Attachment 1 Statement of Work.pdf

PDF 202 KB Posted

Attached to
Proposal for Recreation Center Renovation-Electrical Installation Work
Solicitation number
PR15989094
Issued by

About this file

This is a Statement of Work (SOW) for electrical installation works on a Recreation Center Renovation Project – Phase III, Solicitation No. 19CE2026Q0008.

The contractor must provide complete modification, supply, installation, wiring, testing, and commissioning of electrical power and lighting systems for the Clubhouse, Tool Store, Security Office/Guard House, Generator Room, and associated external and service areas. All cable trays and trunking must be Zn-Al powder coated with minimum 100-micron coating thickness, use only factory-fabricated fittings (site-modified fittings prohibited), and include HDG support systems with 2.5 sq.mm Cu/PVC earth conductor bonding at all joints. All conduits and accessories must be Low Smoke Zero Halogen (LSZH) with cables rated minimum 500/750V, proper color coding, and voltage drop compliance with latest NEC limits. Third-party inspection and certification by a licensed/authority-approved electrical engineer is mandatory.

The electrical distribution system includes modifying panels SDB-CL, MDB-TL, and SDB-SC, and installing new VRV/VRF Power Panel SDB-AC. Main power cabling runs from MDB-TL to SDB-CL and SDB-AC using 4C x 16 sq.mm Cu/XLPE/LSZH plus 16 sq.mm earth. Lighting fixtures required include seven specific types (DL1, DL2, TB1, SP1, LS1, WL1, ST1) all DALI-2 certified or KNX compatible, fully integrated with Lutron Athena/KNX systems. Socket outlets must include IP65 flip-cover 13A sockets in kitchens/washrooms, floor boxes (OBO Bettermann equivalent), and 16A IP66 interlocked industrial sockets. Circuit wiring specifications include 2 x 1C 1.5 sq.mm Cu/XLPE/LSZH for lighting and 2C x 2.5 sq.mm plus earth for 13A and industrial socket circuits. The contractor must supply, install, test, program, and commission complete lighting control systems with panels, keypads, actuators, and control cabling. Testing and commissioning must include insulation resistance, continuity, and functional testing of power, lighting, and control systems. Deliverables include shop drawings, material submittals, method statements, as-built drawings, and O&M manuals. The contractor must perform all builder's works including openings, chasing, masonry, and finishing, and execute complete installations in the Generator Room, Tool Room, and Guard House/Security Room, with any additional related work to meet functional requirements within 5% of total cost to be borne by the vendor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1 Statement of Work

Solicitation No. 19CE2026Q0008

P a g e 1 | 9

STATEMENT OF WORK (SOW)

ELECTRICAL INSTALLATION WORKS – RECREATION CENTER RENOVATION

PROJECT- PHASE III

1. PROJECT DESCRIPTION

This project comprises the modification, supply, installation, wiring, testing, and commissioning of the electrical power and lighting systems for the following areas:

• Clubhouse

• Tool Store

• Security Office / Guard House

• Generator Room

• Associated external and service areas

The work includes complete system integration, including lighting, power distribution, control systems, and associated infrastructure.

2. GENERAL TECHNICAL REQUIREMENTS (MANDATORY – FROM BOQ NOTES)

The Contractor shall strictly comply with the following:

2.1 Cable Management & Containment

• All cable trays/trunking shall be:

o Zn-Al powder coated o Minimum coating thickness: 100 microns

• Only factory-fabricated fittings shall be used o Site-modified fittings are strictly prohibited

• Provide HDG (Hot Dip Galvanized) support systems

• All tray/trunking joints shall be bonded using:

o 2.5 sq.mm Cu/PVC earth conductor

P a g e 2 | 9

2.2 Wiring System

• All conduits and accessories shall be:

o Low Smoke Zero Halogen (LSZH)

• All cables:

o Minimum insulation rating: 500/750V

• Provide:

o Proper color coding and identification labeling system

• Voltage drop:

o Must comply with latest wiring regulations / NEC limits

2.3 Compliance & Certification

• Contractor shall:

o Arrange third-party inspection and certification o Certification shall be by licensed/authority-approved electrical engineer

• Panel sizing:

o Must be coordinated with actual site space constraints

3. ELECTRICAL DISTRIBUTION SYSTEM

3.1 Panel Boards (Supply / Modification)

The Contractor shall supply, install, and modify the following panels:

Locations & Scope

• Clubhouse o Modify: SDB-CL

• Clubhouse (AC System) o New: SDB-AC (VRV/VRF Power Panel)

• Tool Store Area o Modify: MDB-TL

P a g e 3 | 9

• Security Office o Modify: SDB-SC

Scope Includes

• Additional breakers

• Internal wiring modifications

• Busbars, terminals, accessories

• Complete compliance with schematic diagrams

3.2 Main Power Cabling

Cable Runs

• MDB-TL → SDB-CL

• MDB-TL → SDB-AC

Cable Specification

• 4C x 16 sq.mm Cu/XLPE/LSZH + 16 sq.mm Earth

Scope Includes

• Supply, laying, termination

• Glands, lugs, sleeves

• Identification tagging

• Installation via tray/conduit

4. ELECTRICAL FITTINGS & LIGHTING SYSTEM

4.1 General Requirements

• All lighting fixtures:

o Supplied with drivers and controllers o Driver enclosures included in rate

• Installation shall include:

o Brackets, supports, chains, threaded rods

P a g e 4 | 9

• Architect approval required prior to installation (mandatory)

4.2 Lighting Control Compatibility

All fixtures and drivers shall:

• Be DALI-2 certified OR KNX compatible

• Fully integrate with:

o Lutron Athena / KNX system

• Support:

o Digital addressing o Flicker-free dimming o Status monitoring

4.3 Lighting Fixtures (Exact BOQ Types)

Provide complete supply and installation of:

• DL1 – recessed LED downlight (16W, 3000K, IP44)

• DL2 – recessed LED downlight (11W, IP20)

• TB1 – weatherproof luminaire (IP66)

• SP1 – RGBW spotlight (DMX512)

• LS1 – suspended LED strip system with aluminum frame

• WL1 – wall light (IP65)

• ST1 – step light (IP65)

(All fixtures include full accessories, wiring, supports, and drivers)

P a g e 5 | 9

4.4 Socket Outlets & Accessories

General

• All 13A sockets in kitchen/washroom:

o IP65 with flip cover

Items Included

• Floor boxes (OBO Bettermann or equivalent)

• Industrial sockets (16A, IP66, interlocked)

• Standard 13A switched sockets (BS 1363 compliant)

Scope Includes

• Back boxes

• Plates

• Internal wiring

• Fixing accessories

4.5 Isolators & Devices

• 40A, 4P isolator

• 63A, 4P isolator

4.6 Sensors

• Ceiling-mounted motion/presence sensors:

o 360° coverage o 8m detection radius

5. WIRING INSTALLATION (CRITICAL – FULL BOQ COVERAGE)

5.1 General Wiring Scope

Rates shall include ALL components required for a complete installation, including:

• Cables

P a g e 6 | 9

• Switches

• Junction boxes

• Outlet boxes

• LSZH conduits

• Pull boxes

• Clips, supports

• Earth wires

• Draw wires

• Screws, fixing hardware

• Cutting, chasing, making good

• Ceiling boxes and flexible cords

5.2 Circuit Wiring

Lighting

• 2 x 1C 1.5 sq.mm Cu/XLPE/LSZH + Earth

13A Socket Circuits

• 2C x 2.5 sq.mm + Earth

Industrial Socket Circuits

• Same as above (2.5 sq.mm)

Floor Box Circuits

• 2C x 2.5 sq.mm + Earth

6. LIGHTING CONTROL SYSTEM (LUTRON / KNX)

Contractor shall:

• Supply, install, connect, test, program, and commission:

o Lighting control panels o Keypads

P a g e 7 | 9 o Actuators o Control cabling

Scope Includes

• Full system wiring (same inclusions as power wiring)

• Integration with all lighting fixtures

• Final commissioning and programming

7. FEEDER CABLES

• 600/1000V rated Cu/XLPE/LSZH cables

• Installed via tray or LSZH conduit

Includes:

• Termination at both ends

• Glands, lugs, sleeves

• Tray installation

8. CABLE TRAYS / TRUNKING SYSTEMS

• Hot-dip galvanized perforated trays/ladders

• Includes:

o Bends, tees, clamps o Anchor fasteners o Structural supports at regular intervals

Special Installation:

• 100x40mm trunking for lighting system

• Must be compatible with lighting fixtures

9. TESTING & COMMISSIONING

• Full system testing:

P a g e 8 | 9 o Insulation resistance o Continuity o Functional testing

• Final commissioning of:

o Power system o Lighting o Control system

10. PRELIMINARIES

Contractor shall include:

• Shop drawings

• Material submittals & approvals

• Method statements

• As-built drawings

• O&M manuals

• Insurance

• Bank guarantees

• Material storage

11. BUILDER’S WORKS (MANDATORY INCLUSIONS)

Contractor shall allow for:

• Openings in slabs/walls

• Chasing

• Masonry works

• Making good finishes

• Coordination with all trades

P a g e 9 | 9

12. AREA-SPECIFIC WORKS (CRITICAL – FULLY INCLUDED)

The Contractor shall execute complete electrical installations for:

12.1 Generator Room

• Cabling

• Distribution boards

• Lighting

• Power outlets

• Fans and associated services

12.2 Tool Room

• Same full scope as above

12.3 Guard House / Security Room

• Same full scope as above

12.4 General

• All associated works required to fully complete these areas

13. FINAL DELIVERABLE

The Contractor shall provide a fully operational, tested, certified electrical system, including:

• Integrated lighting and control system

• Fully functional power distribution

• Complete installation across all specified areas

• Vendor shall do any other related work to meet the functional electrical system in the full phase of renovation and any changes within the 5% of the total cost to be borne by the vendor