells on this location, the Remington 30-07A, Remington 30-07CK and the Remington 30-07C. All pipes shall be cut and capped at least 3 feet below surface, associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to fencing around huts well head, as well as the 4 well huts and the power drop and all related infrastructure. |
| Access Road: The access road is a faint 2 track coming off a main ranch road. The road will need to be ripped 18-24 inches and seeded after plugging operations. |
| Well Site: There is 1 well on this location. All pipes shall be cut and capped at least 3 feet below surface. All associated infrastructure shall be removed and hauled to an approved facility or storage area. Associated infrastructure includes but not limited to the well head. |