This Statement of Work (SOW) details a parking lot repair and concrete pad construction project for the USDA Center for Grain and Animal Health Research (CGAHR) in Manhattan, Kansas. The project requires comprehensive parking lot maintenance including cleaning and resealing surface cracks in east and west parking lots, patching asphalt potholes in the west parking lot, repairing concrete driveway entrance holes, and constructing two new concrete pads: one for a liquid nitrogen bulk tank and another for an in-ground mounted bike rack.

The project scope includes specific technical requirements such as removing loose materials, ensuring proper base aggregation, applying new asphalt and concrete, and precise pad construction specifications. The contractor must have skilled road maintenance technicians, provide all necessary materials and equipment, obtain required permits, and complete work within 30 days of starting, contingent on moderate temperatures above freezing. The acquisition is a 100% small business set-aside under NAICS code 237310, with a project magnitude between $25,000 and $100,000. The project will be performed at 1515 College Avenue, Manhattan, KS, 66502, with final inspection and verification by the government's location monitor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Parking Lot Repair and Concrete Pad Construction Project for Center for Grain and Animal Health

Research

USDA Center of Grain and Animal Health and Research

Manhattan, KS. 66502

Project Title: Parking Lot Repair and Concrete Pad Construction Project for Center for Grain and Animal Health Research

1. Government Points of Contact

a) Contracting Officer (CO):

TBD

b) Occupational Health and Safety Representative:

DeQuinn Nickerson 785-776-2733 dequinn.nickerson@usda.gov

c) Engineer Project Manager (EPM):

Mark McWilliams

(970) 631-7513 mark.mcwilliams@ars.usda.gov

d) Contracting Officer’s Representative (COR):

Denise Montgomery

785-776-2738 Denise.Montgomery@usda.gov

e) Location Monitor (LM):

David Hinkson 785-539-5579 david.hinkson@usda.gov mailto:dequinn.nickerson@usda.gov mailto:mark.mcwilliams@ars.usda.gov mailto:Denise.Montgomery@usda.gov mailto:david.hinkson@usda.gov

A. Introduction

The USDA Grain and Animal Health Research Center (CGAHR) at 1515 College Avenue, Manhattan KS, 66502 has a need for the following repairs and construction. All the parking lot surfaces need to have surface cracks in the blacktop cleaned and resealed. The west parking lot has three areas that are damaged and needing repair. In addition, two concrete pads need to be poured: one to hold a liquid nitrogen bulk tank and the other for an in-ground mounted bike rack.

B. Background

The parking lot has been in service for over 50 years. The parking lot was resurfaced in 2011, and in 2014 cracks in the asphalt were cleaned up and resealed. However, new cracks have opened and need to be filled. Several areas have become damaged due to truck activity and need to be restored to their original conditions.

There is a need for additional liquid nitrogen storage capacity for the Insectary and Cell Culture

Laboratory at CGAHR. We will be renting a large bulk tank, but prior to installation of this tank, a concrete pad needs to be installed to support the tank.

The front of CGAHR currently has an old metal bike rack, but it is set on gravel and not attached to the ground. To provide a cleaner look, and better security for visitors and staff that ride their bikes to our location we want to install a concrete pad that will support a 7 foot long in-ground mounted bike rack and provide a flat surface to which people can secure their bikes.

C. Scope

1. The West parking lot has three areas that are needing patched and repaired.

2. The west and east parking lots need all cracks cleaned and resealed.

3. The north concrete driveway entrance area in the west parking lot needs cracks and impressions repaired and sealed.

4. The East front parking lot entrance to the building needs a concrete bicycle rack built.

5. On the side of building #2 we need the asphalt removed and a concrete pad poured fori setting a large nitrogen tank on.

D. An onsite walkthrough is necessary before a bid can be accepted

E. Applicable Documents

Pictures

1. Concrete pad for liquid nitrogen tank

2. Bicycle rack Type

3. First pothole

4. Second and third pothole

5. Driveway north entrance

Drawings

Nitrogen tank pad drawing

Bike rack pad drawing

Acronyms

PSF: Pounds Per Square Foot

OCEW: On Center Each Way

2. Work Requirements

A. Technical Requirements for parking lot repairs

Repairing surface cracks in asphalt parking lot and concrete driveway cracks

1. The contractor shall clean dirt, vegetation and debris out of cracks.

2. The contractor shall seal all cracks in the east and west parking lots with hot melt adhesive bitumen, or suitable substitute concrete or asphalt highway repair filler.

3. The contractor shall dispose of all excess dirt and debris.

4. The contractor shall obtain all required permits.

Patching asphalt potholes in west parking lot

1. The contractor shall remove all loose material from the two locations with potholes.

2. The contractor shall ensure there is an adequate base pad of compacted aggregate in the area being repaired, by removal of material and adding aggregate as needed to provide a solid base layer.

3. The contractor shall lay in 6 inches of new asphalt and pressure roll the asphalt to a smooth surface.

Repairing larger holes in the driveway entrance.

1. The contractor shall remove any damaged, loose and deteriorated concrete from the driveway entrance.

2. The contractor shall clean the area where the loose and damaged concrete was with a pressure washer.

3. The contractor shall fill areas where concrete was removed with a rapid set concrete mix.

4. The contractor shall level and smooth the concrete to match the rest of the concrete on the driveway entrance.

Construct new concrete pad for nitrogen tank

1. The contractor shall build the pad according to the equipment drawings provided with the SOW.

2. The contractor shall setup a 14-foot-long X 14-foot-wide X 8 inches deep (196 PSF) level top equipment pad with 2 ft corner stabilization piers.

3. The contractor shall compact the soil, or use replacement fill, if necessary, soil should be compacted to 2,000 PSF.

4. The contractor shall ensure that 6” aggregate material is used for the pads base.

5. The contractor shall ensure that 6” aggregate material is used under slab footings as well.

6. The contractor shall cover base material with 6 mil polyethylene.

7. The contractor shall reinforce the concrete with a double mat of #4 rebar at 18” OCEW.

8. The contractor shall follow the specifications of the equipment pad drawings.

9. The top of the finished concrete pad should be smooth and level.

Construct new bike rack pad

1. The contractor shall follow the specifications of the 5 ft long bike rack installation drawings.

2. The Contractor shall center the rack with the middle brick post on the south tide of the front entrance.

3. The contractor shall build a perimeter form to hold the wet concrete (72 inches long 24 inches wide, and 12 inches deep).

4. The contractor shall set up government supplied bike rack in center of concrete form.

5. The contractor shall mark the center of each end and dig two 7-inch diameter holes that are 14 inches deep.

6. The contractor shall set two 6-inch ID tubes into the 14 inch long 7-inch holes.

7. The contractor shall fill in around the holes and the rest of the form with 5 inches of sand.

8. The contractor shall preset the bike rack to ensure the bottom of the bike rack loops will be even with the top of the form.

9. The contractor shall fill the form with approximately 7 inches of concrete, or level to the top of the form.

10. The contractor shall trial, and final finish the surface to a level and smooth finish.

11. The contractor shall allow two or three days for the concrete to dry.

12. The contractor shall set the bike rack into the two 6-inch ID tubes.

13. The contractor shall ensure the bottom loops of the bike rack tubes are flush to the concrete.

14. The contractor shall remove some of the sand in the 6-inch tubes to make adjustment.

15. The contractor shall ensure the bike rack is center in the tubes and set the bike rack with rapid set concrete or epoxy.

16. The contractor shall stabilize the bike rack until the concrete or sealer sets up.

Notes for the Contractor

The contractor shall dispose of all excess dirt and debris.

The contractor shall obtain all required permits.

The contractor and onsite monitor shall inspect the overall finish and completion of each repair.

B. Deliverables

1. Before and after pictures will be taken to determine that the repairs meet acceptable standards for the Government. Costs are expected to remain within budget.

2. The location monitor and contractor will complete a final inspection on all construction repairs, and confirm that all the project repairs have been completed and meet all government specifications

3. Supporting Information

A. Required skills and resources

a. Contractor skills

1. The contractor shall have skilled commercial road maintenance class technicians’ series classification levels 1 through 4, Asphalt pavers, milling machine operators, concrete laborer’s and concrete finishers should be performing these repairs.

2. Contractors shall have a business oriented in road maintenance, they should have professional experience in paving roads, drives and parking lots.

b. Contractor Resources

1. The contractor shall provide all materials, parts, tools, and equipment needed to complete this project

2. The contractor shall obtain all necessary permits to perform this work

3. All excess material, dirt, and debris shall be disposed of by the contractor.

4. Contractor shall provide all workers with necessary safety training and proper protective safety equipment (PPE): i.e., gloves, glasses, goggles, respirators, boots, hard hats, and safety straps.

c. Government resources

1. The Government will provide storage areas

2. The Government will provide domestic Water

3. The Government will provide gas and electricity

4. The government will provide washroom facilities

B. Risks Assessment

a. Steam, hot tar, and asphalt burns. 20% highly likely

1. Mitigating factor all Workers should wear protect clothing IE. heavy gloves, long durable work pants, heavy long sleeve work shirts.

2. a safety area shall be secured around all active areas:

ii. Mitigation levels: 5% low risk

b. Silica dust exposure with asphalt and pavement millings.

1. Mitigation with up wind detection, and dust masks

2. Implement Water spraying devices to reduce dust particles.

i. Mitigation levels: 5% low risk

c. High flow traffic areas, 20% highly likely

1. Mitigating with highly visible traffic yellow safety vests or jackets.

2. Secured safety areas with barricades and traffic cones.

3. Road construction signs: road work signs, and speed reduction signs

ii. Mitigation levels: 5% low risk

d. Flying object debris: 10% moderately high.

1. Mitigating with Safety glasses, face shields: 5% low risk.

e. Impact hazard from jack hammers and large heavy machines: 10% moderately high.

Mitigating with impact resistant gloves, heavy durable work boots, safety glasses, hard hats, and face shields: 5% low risk.

C. Security

All contractors will report to the front office and will be screened for illness and citizenship or current work visa. They will be issued a contractor’s identification card once proper credentials have been validated.

D. Place of Performance

The location of the work will be at the USDA Center for Grain and Animal Health Research

(CGAHR), 1515 College Avenue, Manhattan KS., 66502.

E. Period of Performance

These repairs will be as soon as weather permits and completed no later than 30 days after the contractor has started work.

F. Special Considerations

This work should be completed in moderate temperatures above freezing.