Attachment_1_-_Statement_of_Work.pdf

PDF 2 MB Posted

Attached to
LAKE24-0135-WB FUEL LINE REPAIR
Solicitation number
140P8124Q0030
Issued by

About this file

This document is a Statement of Work (SOW) for the repair and replacement of fuel and vault lines at the Willow Beach Marina in the Lake Mead National Recreation Area in Arizona. The SOW outlines the project tasks, which include replacing 170 feet of 2-inch aircraft quality fuel lines and 170 feet of 4-inch double wall access pipe, replacing vault support lines, purging the old and new lines, and performing required testing before the system is put back into operation. The contractor will be responsible for proper disposal of waste material, fuel, and construction debris, and will need to provide 14 days' notice to the Contracting Officer's Representative (COR) before shutting down the fuel system for repairs. The period of performance is 15 calendar days after contract award.

The related federal contract opportunity is a solicitation (Solicitation Number: 140P8124Q0030) for the Willow Beach Marina fuel line repair, issued by the Department of the Interior National Park Service Pacific West Region. The solicitation provides the project description and agency details.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lake Mead National Recreation Area

White Hills, Arizona

SERVICES REQUEST: Repair Fuel and Vault Lines at Willow Beach Marina

DATED: May 7th, 2024

Prepared By: Trent Martinez, Supervisory Facility Operations Specialist

NATIONAL PARK SERVICE

Lake Mead National Recreation Area

MOJA – Install Flooring at OX Ranch House

A04 STATEMENT OF WORK: INSTALL FLOORING AT OX RANCH HOUSE

1. BACKGROUND

Lake Mead National Recreation Area (LAKE) is a U.S. national recreation area in Southeastern Nevada and Northwestern Arizona. Operated by the National Park Service, Lake Mead NRA follows the Colorado River corridor from the westernmost boundary of Grand Canyon National Park to just north of the cities of Laughlin, Nevada and Bullhead City, Arizona. LAKE offers visitors with boating recreational activities and has marinas along the Colorado River south of the Hoover Dam. These marinas are operated by concessioners where they provide boat rentals and fuel. Because of this the marina has fuel lines that deliver fuel to the floating fueling stations for boats. The weather, sun, and movement of the docks deteriorate these lines requiring their replacement.

This project will replace two fuel ramp hoses, approximately 85’ of hose and incoming vault support lines at the Willow Beach Marina fuel dock. The old lines and system will need the fuel purged from them and the new lines and system will need to be purged of air. The fuel lines are 2” and of aircraft quality. One line is for regular fuel and the other is for premium higher octane. All work will need to ensure environmental compliance is followed and preventive measures are taken to eliminate the possibly of contamination of the natural waterways.

2. PROJECT LOCATION:

Willow Beach Marina, Arizona 25804 N Willow Beach Rd, White Hills, AZ 86445

3. PROJECT TASKS

The following tasks shall be completed by contractor as a part of this contract:

a) Replace a total of 170’ of 2” aircraft quality fuel lines and 170’ of 4” double wall access pipe including all necessary fittings, couplers, and hardware for mounting pipe.

b) Replace vault support lines, couplers, fittings, and hardware for mounting lines in the vault. Assure penetrations for lines in vault are fuel and watertight to assure containment of any leaks of the lines in the vaults.

c) Purge the old lines / system of fuel and purge the new lines / system of air.

d) Perform all State and Federal required testing of lines before they are put back into operation.

e) Properly dispose of all waste material, fuel, and construction debris.

f) Provide 14 days’ notice to COR in advance of shutting down the fuel system for repairs and anticipated duration the fuel system will be off for.

4. CONTRACTOR USE OF PREMISES

a) Contractor will keep worksite organized and clean as work allows.

b) Designated areas for staging and contractor access will be identified by NPS COR

c) Contractor will be responsible for disposal of all construction debris and waste.

d) Any government property damaged during this project will be replaced at the contractor’s expense.

e) COR has the right to revoke any of the above privileges at any time if cleanliness or unprofessional behavior warrants it.

5. PERIOD OF PERFORMANCE:

All tasks and deliverables for this contract must be completed within 15 days after award. Days listed herein refer to calendar days.

6. PHOTOS

Photo of fuel lines along ramp.

Photo of fuel lines and vault.

Photo of fuel lines going into vault.

Photo of fuel lines in vault.

End of document.

A04 statement of work: Install Flooring at OX ranch House
1. Background
2. project Location:
3. Project Tasks
4. Contractor Use of Premises
5. Period of Performance:
6. PHotos

File details come from the government source that posted it. Updated .