ATTACHMENT 1 - Statement of Work.docx
DOCX document 51 KB Posted
- Solicitation number
- 12444324Q0047
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Statement of Work for the installation of an electrical meter at the IMPROVE Air Station site at the top of Mt Snow Resort in West Dover, Vermont. The Forest Service is seeking a contractor to provide and install a new electrical meter, install a raceway with conductors, energize the meter, and provide labeling on the panel and meter. The contractor must be able to access the site via a 4x4 work road and work in adverse conditions. The project should begin in June 2024 and be completed by September 1, 2024. The contractor is required to provide a project plan, written progress reports, and have experience with similar technical requirements. Travel costs are the responsibility of the contractor. A Forest Service key will be provided to access the site. This requirement is being solicited under Solicitation Number 12444324Q0047 with an estimated period of performance from June 10, 2024 to August 30, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0002 Questions and Answers Document.pdf | ||
| Amendment 0002 - SF30.pdf | ||
| Amendment 0001 - 12444324Q0047.pdf | ||
| RFQ_12444324Q0047.docx | DOCX document | |
| ATTACHMENT 2 - Map.pdf | ||
| SF 1449.pdf | ||
| ATTACHMENT 3 - SCA WD 2015-4139 WINDHAM COUNTY.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents
| Project | 3 |
| General Information | 3 |
| 1.0 Scope of Work | 3 |
| 2.0 Background | 3 |
| Contractor Requirements | 3 |
| 3.0 Technical Requirements / Tasks | 3 |
| 4.0 Government Furnished | 3 |
| 5.0 Deliverables / Schedule | 3 |
| 6.0 Travel | 4 |
| 7.0 Contractor’s Key Personnel | 4 |
| 8.0 Security Requirements | 4 |
| 9.0 Data Rights | 4 |
| 10.0 Section 508 – Electronic and Information Technology Standards | 4 |
| Attachment | 4 |
Project IMPROVE Air Station Electrical Meter Installation
General Information
1.0 Scope of Work
The Forest Service (USFS) is looking to get an electrical meter installed at the IMPROVE Air Station site at the top of Mt Snow Resort in order to get an accurate reading of electrical usage.
2.0 Background
The IMPROVE Air Station site sits at the top of the Beartrap lift at Mt Snow. It is accessible via a 4x4 work road during non-snow months. The Air Station uses sensors, pumps and other devices to measure the air quality in the surrounding area for the EPA. In 2011 an E-Mon classic 5000 electrical meter was installed at the air station, but only lasted 6 months before an electrical surge ruined it. We want the new installation to provide accurate readings for the foreseeable future.
Contractor Requirements
3.0 Technical Requirements / Tasks
· Meter installation
· Provide and install a khw meter at the panel in the air station
· Provide and install a raceway with conductors needed between the panel and meter
· Energize meter and check voltage and current readings
· Provide and install labeling on the breakers for the panel and meter
· Refeed existing adjacent snow making pump house with 60amp feed
· Feed air station building with rigid conduit from transformer
· Working Conditions
· Must be able to get to the site on Mt Snow work road requiring 4wd and work in adverse conditions.
4.0 Government Furnished
N/A
5.0 Deliverables / Schedule
Please submit a project plan outlining the responsibilities, timeline and technical requirements within 10 business days after the contract award. Ideally, work begins in June 2024 but can begin later as long as the project is completed in full by September 1st, 2024. USFS personnel will introduce the contractor to the site and provide a lay of the land. The contractor is required to provide written progress reports each time work is conducted. The progress report shall cover all work completed during the specified period and shall present the work to be accomplished during the subsequent period. This report shall also identify any problems that arose and a statement explaining how the problem was resolved. This report shall also identify any problems that have arisen but have not been completely resolved and provide an explanation.
6.0 Travel
Travel from the base of Mt Snow in Dover, VT to the air station takes approximately 15 minutes on a steep, dirt work road with water bars in a mountainous environment. Map(s) will be provided. The contractor is responsible for all travel costs.
7.0 Contractor’s Key Personnel
Contractor must have experience with the technical requirements and ideally past performance on similar projects.
8.0 Security Requirements
A Forest Service key is needed to access the air station and will be provided for the duration of the contract.
9.0 Data Rights
N/A
10.0 Section 508 – Electronic and Information Technology Standards N/A
Attachment N/A image1.png
File details come from the government source that posted it. Updated .