Attachment 1 - Statement of Work 750KVA Transformer.pdf
PDF 300 KB Posted
- Attached to
- Transformer (750KVA) Pad Mount Replacement and Installation at Cheyenne Mountain Air Force Station
- Solicitation number
- FA251720Q0098
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Transformer Questions and Answers Updated 13July2020.docx | DOCX document | |
| Image 4.JPG | JPG image | |
| Transformer Image 3.JPG | JPG image | |
| Transformer Image 2.JPG | JPG image | |
| Transformer Questions and Answers.docx | DOCX document | |
| Transformer Image 1.JPG | JPG image | |
| Attachment 3 - Contractor Submittal Form (Services).docx | DOCX document | |
| Attachment 2 - Combo FA251720Q0098 - CMAFS Transformer Replacement and Installation.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Pad Mount Transformer,CMAFS
PREPARED BY:
21st CIVIL ENGINEER SQUADRON
1 NORAD RD
CHEYENNE MOUNTAIN AIR FORCE STATION, CO 80914
1. SCOPE OF WORK:
1.1. GENERAL: The work to be performed under this contract and in accordance with this Statement of Work shall consist of furnishing all necessary restricted area escorts, labor, tools, transportation, supplies, equipment, materials, and incidentals necessary for providing all work performed shown in the statement of work, and all applicable codes, regulations, standards, and criteria in effect at the date of solicitation.
1.2. PROJECT DESCRIPTION: The project consists of total replacement of pad mount 750KVA transformer. Provide and install 750KVA replacement transformer at Cheyenne Mountain Air Force Station (CMAFS), Colorado.
1.2.1. Basic Services.
Provide and install 750KVA 4160V Delta to 480/277V Y replacement transformer at Cheyenne Mountain Air Force Station (CMAFS), Colorado. The scope of this project includes Provide and install 750KVA replacement transformer. New transformer to be set in same location as existing. Existing Primary and Secondary conductors to be reused. If applicable, new bushing extension brackets to be mounted on secondary bushings to maintain termination point of existing conductors. Primary Cables to be placed on "parking bushings" inside the vault and disconnected from transformer. Provide removal of existing transformer and dispose of in accordance with local regulations.
1.3. ENVIRONMENTAL AND HAZARDOUS MATERIALS HANDLING.
1.3.1. The Contractor shall comply with the CMAFS Environmental Business Practices for Projects and Services.
1.3.2. The Contractor shall provide and maintain Material Data Sheets (MDS) on all materials used in the performance of this contract. If any of the materials used by the Contractor in the performance of this contract are considered hazardous, the Contractor shall follow all local, state, and federal laws hazardous waste, and pay all costs associated for the proper management or transport of said hazardous waste to the 21st Civil Engineering Squadron. All potentially hazardous materials/toxics found or identified at CMAFS while executing this work will immediately be reported to the Environmental Section.
1.3.3. Hazardous Materials.
1.3.3.1. Ensure employees handle any hazardous materials according to federal, state, or local laws and emergency response requirements.
If required, a license for employees handling of hazardous materials shall be the Contractor’s responsibility and at their expense. Report any instances of spills, leaks, and/or inadvertent release of hazardous materials to the Environmental Section as soon as the event occurs.
1.3.4. HAZMART Requirement.
1.3.4.1. The Government will provide the Contractor an AF Form 3952, Chemical/Hazardous Material Request Authorization, for all materials used on CMAFS at least 2 weeks prior to the start of work.
1.3.5. Hazardous Waste Management.
1.3.5.1. The Contractor shall contact the CMAFS Environmental Section prior to generating any waste that is determined to be hazardous.
The Contractor is encouraged to contact the Environmental Section if assistance is needed in making a waste determination.
1.3.6. Environmental Records.
1.3.6.1. The Contractor shall submit copies of any records showing quantities of disposed hazardous materials and/or recycled materials to the Environmental Section within 5 business days.
1.3.7. Testing.
1.3.7.1. The Contractor shall test for any potential lead or asbestos.
1.4. LICENSES AND PERMITS.
1.4.1. The Contractor shall obtain all necessary licenses and permits, complying with all federal, state, and municipal laws, codes and regulations applicable to the performance of the work. The Contractor shall provide proof of such applicable licenses and permits upon Government request.
2. MOBILIZATION AND PERFORMANCE PERIOD: In response to RFQ, the contractor will electronically submit proposed equipment brand, model and specifications to the CO for approval. At that time the contractor will notify the CO the lead time required to obtain the materials necessary to complete the work. The contractor will have the submitted lead time plus 14 calendar days to mobilize and start work. The performance period of this contract shall be up to 20 weeks.
3. WORK AND MECHANICS: The work for this project shall be executed in the best and most workman like manner, by qualified and efficient mechanics/tradesmen, skilled in their respective trades. The Contractor shall coordinate and perform all operations in a manner that will result in a professional and expeditiously completed project. Work and materials shall comply with this Statement of Work for all applicable criteria, regulations, guidelines, codes, and industry standards.
4. WORK SCHEDULE: Working hours for the Contractor will normally be between the hours of 7:00 a.m. and 4:00 p.m. excluding Saturdays, Sundays, and Federal holidays.
5. WORK AREA ACCESS: If work is located inside a restricted area at CMAFS.
CONTRACTOR WILL PROVIDE THEIR OWN ESCORT. The Contractor shall coordinate with the R&O POC at (719) 474-3616 and/or CMCC (719) 474-3575 for access. Contractor will submit name, social security number for each employee.
Employees who fail to pass a background check will not be permitted to work at CMAFS. If contractor requires a vehicle to be driven into the restricted area additional information will be required such as the make, model, color, VIN, license plate number, etc. This request must be submitted not later than 10 working days in advance of the first day of work.
6. SAFETY: All Contractor operations shall be conducted and performed in accordance with Department of Labor, OSHA requirements found in 29 CFR 1910 (1910.146 and 1910.147) and 29 CFR 1926, and Air Force Occupational Safety & Health (AFOSH) AFOSH standards including 91-205. The Contractor shall also ensure that all work is performed in accordance with project identified national standards, military manuals, instructions, pamphlets, standards, and handbooks, and with the edition in effect on the date of this solicitation of the Corps of Engineers (COE) Safety Manual 385-1-1.
All electrical work shall be done IAW NEC.
7. PROTECTION OF GOVERNMENT PROPERTY: The Contractor shall use reasonable care to avoid damaging existing buildings, equipment, and vegetation on the Government installation. If the Contractor fails to use reasonable care and causes damage to any of this property, the Contractor shall replace or repair the damage at no expense to the Government. If the Contractor fails or refuses to make such repair or replacement, the Contractor shall be liable for the cost, which may be deducted from the contract price.
8. SITE MAINTENANCE AND CLEANUP:
8.1. SITE MAINTENANCE: The Contractor shall protect work area, and if necessary adjacent areas, from dust, dirt or other materials. Work areas shall be maintained in a neat, clean, and safe condition and shall, at a minimum, be cleaned at the end of each shift. All passageways in/or adjacent to the site shall remain free of project generated trash and debris at all times.
8.2. DAILY CLEANING: The Contractor shall keep the site free from debris at all times and shall perform daily cleaning of all areas.
8.3. CLEANUP: The Contractor shall collect any and all trash, debris, refuse, garbage, etc., that is generated and place it in appropriate containers with lids or approved covers on a periodic basis or as directed by the R&O POC. The aforementioned materials shall be hauled from the site by appropriate means on a daily basis, unless otherwise approved by the R&O POC. Disposal shall be outside the limits of Government property. Disposal shall be by sanitary landfill or other approved methods and shall conform to all local, state, and federal guidelines, criteria, and regulations. Upon completion of the work, the Contractor shall leave the work site and storage area(s) in a clean, neat, and workmanlike condition satisfactory to the R&O POC. Hazardous waste or ozone depleting chemical waste generated as part of this project shall be disposed of by the 21st Civil Engineer Squadron (21 CES). Such wastes shall be appropriate captured and contained and provided to 21 CES in a safe manner.
9. MANUALS: The Contractor shall provide all applicable documents for operations and maintenance of the new system. Additionally the contractor shall provide a separate detailed report for condition and maintenance actions required. This report becomes property of the US Government and shall not be shared with third parties except with written permission from the 21 CES.
END OF STATEMENT OF WORK