This document is a Statement of Objectives (SOO) for the Cannon Microwave Project at Cannon Air Force Base and Melrose Air Force Range in New Mexico. The project involves replacing the existing microwave system with a new Aviat microwave system to support installations on Melrose Air Force Range and connectivity between MAFR and Cannon AFB. The project is divided into three Contract Line-Item Number (CLIN) tasks: CLIN 001 covers links between MAFR buildings, CLIN 002 covers links between Cannon AFB buildings and MAFR, and CLIN 003 covers a link from MAFR Building 3161 to Melrose Sundale Gate.

The project requires a new microwave system with specific technical requirements, including Aviat (JITC approved) radio equipment, AES-256 encryption, and a design goal of five 9's (99.999%) reliability with a combined 400 Mbps throughput for the backhaul links. Services include project management, systems engineering, system design, equipment programming, installation, optimization, equipment removal, acceptance testing, basic training, and maintenance support. The contractor must develop a migration plan to minimize disruption to range operations, conduct design reviews, perform spectrum support and frequency interference studies, and ensure compliance with various technical and safety standards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cannon Microwave Project 16 Sep 2024

Statement of Objective (SOO)

For

Cannon Air Force Base / Melrose Air Force Range

Microwave Replacement Project

At

Cannon AFB, Clovis, New Mexico

Contents

1. Needs Statement

2. Existing System

2.1 Site Information

3. Requirements

3.1 Standard Requirements

3.2 Site Specific Requirements

3.2.1 Cannon AFB Building 9

3.2.2 Cannon AFB Building2302

3.2.3 Melrose Building 3161 (GECCO)

3.2.4 Melrose Building 1095 (RSC)

3.2.5 Melrose Sundale Gate

3.2.6 Cannon AFB Building 777

3.2.7 Migration Planning

4. Site Preparation Guidelines

4.1 General Guidelines

4.1.1 Fiber-optic Cable

4.1.2 Tower Loading

4.1.3 Removal of Replaced/Decommissioned Equipment and Materials:

4.2 Grounding Guidelines

4.3 Lightning Protection Guidelines

4.4 Cable Trays Guidelines

4.5 Surge Protection Guidelines

5. Implementation Services

5.1 Schedule

5.2 Program Management

5.3 Design Reviews

5.3.1 Preliminary Design Review (PDR)

5.3.2 Critical Design Review (CDR)

5.4 System Engineering

5.5 Spectrum Support

5.6 Migration Planning

5.7 Project Status Review (PSR) Meetings

5.8 Transportation of System Equipment

5.9 Site Access Information and Visitor Control Requirements

5.10 System Cutover

5.11 Optimization

5.12 Quality Control (QC), Testing, and Burn-In

5.12.1 Quality Control

5.12.2 System Acceptance Test

5.12.3 System Burn-in

5.13 As-Built Documentation

5.14 System Acceptance

5.15 Unique Identification (UID)

5.16 System Award Management (SAM)

6. LOGISTICS REQUIREMENTS

6.1 Spares

6.2 Warranty

6.3 Training

7. Deliverable requirements

ANNEX A (Site Preparation Standards)

ANNEX B (SPECTRUM SUPPORT)

ANNEX C (Labeling standards)

Acronyms

1. NEEDS STATEMENT

Cannon AFB requires a new Aviat microwave system to replace existing unsupportable system. These links support installations on Melrose Air Force Range (MAFR) and connectivity between MAFR and Cannon AFB (CAFB). The goal is a system capable of handling the bandwidth demands of the sites and employing diversity techniques to provide both high reliability and high performance on the links between MAFR and CAFB.

This project is broken into three (3) Contract Line-Item Number (CLIN) tasks as outlined below. Each task needs to stand on its own:

CLIN 001 Link C: MAFR Bldg. 3161 (GECCO) to MAFR Bldg. 1095 (RSC) and Link D: MAFR Bldg. 3161 (GECCO) to MAFR Bldg. 5000 (RC Tower)

CLIN 002 Link A: CAFB Bldg. 2302 to MAFR Bldg. 3161 and Link B: CAFB Bldg. 9 to MAFR Bldg. 3161

CLIN 003 Link H: MAFR Bldg. 3161 (GECCO) to MAFR Sundale Gate

Services shall include project management, systems engineering services, system design, equipment programming, equipment installation and optimization, equipment removal and disposition, acceptance testing, basic training, and maintenance support for the system described in this document.

To minimize impact to range operations CLIN 002 will require transitioning traffic from the current microwave system to the new system. This necessitates partial acceptance of the link between MAFR and 3161.

2. EXISTING SYSTEM

Cannon AFB is located South of Highway 60, approximately 6.7 miles west of Clovis New Mexico. The terrain is flat with sparse vegetation. Location of this site is in the southwest corner of the installation, just west of the Portales truck gate.

Melrose Range is located South of Highway 60, approximately 30 miles west/southwest of Cannon AFB. The terrain is mostly flat with the mesa itself rising 250ft above the surrounding land.

The current microwave system operates in the 7G band and employs several schemes. The contractor shall work with base spectrum management to identify operational frequencies. The following is provided for reference only.

Other frequencies in use at this location include Melrose Sundale Gate M4700 and Melrose Control Tower M4745 via Cambium PTP links. Further spectrum information will be available to the contractor at time of walk-thru.

2.1 SITE INFORMATION

CAFB 9

Building 9 is the main tower on Cannon. Tower has a reported height of 75 ft. Tower did not have an ID or manufacturer tag. This location provides the link to GECCO 3161 Tower b (approximately 68 ft). MAFR link drops off two network connections, one for base Land Mobile Radio (LMR) and one for LAN, both are converted to fiber and run back to Building

10. The system currently handles TDM (T1) connections, but that is expeted to be discontinued before this effort takes place. TDM also ships to Buidling 10 over fiber and then spit out with an ADIT-600.

CAFB 2302

Building 2302 houses the second shot to MAFR tower b (new tower). This is a Nokia system that is currently not in use; active but not passing traffic. The 100ft tower has space for increasing elevation. Based on conversations with Cannon, there is a high-tension line and terrain obstruction located 1.84 miles LOS from this tower. Distance between tower and B2302 is aproximatly 267ft. Two 4in ducts run between the building and tower base. Fiber exists at this location and Cannon will provide dark fiber back to the closest ITN and to Building 10 for the base LMR connection. The contractor shall be responsible for connecting the dark fiber into base LAN and base LMR. This link will have to be established and proven before the link to Building 9 can be turned down.

Tower ID 225402, ROHN 100’ RT, Drawing 225402-01-A1

MAFR 3161

Building 3161, also called GECCO, is the main microwave facility and switching center on MAFR. The new tower (tower b) is on the west (Tower ID 225400, ROHN 100’ RT, Drawing 225400-01-A1) and the old tower (tower a) is on the east (no tag was found). Two 4” ducts run from the base of tower b to the cable bridge between tower a and building 3161. Aproximate distance from tower base is 220’ from tower b and 40’ from tower a. The shot between 3161b and 2302 is mid way up the tower at 45’. Additional path clearance may be found by increasing the heigh of this antenna. NOTE: cable management stops at the microwave dish and will have to be extended up the tower if the antenna height is increased.

Tower B Tower A

3161 also houses the LMR site for MAFR, this is a dedicated network link back to Building 10 via the microwave at Building 9. The existing TDM (broken out by an ADIT-600) is projected to be decommisioned by the time of this project.

There are five (5) links at this location.

• 3161a to Building 9: [Harris] carries all of the range traffic.

• 3161b to Building 2302: [Nokia] Active but not in use.

• 3161b to RSC (Range Support Complex): [Nokia] Provides RSC with phones and network. By the time of this project all phones are expected to transition to VoIP and no TDM links will be required. Space exists on the tower to have a sytem set up in parallell, however space does not exist on the tower down at RSC.

• 3161b to Control Tower (Building 5000): PTP-600 link supporting network only

• 3161b to Sundale Gate: PTP-600 link supporting network only.This link uses a connectorized variant with dish antenna on both ends.

Harris Stratex

Nokia

MAFR 1095 (Range Support Center)

Tower is 40’ with dish located at 25’. Two 4” ducts run from the tower base to comm room in 1095. Distance from tower to comm room is approximately 60’. Dish location is lower to clear power lines immediately southeast of the facility along the roadway. Facility uses a Nokia microwave. Transport is LAN only, no TDM exists at this facility.

MAFR 5000

Range tower (Building 5000) uses a single PTP-600, LAN only, shot back to 3161a. Antenna is mounted to the handrail at tower top (150ft). Power injector for the PTP is in FPI-1 at the end of the comm room (301). One more floor up to the tower cab then a ladder to the roof.

(approximately 45ft of cable distance).

Note: Suppression device for the PTP-600 is connected in the rack. Contractor shall not reuse this location and place lighting protection devices isolated from equipment racks.

MAFR Sundale Gate

MAFR Sundale gate utilizes a pole mounted PTP-600 (20ft) pointed back the old tower (tower a) on GECCO (building 3161). This is a network only link.

The following table is provided to provide information on the microwave links.

Location Lat Lon TWR Height (ft) Bldg 9 34°23’28.623”N 103°19’36.081”W 75

RSC B1095 34°19'20.85"N 103°50'24.903"W 40

B5000 34°17'13.17"N 103°48'35.84"W 150 Bldg 2302 34°21'57.50"N 103°19'24.50"W 100 Bldg 3161b 34°17'15.89"N 103°49'3.74"W 100 Bldg 3161a 34°17'15.76"N 103°49'1.59"W 80 Sundale 34°17'17.77"N 103°41'2.94"W 20

Link Map (notional, does not show data connectivity)

Link A: CAFB Bldg. 2302 to MAFR Bldg. 3161 (inoperable)

Link B: CAFB Bldg. 9 to MAFR Bldg. 3161 (operational)

Link C: MAFR Bldg. 3161 (GECCO) to MAFR Bldg. 1095 (RSC) (operational)

Link D: MAFR Bldg. 3161 (GECCO) to MAFR Bldg. 5000 (RC Tower) (operational)

Link H – MAFR Bldg. 3161 (GECCO) to MAFR Sundale Gate (operational)

3. REQUIREMENTS

3.1 STANDARD REQUIREMENTS

Microwave Radio: Manufacturer shall be Aviat (JITC approved and on the DODIN APL).

All Fixed Network Element (F-NE) provided under this effort must be approved through the Joint Interoperability and Testing Center (JITC) with current IO Certification(s) as indicated in the Approved Products List Integrated Tracking System (APLITS) (https://aplits.disa.mil).

All radio equipment provided must have a current J/F-12 (DD Form 1494) Spectrum Certification.

https://aplits.disa.mil/

All radio links shall be provided with AES-256 encryption with FIPS 140-2 Level 2 certification.

3.2 SITE SPECIFIC REQUIREMENTS

Understanding that maximum bandwidth is reliant on atmosphere and frequency authorizations, the goal is to provide maximum thruput with high reliability. The contractor shall provide bandwidth expectations based upon spectrum allocation, diversity method chosen and site data (location/elevation).

Design goal for the backhaul links A/B (Cannon Building 9 and Cannon Building 2302 to MAFR) is five 9’s (99.999%) with a combined 400 Mbps thruput.

3.2.1 Cannon AFB Building 9

Building 9 uses media converters and fiber to connect to Building 10 where connections are made into the base network and Land Mobile Radio infrastructure. The contractor may reuse existing media converters if they are deemed suitable.

Building 9 shall provide connectivity to Melrose 3161 (currently landed at tower a) via a link employing diversity techniques. The contractor shall examine the frequency authorizations provide, tower loading, and propose a method that best provides high capacity with high reliability.

3.2.2 Cannon AFB Building2302

Building 2302 shall provide connectivity to Melrose 3161 (currently landed at tower b) via a link employing diversity techniques. The contractor shall examine the frequency authorizations provide, tower loading, and propose a method that best provides high capacity with high reliability. This link shall be completed and running traffic before the link from building 9 is decommissioned. The contractor may propose tower modification to 2302 if the path is determined to be unreliable without raising the antenna at this location and at 3161.

3.2.3 Melrose Building 3161 (GECCO)

Building 3161 shall provide routing/failover between the links running back to CAFB. Single points of failure shall be minimized to ensure loss of either Building 9 or Building 2302 links do not impact range operations. LMR traffic shall be given precedence with a lower threshold of 1 Mbps and be kept separate from base network traffic.

Building 3161 shall provide connectivity to both Buildings 9 and 2302 on CAFB in accordance with the designs for those locations.

Building 3161 shall provide connectivity to Building 5000 (Range Control tower). Design goal is 200 Mbps of base LAN connectivity with no space diversity required.

Building 3161 shall provide connectivity to Building 1095 (RSC). The contractor shall examine the frequency authorizations, tower loading, and propose a method that best provides high capacity with high reliability.

3.2.4 Melrose Building 1095 (RSC)

Building 1095 shall provide connectivity to Building 3161. The contractor shall examine the frequency authorizations, tower loading, and propose a method that best provides high capacity with high reliability.

3.2.5 Melrose Sundale Gate

Sundale Gate requires a Point-to-Point link established between the gate and Building 3161. Design goal is 200 Mbps of base LAN connectivity. Given the distance to Sundale, a connectorized unit may be required.

3.2.6 Cannon AFB Building 777

Design goal is to provide a microwave management console accessible across NIPR or on a VLAN and present in Building 777 (2nd floor) situated with EITOS office. The contractor shall propose the necessary software/configuration required to allow EITOS to monitor and control the microwave system.

3.2.7 Migration Planning

To keep MAFR in operation and minimize outages it is necessary to keep link B from 3161 to 9 in operation until all range users are migrated to link A from 3161 to 2302. A suggested schedule is as follows:

Link A, (must be done before Link B) Link C, Link D, Link H (done prior to migration from Link B to Link A) Link B (done last then any cross-connects to Link A established for path redundancy)

4. SITE PREPARATION GUIDELINES

Unless otherwise identified, the contractor shall be responsible for all necessary site preparation/development. Site preparation includes all site work, building modifications, electrical wiring, AC Power, and grounding systems.

4.1 GENERAL GUIDELINES

4.1.1 Fiber-optic Cable

All fiber connections shall be fusion spliced.

• All fibers shall be tested, and a report produced.

• All patch panels shall use SC type connectors.

• Outside plant optical cable shall be loose buffer tube, single mode, water blocked, suitable for outside plant underground applications and shall meet or exceed RUS Regulation 1755.900 and RUS Bulletin 1753F-601.

• All cabling installed shall also meet or exceed the manufacturer’s specifications and specifications detailed within ANSI/TIA-568-C.3 Optical Fiber Cabling Components Standards. These standards address several items including cable transmission performances, minimum cable bend radius, cable pull strength/pull tensions, etc.

• All optical fiber cables shall comply with industry standards with regard to manufacturers’ cable markings, jacket, rip cords, filling compound/water blocking, fiber color coding, jacketing materials, etc. In addition, the fibers shall comply with industry standards with regard to mode field diameter, core-cladding concentricity, attenuation, and dispersion characteristics at 1310 nm and 1550 nm, and also be acceptable for 10-Gigabit Ethernet applications.

• Fiber appearances on patch panels shall be in the same order on each end of the fiber run. Where the multiple fiber cables are terminated in the same patch panel the first fiber shall appear on 1 +12n position and correspond to a 1 +12m position on the distant end (m and n are integers). For further clarification contact 27 SOCS/SCX.

• All Outside Plant cables shall be labeled using Cannon AFB provided standard as shown in ANNEX C (Labeling standards).

• All Patch panels should be installed from the top down, fiber on top then copper.

• All installations shall be tested for FO cable performance per EIA or the latest approved version of the

ANSI/TIA/EIA standards. Test results will be provided to the 27SOCS.

4.1.2 Tower Loading

• Tower loading shall be calculated using TIA-222/G wind load standard.

• A structural loading analysis shall be accomplished for each tower modification. The analysis shall bear a

Professional Engineering seal certifying the design meets the TIA-222/G wind load standard for the installed location.

4.1.3 Removal of Replaced/Decommissioned Equipment and Materials:

The contractor shall coordinate with Cannon AFB and remove all decommissioned microwave equipment, antennas, and cabling. Contractor shall coordinate with Cannon AFB for where equipment is to be turned in. Contractor is responsible for proper disposal of all other removed items. Holes for mounts and penetrations shall be filled.

4.2 GROUNDING GUIDELINES

If required by the proposed technical solution, the contractor shall meet the following minimum Government guidelines: In the event of a conflict between the following and National/State code, National/State code shall supersede.

• The contractor shall ensure that all equipment is electrically bonded, grounded, and protected in accordance with the National Electric Code.

• The contractor shall provide all grounding and lightning protection equipment, including surge arrestors, to comply with the requirements of all equipment being installed and connected as part of the system.

• Building conductors shall be used to bond the various pieces of equipment, conduit, trays, etc. together.

• All equipment supplied with a ground connection point, metallic equipment mounting rails or brackets and metallic parts of dispatch furniture shall be suitably bonded to the main ground bar or ground bus conductor.

• A single point ground system shall be used, whenever possible, and approved by the site manager, on all equipment installed as part of the system. The single point ground system installed within equipment shelters or buildings shall be connected to the exterior building/tower ground system.

• Each waveguide installed on the tower shall be grounded at three points. At the base of the antenna, at the transition from the tower to the ice/cable bridge and at the entrance to the shelter. Microwave installation shall follow vendor specified grounding standards.

• The grounding system installation shall be in accordance with the following guidelines:

o Each single row of equipment shall have a separate ground bus consisting of an American Wire

Gauge (AWG) #2 or larger copper conductor.

o Each bus shall be connected to the single point ground window.

o A single cabinet, rack, or enclosure and any associated transmission line or circuit protection devices shall have a ground conductor bonding all components to a single point ground near the equipment installation.

• The antenna support structure/tower must be bonded to the external ground system using an exothermic weld, if permitted by the tower manufacturer.

• All grounding conductors that compose the external ground system shall be connected using exothermic welding and where connected to grounding rods shall be a minimum of 1/0.

• Transmission lines shall be grounded with proper sized ground kits connected to the tower ground and building entry bus.

• The external ground system shall provide a ground resistance of 5 ohms or less. If the soil conditions at a site are such that the contractor cannot reasonably design a ground system that meets this requirement, the contractor shall design a ground system that meets the best possible value as agreed to by the Government.

• New grounding systems shall be installed in accordance with the National Electrical Code and applicable best industry practices and standards. All external ground rings, copper ground rods, chemical ground rods, and interconnecting copper conductors must be buried to a minimum depth of 30 inches, or 6 inches below the freeze line for the area, whichever is greater.

• All main ground lead connections shall be thermally welded, compression joints shall not be used. The preferred installation standard is Motorola R56. Shelters and towers shall employ joined ground rings (Refer to NFPA 70, Article 250-50 and NFPA 780, Section 3-13.3 for more information.).

4.3 LIGHTNING PROTECTION GUIDELINES

Lightning protection shall be provided for the shelter, tower and all significant metallic structures IAW the NFPA 780 Standard for Installation of Lightning Protection Devices.

4.4 CABLE TRAYS GUIDELINES

If required, the contractor shall install 24-inch wide cable trays or ladder over the rows of proposed equipment racks.

Cable tray/ladders shall be:

• Installed a minimum of 6-inches above the equipment racks.

• Bonded together and tied to ground system.

4.5 SURGE PROTECTION GUIDELINES

The contractor shall provide surge protection from incoming electrical transients on all AC power lines and telephone/data lines.

5. IMPLEMENTATION SERVICES

5.1 SCHEDULE

The offeror shall provide a detailed working schedule for accomplishing the requirements of this project in MS Project format which includes all Government activities, e.g. IA activities and network connectivity. The schedule shall identify all critical milestones and deliverables for the final design, integration, installation, and testing of the system. The milestones and schedule shall be described with reference to days after receipt of notice to proceed.

(CDRL A002)

5.2 PROGRAM MANAGEMENT

Program Management shall be provided throughout the design and implementation of the system.

5.3 DESIGN REVIEWS

5.3.1 Preliminary Design Review (PDR)

The vendor will conduct a Preliminary Design Review (PDR) as soon as possible, after contract award. The purpose of this meeting will be to:

• Identify and explain work conditions and requirements for the vendor

• Establish procedures for communication and installation updates

• Document and discuss specific installation criteria

• Explanation and clarification of contract procedures for the customer and the vendor

• Define in writing all project timelines

• Define in writing all vendor and Base responsibilities

5.3.2 Critical Design Review (CDR)

The vendor will conduct a Critical Design Review (CDR) prior to design acceptance. The purpose of this meeting will be to:

• Document and discuss specific installation and delivery timelines

• Confirm that the vendors design meets government requirements and is implementable as designed

• Provide sign-off on contractors’ facility and tower design with respect to base civil engineering requirements

• Provide sign-off on contractors’ microwave design with respect to base frequency management

5.4 SYSTEM ENGINEERING

Systems engineering services shall be provided from the preliminary system design through the completion of system implementation, security evaluation, and functional testing. As a minimum, system engineering services shall include the following:

• System design

• System architecture development

• Baseline System Configuration

• Frequency analysis and planning

• Link analysis

• Traffic (loading) analysis

• Channel Partitioning/Prioritization

• Implementation support (design synthesis)

• Acceptance testing

• Final (as-built) system documentation

5.5 SPECTRUM SUPPORT

As a part of their proposal, the vendor shall provide information as outlined in ANNEX B (SPECTRUM SUPPORT). An RF frequency interference study shall be performed by the installing contractor at all new tower locations to compare selected new microwave frequencies and existing frequencies in adjoining facilities are not likely to interfere with one another. This may require that the final selected frequencies for the new microwaves must be changed to preclude interference. The contractor shall work with the base spectrum manager to obtain the appropriate frequencies.

5.6 MIGRATION PLANNING

The contractor shall develop a Migration Plan in coordination with the Program Manager at the Base. The Migration Plan will provide an orderly migration of all microwave users to the new system with minimal disruption to operations.

5.7 PROJECT STATUS REVIEW (PSR) MEETINGS

The contractor shall participate in weekly (or as decided by the IPT) PSR meetings. The contractor shall include any existing action items for both the Government and contractor. (CDRL A004)

5.8 TRANSPORTATION OF SYSTEM EQUIPMENT

The Government will provide a “Ship-to” address and temporary storage/staging area. The contractor shall be responsible for inventory and reconciliation of all shipments, which will be coordinated with and verified by a Government representative. The contractor shall transport all equipment from the temporary storage area to its final destination. Melrose roads are semi-improved caliche. Before delivery the contractor is advised to check with Cannon on the road conditions as they may not support standard heavy transport vehicles.

5.9 SITE ACCESS INFORMATION AND VISITOR CONTROL REQUIREMENTS

The contractor shall coordinate all site visits through the Base Project Leader, the Range Management Office, and the Wing Scheduling Office. All personnel working or visiting MAFR are required to attend Range Lead Training prior to entering the range. MAFR is an active range, the contractor shall adhere to all range policies and procedures. The contractor shall provide all necessary site visit information at least 10 days prior to any site visit by any contractor or subcontractor. The contractor shall coordinate all deliveries with the Base Project Leader at least 10 days prior to delivery and provide any site visit information required for the delivery. This will ensure visit clearances can be obtained from the local Security/Visitor Control Office.

Cannon will provide escorts as necessary at all installations and locations. Contractor shall provide personal information as requested by Cannon to facilitate clearance onto military installations.

5.10 SYSTEM CUTOVER

See also 5.6 Migration Planning. The contractor shall develop a cutover plan in coordination with installation personnel and the Government Program Manager. The plan shall provide for an orderly, cost-effective transition of all circuits to the new system with minimal disruptions to operations and end users. There are two paths, soft cutover and hard cutover. Soft cutover means that the old and new systems will both be in operation at the same time until operational cutover is completed to the new system. Hard cutover means the old system will be deactivated for a period until the new system can take on traffic. Soft cutover is preferred. Hard cutover requires the contractor to coordinate with the base and be given an Authorized System Interruption (ASI) before any actions impacting existing circuits can be taken. The goal is to minimize interruption to activities. (CDRL A006)

5.11 OPTIMIZATION

The contractor shall optimize all microwave equipment after system installation is completed to ensure optimal performance and reliability.

5.12 QUALITY CONTROL (QC), TESTING, AND BURN-IN

5.12.1 Quality Control

The contractor shall provide a QC focal point for the entire life of the project. The QC shall assist the government Quality Assurance Evaluator (QAE) representative in performing random spot checks and in performing the system acceptance tests. The QC shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A Status Report will be submitted, indicating project progress/statuses and listings any deficiencies/discrepancies found and actions to correct them. (CDRL A003)

5.12.2 System Acceptance Test

The Contractor shall provide the Acceptance Test Plan for the system. (CDRL A006)

System Acceptance Test shall include:

• System alarming, monitoring, and fault management as it pertains to the ability to diagnose, monitor, and maintain the microwave system.

• All equipment installed by the prime contractor or its sub-contractors.

• Failover testing of generator and UPS.

The contractor shall ensure that the entire system is completely tested 10 days prior to system cutover.

The contractor shall have 15 days after completion of the System Acceptance Testing to research, develop, and document the resolution of all discrepancies. The contractor shall provide in writing a detailed explanation to the Government engineer/ Project Leader/QA representative of how the discrepancy will be resolved including any changes to the radio programming or the system data bases. (CDRL A003) Upon direction of the Project Leader, the contractor shall implement the proposed resolution and perform the portion of the System Acceptance Test that previously failed.

5.12.3 System Burn-in

The Government reserves the right to refuse start of 30-day burn-in until all discrepancies have been resolved to the satisfaction of the Government. The Government will review all test results and prepare the official list of discrepancies, if any. The contractor shall support this effort by submitting his/her own list of discrepancies based on discrepancies detected/identified during testing and/or inspections conducted by either the contractor or the Government QA representative.

The contractor shall perform a 30-day Operational Test of the system. The 30-day equipment burn-in will not start until the system has successfully passed all of the tests in the system ATP, all QC discrepancies have been resolved, the IA effort is complete, and Government approval has been provided from the Project Leader. If any major failure occurs during the 30-day burn-in, the test shall be terminated, corrective action shall be taken and approved, and the entire 30 days shall be restarted. If any minor failure occurs during the 30-day test period, the testing period may resume after resolution of the problem. The contractor shall document in detail any discrepancies that occur during testing. (CDRL A005)

5.12.3.1 System Burn-in Tracking Reports Support

The contractor shall support the site in tracking any problems during the System Burn-in. As a minimum, the contractor’s responsibilities shall include, answering called-in trouble calls, creating trouble tickets and logs, providing tracking reports for active and closed tickets, answering questions, and correcting any system deficiencies that are identified. The Project Leader will prioritize the trouble calls.

5.13 AS-BUILT DOCUMENTATION

The Contractor shall provide full documentation on the installed system. (CDRL A001)

5.14 SYSTEM ACCEPTANCE

Formal system acceptance shall be granted after completion of the acceptance test and a successful 30-day equipment burn-in period. Final acceptance shall require at a minimum:

• Completion of all facility work, system, component, hardware and software delivery, installation, testing, optimization, phased integration, as built documentation, and training.

• Acceptance of system facilities, individual systems, and equipment by Communications Squadron and management personnel. Correction of any operational, performance, or workmanship defects shall be at the sole expense of the contractor.

• Successful completion of System Acceptance Testing. Failure of any tests during the system acceptance test will delay the start of the 30-day burn-in period until all tests have passed.

• Successful completion of the RF testing. Failure of the system to provide the designed capacity will delay the start of the 30-day burn-in period until any RF issues are resolved to the satisfaction of the Government.

• Successful completion of the IA certification.

• Successful completion of the 30-day burn-in period.

• Completion of system and maintenance training.

Upon final acceptance, the Government shall complete an AFTO 747 and provide one copy to the Contractor.

5.15 UNIQUE IDENTIFICATION (UID)

The Office of the Under Secretary of Defense for Acquisition Technology and Logistics developed a Defense Procurement and Acquisition Policy for unique identification (UID). The requirement affects all delivered items for which the Government’s unit acquisition cost is $5,000 or more.

The contractor shall apply physical unique item identifiers (UII) in the format specified in referenced DFARS clause. The required information includes, but is not limited to:

(1) Concatenated UII or DoD recognized unique identification equivalent

(2) UII type

(3) Issuing agency code

(4) Enterprise identifier

(5) Original part number

(6) Lot or batch number

(7) Current part number

(8) Current part number effective date

(9) Serial number

(10) Unit of measure

(11) Description

The contractor shall apply physical UIIs to all equipment with a unit acquisition cost of $5,000 or more that is procured through this requirement. Contractors shall also register the UIIs in the item unique identification (IUID) Registry. The vendor shall provide a detailed description of how the requirement of DFARS policy and clause 252.211-7003 will be accomplished, including a description of how the vendor will provide verification that the reporting requirement has been met.

5.16 SYSTEM AWARD MANAGEMENT (SAM)

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Installation via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.sam.gov

6. LOGISTICS REQUIREMENTS

6.1 SPARES

The contractor shall propose all necessary spares for their system.

6.2 WARRANTY

The contractor shall provide a standard commercial warranty in conformance to NetCents contact. The warranty shall commence at the date of final system acceptance.

6.3 TRAINING

The contractor shall provide Training Plan and Syllabus for system maintainers. The classes shall be scheduled in cooperation with Cannon AFB to minimize the impact on shift personnel. Classes shall be scheduled close to the time personnel will start performing system functions to ensure retention of material. System management (including system security), device management, and basic radio maintenance tasks shall be provided during the system implementation process. The system security training shall encompass at a minimum; security component operation and maintenance, backup and restore procedures, patch update procedures, file/log retrieval and archiving, and password maintenance. (CDRL A007)

Training shall include course material for all training classes with a right to reproduce in hard copy, computer CD, or DVD. Cannon AFB will provide all necessary on-site classrooms for training that occurs at the installation. The contractor shall identify all classroom and class support requirements.

The contractor shall provide all instruction material, including printed manuals, audio, video, interactive self-paced personal computer programs, training aids, handouts, support equipment, and complete equipment operating instructions for all technical and operational training classes. The contractor shall provide electronic versions of all training materials for all classes, and supply Cannon AFB with additional hard copy materials for all “train-the-trainer” classes. Actual and/or exact models and series of equipment being delivered shall be made available for “hands-on” use and operation during training. The contractor shall provide each trained individual a certificate of completion.

7. DELIVERABLE REQUIREMENTS

The contractor shall provide adequate documentation of the final system design and implementation plans. Specific addresses and copies will be addressed after contract award. The contractor shall supply system manuals and equipment manuals. At a minimum, documentation shall include the following.

CDRL Data Item Title Paragraph(s) A001 Communication-Computer Systems Installation Records (CSIRs) A002 Work Schedule A003 Status Report A004 Meeting Minutes A005 Installation Test Report A006 Test Plan/Report A007 Training Plan

ANNEX A (SITE PREPARATION STANDARDS)

• ANSI/EIA/TIA-222G, Structural Standards for Steel Antenna Towers & Antenna Supporting Structures

• NFPA 780, Standard for Installation of Lightning Protection Devices, 5 August 2004

• NFPA 70 National Electrical Code (NEC)

• FAA Advisory Circular 70/7460-2k, Proposed Construction or Alteration of Objects that May Affect the

Navigable Airspace, 1 March 2000

• FAA Advisory Circular 70/7460-1K, Obstruction Marking and Lighting, 1 August 2000

• FAA Advisory Circular150/5345-43F, Specification for Obstruction Lighting Equipment, 12 September 2006

• Motorola R56 Standard, “Standards and Guidelines for Communications Sites”

• ANSI/NECA/BICSI 568

• UFC 3-600-01, “Fire Protection Engineering For Facilities”

• UFC 4-010-01, “DoD Minimum Antiterrorism Standards For Buildings”

ANNEX B (SPECTRUM SUPPORT)

1) Requested Frequency range/Operational Frequency(s):

2) Emission Bandwidth:

3) Transmitter Power (Watts):

4) Emission Designator:

5) Equipment Type

a. Manufacturer

b. Model Name

c. J/F 12 No.

d. FCC No.

6) Antenna

a. Type

b. Gain

c. Antenna feed point (height above ground elevation)

d. Latitude (dd-mm-ss.ss)

e. Longitude (dd-mm-ss.ss)

f. Antenna Azimuth

ANNEX C (LABELING STANDARDS)

ACRONYMS

AES Advanced Encryption Standard AFB Air Force Base AFSOC Air Force Special Operations Command ARO After Receipt of Order ATS Automatic Transfer Switch CDR Critical Design Review DIACAP DoD Information Assurance Certification and Accreditation Process EFI&T Engineer, Furnish, Install, and Test FCC Federal Communications Corporation FM Factory Mutual GoS Grade of Service GUI Graphical User Interface HVAC Heating, Ventilation, and Air Conditioning IA Information Assurance IAVA Information Assurance Vulnerability Alert ID Identification IP Internet Protocol ISM Installation Spectrum Manager IV&D Integrated Voice and Data JITC Joint Interoperability Test Center LAN Local Area Network LMR Land Mobile Radio MAFR Melrose Air Force Range NFPA National Fire Protection Association NIST National Institute of Standards and Technology NLT Not Later Than NSA National Security Agency NTIA National Telecommunications and Information Administration POA&M Plan Of Action and Milestones PDR Preliminary Design Review PSR Program Status Review RF Radio Frequency RSC Range Support Complex SMT System Manager Terminal TIA Telecommunications Industry Association UHF Ultra High Frequency UPS Uninterruptable Power Supply

1. Needs Statement
2. Existing System
2.1 Site Information
3. Requirements
3.1 Standard Requirements
3.2 Site Specific Requirements
3.2.1 Cannon AFB Building 9
3.2.2 Cannon AFB Building2302
3.2.3 Melrose Building 3161 (GECCO)
3.2.4 Melrose Building 1095 (RSC)
3.2.5 Melrose Sundale Gate
3.2.6 Cannon AFB Building 777
3.2.7 Migration Planning
4. Site Preparation Guidelines
4.1 General Guidelines
4.1.1 Fiber-optic Cable
4.1.2 Tower Loading
4.1.3 Removal of Replaced/Decommissioned Equipment and Materials:
4.2 Grounding Guidelines
4.3 Lightning Protection Guidelines
4.4 Cable Trays Guidelines
4.5 Surge Protection Guidelines
5. Implementation Services
5.1 Schedule
5.2 Program Management
5.3 Design Reviews
5.3.1 Preliminary Design Review (PDR)
5.3.2 Critical Design Review (CDR)
5.4 System Engineering
5.5 Spectrum Support
5.6 Migration Planning
5.7 Project Status Review (PSR) Meetings
5.8 Transportation of System Equipment
5.9 Site Access Information and Visitor Control Requirements
5.10 System Cutover
5.11 Optimization
5.12 Quality Control (QC), Testing, and Burn-In
5.12.1 Quality Control
5.12.2 System Acceptance Test
5.12.3 System Burn-in
5.12.3.1 System Burn-in Tracking Reports Support
5.13 As-Built Documentation
5.14 System Acceptance
5.15 Unique Identification (UID)
5.16 System Award Management (SAM)
6. LOGISTICS REQUIREMENTS
6.1 Spares
6.2 Warranty
6.3 Training
7. Deliverable requirements