Attachment 1 - Statement of Work 648-20-119 draft.pdf
PDF 79 KB Posted
- Solicitation number
- 36C26025Q0448
About this file
This Statement of Work details electrical infrastructure upgrades for the Portland VA campus, specifically focusing on power distribution equipment improvements across multiple buildings (Buildings 100, 101, 103, and 16). The primary scope includes replacing and upgrading electrical systems, performing arc-flash hazard risk assessments, ground resistance testing, transfer switch modifications, and emergency generator control panel electronics replacements. The project involves comprehensive electrical work such as replacing MV switchgear, circuit breakers, installing spare circuit breakers, and upgrading power distribution equipment.
The project has a 545-day performance period with strict work hour restrictions, requiring most activities to be conducted after-hours (generally 4:00 PM to 7:00 AM), with specialized time windows for sensitive areas like the Emergency Department (10:00 PM to 10:00 AM) and Operating Rooms (9:00 PM to 7:00 AM). Work must be coordinated and approved with VA, with weekends considered after-hours. The electrical upgrades are designed to correct existing infrastructure deficiencies and enhance electrical system safety and reliability across the VA Healthcare System's Portland campus.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26025Q0448.docx | DOCX document | |
| Attachment 2 - Sources Sought Questionnaire 648-20-119.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work: Perform the following electrical work on the Portland VA campus:
1. All buildings within scope: Replace, modify, or upgrade existing electrical power distribution equipment to provide corrections per Wiley-Wilson arc-flash report. Once all power aspects of the project have been completed, a facility wide arc-flash hazard risk assessment with report and labeling shall be performed in accordance with specification 26 05 73.
2. Buildings 100, 101, 103: Replace all MV “Old Switchgear” and unit substation circuit breakers.
3. Building 100: Facility wide ground resistance testing per VHA directive 1028-8.j(6)(e).
4. Buildings 100, 101, 103: LS & Critical automatic transfer switches power meter and communication module upgrades (7atss total).
5. Building 100: Provide power distribution equipment for delayed equipment automatic transfer switches; distribution equipment includes mv interrupter switches, mv dry-type transformer, and distribution switchboard.
6. Building 100: Replace MV ring loop feeder from MV Old Switchgear to unit substation
USNW.
7. Building 100: Replace emergency generator control panel electronics within generator master control panel and provide redundant PLC CPU within OHSU control panel, provide programming as required.
8. Buildings 100, 101, 103: Provide spare circuit breakers for mv and unit substation switchgear.
9. Building 16: Replace main electrical distribution equipment.
Period of performance is 545 days
Project Work Hours: All work shall be coordinated and approved with VA. All work shall be conducted after-hours, unless directed otherwise by VA. In general, after hours span from 4:00 PM to 7:00 AM.
Specialized arears/rooms have specific after-hours as indicated below:
-ED (100-1B), 10:00 PM to 10:00 AM
-OR (100-3C), 9:00 PM to 7:00 AM
-Occupied Ward, 4:00 PM to 9:00 PM and 6:00 AM to 7:00 AM
-Weekend is considered after hours.