Attachment 1 - Statement of Work.pdf
PDF 172 KB Posted
- Attached to
- Drain Modifications Federal contract opportunity
- Solicitation number
- 1232SA26Q0340
About this file
This is a Statement of Work for the U.S. Department of Agriculture's Eastern Regional Research Center (ERRC) located at 600 East Mermaid Lane, Wyndmoor, Pennsylvania. The project requires the removal of three insulated boxes and installation of nine floor drains in the Mechanical Services Building second-floor laboratory. The work includes coring the concrete floor, installing new flush-to-floor drain assemblies with traps, connecting the new drainage system to existing first-floor overhead piping, correcting non-conforming repairs from historical work, and patching the finished floor to match the existing epoxy finish.
The technical requirements specify that all floor drains and piping must be Flame-Resistant Polypropylene (FRPP) conforming to ASTM D4101 and ASTM F1412, with schedule 40 piping matching existing drain systems. Piping shall be installed in accordance with UFGS 22 00 70 for corrosive waste, with all fittings joined by thermal fusion except hard-piped sink trap assemblies. The contractor must protect the existing epoxy floor from damage during removal operations, submit proposed drain locations for approval prior to coring to avoid structural members, seal all floor and wall penetrations with UL-certified sealant conforming to ASTM E814 Class A, and match the finished floor patch to existing epoxy finishes per UFGS 09 67 23.14. The project must be completed within 180 calendar days during normal business hours (Monday through Friday, 7:30 AM to 3:00 PM), and the contractor must provide a minimum one-year warranty on all materials and labor. Contractors and subcontractors must provide picture identification for visitor badges and are restricted to areas authorized by the Contracting Officer's Representative or Facility Contractor.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30 - Amendment 01.pdf | ||
| Site Visit Sign-In 03312026.pdf | ||
| Site Visit Sign-In 04012026.pdf | ||
| RFIs.pdf | ||
| Attachment 5 - Div 1 Submittal Log.xlsx | XLSX spreadsheet | |
| Attachment 8 - MSB Structural Drawing.pdf | ||
| Attachment 4 - Div 1 General Requirements.pdf | ||
| Attachment 7 - MSB Structural Drawing.pdf | ||
| Attachment 9 - MSB Structural Drawing.pdf | ||
| Attachment 10 - Wage Determination.pdf | ||
| SF1442 - Solicitation Terms and Conditions.pdf | ||
| Attachment 2 - MSB Second Floor Box Demo Dwg.pdf | ||
| Attachment 3 - MSB Drn Instl 2nd Flr.pdf | ||
| Attachment 6 - Project Specific Submittal Log.xlsx | XLSX spreadsheet |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Miscellaneous ERRC Mechanical Services Building drain mods and Equipment removal
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
3.0 Technical Requirements / Tasks
4.0 Deliverables / Schedule
5.0 Security
Project USDA, Eastern Regional Research Center, Wyndmoor, PA, Mechanical Services Building drain mods and Equipment removal
General Information
1.0 Scope of Work
The Eastern Regional Research Center (ERRC), 600 East Mermaid Lane, Wyndmoor Pa requires removal of three (3) insulated boxes and installation of nine (9) floor drains in the Mechanical Services Building (MSB) second floor laboratory. The second-floor drains were removed in 2005 supporting a specific requirement. The piping was capped off at the first-floor overhead level, and the holes in the concrete second-floor were filled. Historical repair work was accomplished with non-conforming materials. The work includes coring the concrete floor, installing new flush to floor drain assemblies and traps, connecting new drain/trap assemblies to existing piping in first floor overhead, correcting non-conforming repairs, and patching the finished floor.
2.0 Background
The Eastern Regional Research Center (ERRC) is one of four Regional Research Centers of the Agricultural Research Service, U.S. Department of Agriculture. The ERRC is home to the nation’s leading scientists and engineers who solve problems facing the U.S. today and tomorrow with fundamental, applied, and developmental research on agricultural commodities.
Most of this research is conducted in the main building within two laboratory wings. The original building was constructed in 1940. Due to continuous upgrades and renovations, ERRC is very modern with respect to laboratory design and system condition.
Contractor Requirements
3.0 Technical Requirements / Tasks
1. The contractor shall provide all labor and materials to remove and properly dispose of three (3) insulated boxes as shown in Attachment 2, MSB second floor box Demo dwg.
The contractor shall protect the existing epoxy floor from damage.
2. The contractor shall provide all labor and materials to install floor drains and piping in accordance with Attachment 3, MSB Drn Instl 2nd Flr. Locations shown in attachment 3 are approximate. The contractor shall verify locations avoid structural members. Contractor proposed drain locations shall be submitted for approval prior to coring. Attachments 7, 8, and 9, structural drawings are provided for reference. The contractor shall also provide all material and labor to replace substandard material identified in attachment 3
3. Floor drains and piping shall be Flame-Resistant Polypropylene (FRPP) conforming to ASTM D4101 and ASTM F1412. Contractor installed piping shall be schedule 40 matching existing drain piping. Floor drains shall be installed flush with floor and shall be provided with a removable grate and sediment strainer. Piping shall be provided and installed IAW UFGS 22 00 70 for corrosive waste. All fittings except hard-piped sink trap assemblies shall be joined by thermal fusion. Mechanical joining or removable fittings shall not be used unless specifically called for in Attachment 3.
4. All Concrete shall be in accordance with UFGS 03 01 00.
5. The contractor shall seal all floor and wall penetrations with UL certified sealant conforming with ASTM E814 Class A.
6. The contractor shall patch finished floor to match existing epoxy finish IAW UFGS 09 67
23.14 and manufacture’s recommendations.
4.0 Deliverables / Schedule
1. The contractor shall provide drains, piping, fittings, and ancillaries necessary to augment the existing drainage system to include the needed additional floor drains.
2. The contractor shall warranty material and labor for a period not less than one year.
3. Project shall be completed during normal business hours, Monday thru Friday, 7:30AM- 3:00PM. The work shall be completed within 180 calendar days.
5.0 Security
1. Contractors and their subcontractors shall provide a picture ID to security at the main lobby before visitor badges are issued, unless a site badge or LincPass has been approved.
2. Contractors and their subcontractors shall be allowed access to only those areas authorized by the Contracting Officer’s Representative (COR) or Facility Contractor.
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| 3.0 Technical Requirements / Tasks |
| 4.0 Deliverables / Schedule |
| 5.0 Security |
File details come from the government source that posted it. Updated .