Attachment 1 - Specifications.pdf
PDF 584 KB Posted
- Solicitation number
- 697DCK-24-R-00360
About this file
This document is a set of specifications for a federal contract opportunity to replace the parking lot lights and poles at the FAA's Guam Center Radar Approach Control (CERAP) facility in Barrigada, Guam. The work includes providing and furnishing all material, labor, equipment, transportation, and services required to remove and replace the parking lot lights, poles, lighting controls, and electrical wires.
The key details are:
- The project is estimated to cost between $150,000 and $300,000.
- It is set aside for small businesses under NAICS code 238210 - Electrical Wiring Contractors.
- Important dates include: a site visit on May 1, 2024, questions due by May 17, 2024, and offers due by May 29, 2024.
- The FAA's Northwest Mountain Region is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
FOR
REPLACE PARKING LOT LIGHTS AND POLES
ZUA GUAM CERAP
AGANA, GUAM
JANUARY 2024
Prepared by: Federal Aviation Administration ATO Tech Ops Enroute Engineering Services Western Service Area (WSA-950)
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
TOC-1 Table of Contents
DIVISION 1 — GENERAL
011000 013000 013526 017700
SUMMARY
SUBMITTALS
SAFETY REQUIREMENTS
CLOSE OUT PROCEDURES
DIVISION 26 — ELECTRICAL
260519
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260553 265600
IDENTIFICATION FOR ELECTRICAL SYSTEMS
EXTERIOR LIGHTING
PROJECT DRAWINGS
Cover Sheet ZLA–D–ARTCC-G014 Electrical Site Plan ZLA–D–ARTCC–E001 Electrical Power Plan ZLA–D–ARTCC–E002
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUMMARY 011000 - 1
SECTION 011000 – SUMMARY
PART 1 - GENERAL
1.1 SUMMARY OF WORK
A. This Section includes:
1. Project Information
2. Work covered by Contract Documents
3. Furnished Products
4. Use of Premises
5. Access to Site
6. Security and Badging Requirements
7. FAA Occupancy Requirements
8. Work Hours and Restrictions
9. Project Safety Plan
10. Project Coordination
1.2 PROJECT INFORMATION
A. Project Identification: Guam CERAP
1. Project Location: 1775 Admiral Sherman Blvd, Barrigada Guam 96913
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
Provide and furnish all material, labor, equipment, transportation and services required to remove and replace Parking Lot Lights, Poles, Lighting Controls and Electrical Wires.
B. Intent of Specifications
1. All work performed and all materials and equipment used shall be approved by the Contracting Officer Representative (COR). This shall include but is limited to inspection, scheduling, reporting and submittals.
2. Titles to divisions and sections of the specifications referring to subcontractor, division of work by trade, or type of work are introduced merely for convenience in reading the specifications and do not imply any separate contractual arrangement of work assignments. Such separations into titled divisions and sections shall not operate to make the Government an arbiter to establish subcontract limits between the Contractor and subcontractors or between the subcontractors themselves.
3. The Contractor shall not use dimensions scaled from drawings. All dimensions shown on the drawing shall be verified by the Contractor by actual measurements in the field. Any discrepancies between the drawings and specifications and the existing conditions shall be referred to the COR for adjustment before any affected work is performed.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUMMARY 011000 - 2
1.4 FAA-FURNISHED PRODUCTS
A. FAA-Furnished Products: None
1.5 USE OF PREMISES
A. Contractor shall have use of the CERAP premises for demolition and installation activities, limited as indicated on project drawings and as otherwise addressed.
B. Use of Site: Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. FAA occupancy and operations: The CERAP is a continuously occupied critical facility operated to assure air traffic safety. FAA occupancy of Project site shall occur during all project activities. Operations shall take precedent over all construction and installation activities.
1.6 ACCESS TO SITE
A. Precautions - The CERAP is a 24 hour, 7 day per week operating facility occupied by Air Traffic Controllers and Technical Operations personnel. The function at the facility is vital to the safety of the flying public. In the event of any actual or potential conflict, air traffic control activities shall have priority over all Contractor activities. It is absolutely mandatory that the Contractor schedule and plan all construction activity and coordinate with the Contracting Officer Representative (COR) so that normal operations may continue. No unplanned disruption or interruption to the facility operation can be tolerated at any time.
B. Driveways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to the FAA and emergency vehicles at all times. Do not use these areas for parking or storage of materials. All deliveries shall be coordinated with the Contracting officer Representative.
1. Schedule deliveries to minimize use of the loading dock, driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Condition of Existing Building (interior and exterior), Paving, Lawns, Curbs and Sidewalks: Contractor shall restore, repair any damage it caused due to accidental or incidental negligence and to project operations. Building occupants must be kept safe at all times.
1.7 SECURITY REQUIREMENTS
A. Security ID Badging Requirements - Contractor personnel shall be subject to a security investigation by the FAA and shall obtain FAA Identification Media Badge prior to start of on-site work.
1. After contract award and pursuant to Contract Clause 3.14-2, Contractor Personnel Suitability Requirements.
(a) Contractor shall provide the Contracting Officer with a list of contractor per-sonnel who shall request FAA Identification Media Badge. The list shall be kept current during the entire duration of the project.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUMMARY 011000 - 3
(b) The Contractor shall designate a representative to be the point of contact (POC) for inputting employee information into the Vendor Applicant Process (VAP).
2. Badging two-stage process: VAP entry followed by coordination with the FAA Se-curity Office Representative.
( a ) Submitting all necessary forms including FD 258 Fingerprint Card and FAA background check.
( b ) The FAA Security Office Representative provides notification of “Interim Suit-ability” and directs contractor employees to make an appointment at a FAA Personal Identity Verification (PIV) Center. FAA PIV Center is located on the grounds of the L o s A n g e l e s Air Route Traffic Control Center. Al-ternate locations for PIV Centers can be provided upon request.
(c) The badging process takes approximately 30 days to complete. The time frame varies based on filling out the forms timely, correctly and scheduling appoint-ments at the PIV Center promptly, etc. Each contractor employee must have their own individual email address to complete the application process. Prior to receiving a FAA Identification Media Badge, the employee is required to take FAA Security Training.
3. Types of FAA Identification Media Badge: FAA Identification Media consist of a Contractor PIV Badge (with green strip).
( a ) Contractor PIV Badge allows the contractor access to the grounds and work site and escort authorized visitors at the work site. Typically the contractor superintendent and subcontractor foreman/superintendent obtain Contractor PIV Badge. The FAA reserves the right to limit the number of “PIV” Badges issued.
4. Visitor Access: A visitor is defined as any employee who does not have a FAA Identification Media Badge. A minimum of two (2) work day notification to the COR is required for admittance to the FAA facility. Contractor personnel with a “PIV badge” shall escort the visitor at all times while on site. FAA employ-ees will not escort contractor employees except when it is coordinated and ap-proved by the COR.
B. Contractor’s personnel shall not violate any FAA security regulations. Violators will be removed from the premises with the right to reenter revocable.
C. Current procedures at FAA facilities include the "right to search". Access to the site constitutes consent to search. If in the judgment of the FAA Security Guard a cause to search a vehicle or the person of personnel exists, such search will be made.
D. Contractor's personnel shall not violate any security regulations pertaining to the CERAP facility. Violators may be removed from the premises with the right to re-enter revocable.
E. All persons entering or delivering to this federal facility must have valid government issued identification.
Valid issued government identification is:
a) ID issued by the federal, state, county, or city government or by the military.
b) Must have the person’s legal name.
c) Must have a unique ID number.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUMMARY 011000 - 4
d) Must have an expiration date.
e) Must have a picture of the individual.
f) Must have the name of the agency issuing it.
(Examples: state issued drivers’ license or IDs, passports, or military ID.)
F. Persons entering on to federal property (including visitor parking lot) are prohibited from having on their person or in their vehicle:
a) Guns
b) Knifes with blades over 3 inches except for valid tools.
c) Projection devices, bow & arrows, paint ball weapons, blow guns, etc.
d) Clubs, batons, collapsible batons, or saps.
e) Stun guns or Tasers.
f) Chemical agents, mace, or pepper sprays.
g) Marshal arts weapons of any kind.
h) Weapons of any kind.
i) Alcohol
j) Illegal drugs
k) Animals with the exception of a verified service animal.
l) Family members, friends, children, minors, anyone not authorized on the
FAA visitor list.
1.8 FAA’S OCCUPANCY REQUIREMENTS
A. Full FAA Occupancy: FAA will occupy the building during entire project duration.
Cooperate with FAA during demolition and installation operations to minimize conflicts and facilitate FAA usage. Perform the work so as not to interfere with FAA's day-to-day operations. Maintain existing exits, unless otherwise indicated.
(a) Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from COR.
(b) Provide not less than 72 hours' notice to the COR of activities that will affect FAA's operations.
B. FAA Occupancy of Completed Areas of Construction: FAA reserves the right to occupy and to place and install equipment in completed areas of building, before Substantial Completion, provided such occupancy does not interfere with completion of the Work.
Such placement of equipment and partial occupancy shall not constitute acceptance of the total Work.
1. COR will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied before FAA occupancy.
2. Obtain a Certificate of Occupancy from authorities having jurisdiction before FAA occupancy.
3. Before partial FAA occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed and documented. Upon occupancy the FAA will operate and maintain mechanical and electrical systems serving occupied portions of building.
4. Upon occupancy the FAA will assume responsibility for maintenance and custodial service for occupied portions of building.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUMMARY 011000 - 5
1.9 WORK HOURS AND RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed inside the building during normal business working hours of 7:30 a.m. to 4:00 p.m., Monday through Friday, except when project exigencies required otherwise. Work hours shall be coordinated with the
COR.
1. No work will take place on federal holidays without prior approval by the COR.
2. Weekend Hours: Weekend work and overtime is not authorized, except as otherwise noted, without approval by the COR.
3. Early Morning Hours for Noisy, Vibration Activity: Construction noise, vibration within the facility must be minimized between 7:00 a.m. and 8:30 p.m. Coordinate the work hours for noisy work with the COR.
4. Hours for Utility Shutdowns: Shutdowns and cutovers of environmental, utility and electrical systems impacting facility operations shall be accomplished between the hours of 6:00 p.m. and 4:00 a.m.
5. Hours for core drilling or drilling into concrete for anchors: Construction noise, vibration within the facility must be minimized between 2:00 a.m. and 5:00 a.m.
Coordinate the work hours for noisy work with the COR.
6. No work shall be scheduled or take place during the week of and the weekend pre-ceding and following the Thanksgiving, Christmas and New Year Holidays. Only emergency work to restore critical services to the facility will be considered and a moratorium waiver must be submitted and approved. The moratorium period will not be counted against the contract construction duration.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by FAA or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify the COR not less than fourteen (14) working days in advance of proposed shutdowns and cutovers of environmental, utility and electrical systems.
Note: All advanced installation for temporary systems shall be completed prior to schedule shutdown and/or cut-over to minimize the duration of the shutdown.
C. Nonsmoking Building: Smoking is not permitted within the CERAP Building or within 25 feet of building entrances, operable windows, or outdoor air intakes.
1.10 SUBMITTALS – Project Safety Plan (Refer to Section 013526 for other requirements)
A. Safety Plan: The contractor must submit to the Contracting Officer twenty (20) calendar days after award of contract an Accident Prevention/Safety Plan. The plan shall be ac-cepted by the Contracting Officer prior to start of on-site work. The plan shall be project site specific and contain as a minimum the following major elements:
a. Management commitment and employee involvement,
b. Work site analysis
c. Hazard prevention and control
d. Fall protection
e. Safety and health training
f. Construction safety checklist
g. Emergency preparedness and procedures
h. Accident investigation forms.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUMMARY 011000 - 6
B. Hazcom Plan: The Contractor shall provide a project site specific HAZCOM Plan to the
COR prior to commencing on-site work. The HAZCOM plan shall be prepared in ac-cordance with 29 CFR, Part 1910.1200 - Federal Hazard Communications [HAZCOM] Standard. As a minimum, the plan shall contain the following:
1. Provide a name for the responsible HAZCOM person.
2. Provide the name of the person responsible for updating the MSDS’s.
3. Provide the name of the person responsible for “LABELING” all material on site.
4. Provide the name of the person responsible for training employees.
5. Provide the name of the person responsible for the Contingency Plan.
6. Provide the name of the person responsible of disseminating information to the
FAA HAZCOM Point of Contact within 24 hours.
7. Provide the training and records of employees trained in HAZCOM.
8. Provide an MSDS for each and all chemicals brought on site.
9. Written procedures for the introduction of unanticipated chemicals at the job site.
C. MSDS Sheets: Prior to bringing chemicals into the facility, contractor shall submit
MSDS sheets to the FAA for approval.
1.11 PROJECT COORDINATION
A. Seven (7) calendar days prior to start of on-site work, the Contractor shall meet the COR and Facility representatives at the site for a project pre-commencement meeting to review access and coordination requirements, safety procedures, project hazards and risk analy-sis, and safety and health requirements.
FAA Form 3900-18, Pre-Construction Environmental and Occupational Safety and Health Checklist, will be filled out, and all parties shall sign the form to document dis-cussion of the items on the form.
B. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, with the COR not less than 10 working days in advanced of proposed work
1. Contractor shall have in place mitigation measures such as local exhaust ventila-tion and perimeter seals during odorous work activity. Contractor shall prevent migration of odors to FAA Occupied Work Areas.
C. Construction Aids - Furnish, install and maintain required construction aids. Remove on completion of work. Provide construction aids and equipment required by personnel and to facilitate execution of the work i.e. trench boxes, scaffolds, staging, ladders, stairs, ramps, runways, platforms, railings, hoists, cranes, chutes and other such facilities and equipment.
D. Barriers - Furnish, install and maintain suitable barriers as required to prevent public en-try, and to protect the work, existing facilities, trees and plants from construction opera-tions; remove when no longer needed, or at completion of work. Materials of contractor's option, as appropriate to serve required purpose and approved by RE. Where any remov-al, drilling or cutting of walls or other surfaces in areas of existing facilities operations occurs, the contractor shall install temporary partitions prior to demolition to prevent en-
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUMMARY 011000 - 7
trance of dust or other matter into the working areas. Where normal activities are to be carried on inside the building adjacent to the partition, the partition shall be thermally in-sulated and acoustically treated to prevent entry of temperature extremes and construction noise.
E. Lead Coating Work Practices: For any construction operations, such as sanding, drill-ing, cutting, or coring, on existing surfaces with lead containing coating, the Contractor shall employ measures to minimize the exposure of workers and FAA employees to air-borne lead dust. It shall be assumed that existing paint on walls and ceilings contains some lead. A negative exposure assessment has been done for the Los Angeles Air Route Traffic Control Facility.
The Contractor shall follow one of the two procedures below when drilling into painted surfaces. All Contractor’s personnel drilling into such surfaces shall be certified to have attended a two hour Lead Awareness class. For Contractor’s personnel not certified, the FAA will conduct a 2 hour Lead Awareness Class after the pre-construction conference.
1. Manufactured Shroud Attachment
a) Identify and mark locations for drilling.
b) Securely attach shroud to the drill.
c) Attach HEPA vacuum hose to drill shroud and duct tape connection. Con-nection shall be airtight.
d) Turn on HEPA vacuum.
e) Place drill bit on marked location.
f) Make sure the shroud makes full contact with a flat surface.
g) Drill hole.
h) When finished drilling, leave HEPA vacuum running, turn drill/shroud up-right to keep any dust and debris within the shroud to where it will be col-lected by the vacuum.
i) Wipe off drill bit with a wet rag or wet cloth.
j) The shroud shall be sealed with duct tape when not in use.
k) HEPA vacuum dust and debris from the drilled hole.
l) Cover drilled hole with duct tape.
m) HEPA vacuum floor and/or wipe with wet rag or cloth.
n) HEPA vacuum and wet wipe drill and shroud upon completion of drilling ac-tivities.
2. PVC Attachment
a) Identify and mark locations for drilling.
b) Attach HEPA vacuum hose to side opening of a PVC tee fitting. Duct tape connection. Connection shall be airtight. Place duct tape over the top open-ing of the tee.
c) Turn on HEPA vacuum.
d) Push drill bit through duct tape over the top of the tee and place drill bit on marked location.
e) Make sure the bottom of the tee makes full contact with a flat surface.
f) Drill hole.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUMMARY 011000 - 8
g) When finished drilling, leave HEPA vacuum running, turn drill/tee upright to keep any dust and debris within the tee to where it will be collected by the vacuum.
h) Wipe off drill bit with a wet rag or wet cloth.
i) The tee shall be sealed with duct tape when not in use.
j) HEPA vacuum dust and debris from the drilled hole.
k) Cover drilled hole with duct tape.
l) HEPA vacuum floor and/or wipe with wet rag or cloth.
m) HEPA vacuum and wet wipe drill and tee upon completion of drilling activi-ties.
PART 2 - PRODUCTS
2.1 Asbestos Free Materials. All materials used on the project shall be certified asbestos free.
Provide letters of certification for the project at completion.
2.2 Lead-Free Materials. Paints and coating materials shall be certified lead-free. Provide letters of certification for the project at completion.
2.3 Low and Zero VOC. Paints and coating materials shall comply with the California Code of Regulations permissible level. Any field applied painting and coating shall be zero VOC.
END OF SECTION 011000
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUBMITTALS 013000 -1
SECTION 013000 - SUBMITTALS
PART 1 – GENERAL
Applicable provisions of this Section and other provisions and requirements of the Contract Documents apply to all sections.
1.1 SUMMARY
A. Submit Shop Drawings, product data, samples, warranties, certificates, test reports, operations/maintenance instructions, and parts lists as required by the contract documents.
B. Notice to Begin Construction: The Government will not issue notice to the Contractor to begin construction until all submittals for the Work have been received and approved.
1.2 RELATED REQUIREMENTS
A. Section 017700: Closeout Procedures
1.3 SUBMITTALS
Submittals required include, but are not necessarily limited to, the following:
A. Contractor’s construction schedule
B. Shop Drawings
C. Product Data, including Material Safety Data Sheets (MSDS)
D. Quality assurance submittals
E. Certificates
F. Warranty Information
G. Operation and Maintenance Manuals
H. Site Specific Accident Prevention and Safety Plan
I. Site Specific Hazcom Plan
1.4 SUBMISSION REQUIREMENTS
A. Number of Copies - Submit prepaid and in ample time for approval before installation.
Unless otherwise noted, submit four (4) copies of documents to the Contracting Officer Representative (COR). Two (2) copies will be retained by the COR. If additional copies are required, provide the quantity and submit additional copies to meet this requirement.
B. Time for Approval - Receive submittal approvals prior to starting the work. Time necessary for government approval or disapproval of samples, certificates, test reports, and shop drawings will not be more than twenty-one (21) calendar days after receipt of a submittal. All materials installed in the work shall match the approved submittals. After a submittal has been approved, no substitutions will be permitted without written
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUBMITTALS 013000 -2
approval by the COR. No extension of Contract Time will be authorized because of failure to transmit to the COR sufficiently in advance of the Work to permit processing.
The Contractor shall note priorities, if any, desired in the review of submittals; otherwise, submittals will be reviewed in the order received.
C. Submittal Approval - The checking, marking or approval of the submittal by the FAA shall not be construed as a complete check, but will indicate only that the product or method of construction and detailing is satisfactory. Approval will not relieve the contractor of the responsibility for compliance with the specifications or for any error which may exist. The Contractor shall be responsible for the dimensions and design of adequate connections, details, and satisfactory construction of all work. Possible approval actions taken by the FAA include:
1. Approved as submitted - If "approved as submitted" is marked by the COR, each copy of the submittal will be identified as having received such approval by being stamped and dated. After submittal has been approved, no substitutions will be permitted without written approval by the COR.
2. Approved as noted - If "approved as noted" is marked by the COR, the submittal is satisfactory contingent upon Contractor acceptance of corrections, notations, or both, and if accepted, does not require resubmittal.
3. Not approved - If "not approved" is marked by the COR, the submittal data does not meet job requirements and the Contractor must resubmit. If the submittal is disapproved, the Contractor shall resubmit the corrected material in the same quantity as specified for the original submittal. Correct disapproved submittals and resubmit for approval by the COR. Approval of resubmittals require an additional twenty-one (21) calendar days.
4. Submittal Schedule - Identify within the Contractor’s Construction Schedule a schedule of submittals for shop drawings, material approval, etc., showing the dates when submittals will be submitted for the project.
a) Contents - On the schedule indicate the following information:
1) Schedule date for submittal
2) Related Section number.
3) Submittal category (Shop Drawings, Product Data, or Samples).
4) Name of the subcontractor (if applicable)
5) Description of the part of the Work covered.
5. Distribution - Following response to the initial submittal, print and distribute copies to the COR, Government, subcontractors, and other parties required to comply with submittal dates indicated. When revisions are made, distribute to the same parties. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in construction activities.F
6. Schedule Updates - Revise the schedule after each meeting or activity where revisions have been recognized or made.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUBMITTALS 013000 -3
D. Construction Progress Schedule – The progress chart to be prepared by the Contractor pursuant to the Contract Clause entitled “SCHEDULES FOR CONSTRUCTION CONTRACTS” shall consist of network analysis system, or pertchart (barchart).
1. The diagram shall show a continuous activity flow from left to right. The diagram shall show the sequence in which the work is to be accomplished as planned by the Contractor.
2. Dates shall be shown on the diagram for start of the project, any milestones required by the contract, and contract completion.
3. The critical path shall be clearly identified.
4. Network activities shown shall include submittal and review of shop drawings and samples and procurement of materials and construction activities.
5. Government activities that affect progress shall be shown. These include but are not limited to: Notice-to-Proceed, approvals, and inspections.
NO PHYSICAL CONSTRUCTION WORK AT THE SITE MAY TAKE PLACE UNTIL THE
CONTRACTOR SUBMITS AND THE GOVERNMENT APPROVES THE SCHEDULE.
Government review of schedule submittal(s) will not exceed 21 calendar days. Resubmittal, if necessary shall not exceed 21 calendar days.
E. Two-week "Look Ahead" schedule - This schedule may be of the contractor's choosing, either bar chart or CPM form. Only activities scheduled to be occurring during the forecasted two week time periods are to be shown. Schedules shall be submitted weekly.
Early and Late Start and Finish dates, and subcontractors involved are data to be included in the schedule.
F. Submittals - Submit shop drawings, material and equipment lists, and all other data required under various headings of these specifications necessary to permit commencement of work. COR will return the submittals within 21 calendar days after receipt, indicating approval or disapproval.
G. Submittal Preparation - Place a permanent label or title block on each submittal for identification. Indicate the name of the entity that prepared each submittal on the label or title block.
1. Transmittals - All submittals shall be accompanied by transmittal letters identifying the contents of the submittal. It shall be clearly indicated on the transmittal letter with a statement and signature of the Contractor that the submittal item was verified for compliance with the contract requirements and approved by the Contractor. Transmittal letters shall consist of one original.
2. Contents - Submittals shall be complete and detailed and assembled into sets.
Lack of completeness or clarity or inadequate description will be justification for disapproval. Submittals shall bear the following information:
a) Name of project or facility and contract number;
b) Date of submission;
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUBMITTALS 013000 -4
c) Contract drawing number and latest revision;
d) Specification page and paragraph number;
e) Name of contractor and subcontractor or supplier/manufacturer;
f) Clearly identified contents and location of work;
g) Any proposed variances to specification requirements;
h) Contractor’s approval certifying he checked and coordinated the work of other trades.
H. Ordering of Equipment and/or Fabricated Materials – The Contractor shall not order equipment or fabricated materials until the submittals affecting these materials and/or equipment have been approved. Where the Government must redesign or change materials or equipment specifications because of unforeseen problems, the Government shall not be responsible for restock or refabrication costs of equipment and/or materials ordered by the Contractor prior to receiving approved submittals.
I. Coordination – It shall be the Contractor’s responsibility to utilize submittals to coordinate the work of different trades. Where conflicts, such as clearance problems, interferences, incompatibility with new or existing work, etc. occur, the Contractor shall notify the COR in writing immediately. Furthermore, the Contractor shall resolve all conflicts between trades with regard to Contractor’s designed work or locating of work, assuring that the work complies with contract documents.
1.5 SHOP DRAWINGS
A. Applicable Documents -
B. Presentation - Present drawings in a clear and thorough manner. Identify details by reference to sheet and detail, building wing and section shown on contract drawings.
1. Submit newly prepared information drawn accurately to scale. Highlight, encircle, or otherwise indicate deviations from the Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings. Standard information prepared without specific reference to the Project is not a Shop Drawing.
2. Shop Drawings include fabrication and installation Drawings, setting diagrams, schedules, patterns, templates and similar Drawings.
C. Contents - Provide the following information on each submittal:
1. Submittal number (paragraph 2.1 of this Section) and identify as "Part A" or "Part B" item
2. Date of submission
3. Name of project and facility (full name)
4. Name of Contractor or Subcontractor
5. Reference to drawing number (with revision, if applicable) and/or specification section.
6. Clearly identify contents and location of work.
7. Contractor's approval certifying he checked and coordinated the work of other trades.
8. Dimensions.
9. Identification of products and materials included by sheet and detail number.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUBMITTALS 013000 -5
10. Compliance with specified standards.
11. Notation of coordination requirements.
12. Notation of dimensions established by field measurement.
13. Sheet Size: Except for templates, patterns and similar full-size Drawings, submit
Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 36 by 48 inches.
D. Submittal - Submit blue- or black-line prints for the COR's review. Submit the number of copies the Contractor requires, plus three which will be retained by the COR.
1. One of the prints returned shall be marked up and maintained as a "Record Document."
2. Do not use Shop Drawings without an appropriate final stamp indicating action taken.
E. Details and Connections: Unless otherwise specified, all connections necessary to properly complete the work under these drawings and specifications shall be detailed and completed in a satisfactory manner by the Contractor. This shall apply with equal force to details not shown or specified, but necessary to make indicated or specified additions to any existing work and connection for any future additions indicated on the drawings or specified. All parts detailed by the Contractor shall be strong enough to withstand, without excessive deflection, any loads or pressures to which they are likely to be subjected and to develop the strength of the members connected. In no case shall the construction be inferior in any way to that shown on the contract drawings.
E. Equipment Clearances: The Contractor shall not proceed with any construction that may be affected in any manner by machinery and equipment until the Contractor has submitted and obtained approval of shop and erection drawings, schedules, and equipment layouts showing all components with dimensions and necessary clearances.
The Contractor is responsible to ensure that all items installed have proper clearances.
F. Related Work: In indicating or describing the work and materials for related work in the submittals, the term "by others" will not be acceptable. The specific Contractors and trades to furnish and install such related work shall be clearly noted by name or description; where such name or description is missing, it shall be understood and agreed that the General Contractor is to furnish and install such related work. Certification by the Contractor that the submittals have been checked by him shall include checking of all related work.
1.6 PRODUCT DATA
A. Collect Product Data into a single submittal for each element of construction or system.
Product Data includes printed information, such as manufacturer's installation instructions, catalog cuts, Material Safety Data Sheets (MSDS), standard color charts, roughing-in diagrams and templates, standard wiring diagrams, and performance curves.
B. Preparation
1. Clearly mark or highlight each copy to identify pertinent site specific products or models the Contractor intends to use
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUBMITTALS 013000 -6
2. Highlight/clearly indicate all performance characteristics and capacities
3. Highlight/clearly indicate all dimensions and clearances required
C. Manufacturer's Standard Schematic Drawings and Diagrams.
(a) Modify drawings and diagrams to delete information which is not applicable to the work.
(b) Supplement standard information to provide information specifically applicable to the work.
D. Drawings. Catalog data submittal shall not be construed as relieving the Contractor of the responsibility for submitting complete drawings and schedules; however, standard machinery and equipment need not be detailed, but all sizes, supports, connections, and clearances shall be indicated and detailed.
E. Manufacturer’s Instructions. Where installation of work is required in accordance with the product manufacturer’s directions, the Contractor shall obtain and distribute copies to his field personnel and at least four (4) copies to the COR.
Note: If the submittal is not clearly marked, regarding the above pertinent data, the submittal will be returned marked "DISAPPROVED".
1.7 SAMPLES
A. Submit three (3) of each sample approved for installation. Submittals include all components of the materials to be used as specified and physically identical with the material or product proposed.
B. Display - For each sample include the following:
1. Generic description of the Sample.
2. Sample source.
3. Product name or name and address of the manufacturer.
4. Catalog number
5. Project title,
6. Contrctor’s name
7. Availability and delivery time.
C. Records - Maintain sets of Samples at the Project Site, for quality comparisons throughout the course of construction.
1. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal.
2. Sample sets may be used to obtain final acceptance of the construction associated with each set.
D. Color, patterns and textures. For items required to be of selected and approved colors, patterns, textures, or other finish requirements, obtain instructions from the COR and submit suffiecient samples to show the range of shades, tones, values, patterns textures, REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUBMITTALS 013000 -7
or other features corresponding to the instructions. Submit color samples of field-applied paint materials.
D. Approved Samples. Approved samples may be incorporated in the job where applicable.
1.8 WARRANTIES/GUARANTIES
A. Assemble two (2) copies with original signatures of warranties executed by each of the respective manufacturers, suppliers, and subcontractors into a warranty book and prepare a Table of Contents.
B. Additional Data - Provide complete information for each item, include the following:
1. Product or work team
2. Firm, with name of principal, address, and telephone
3. Scope
4. Effective dates of warranty based on Final Acceptance of the item.
5. Information for owner's personnel on proper procedures to evoke the warranty in case of failure and instances which might affect the validity of warranty
C. Warranties - Effective after project completion and acceptance by the FAA.
1.9 CERTIFICATES
Assemble certificates executed by each of the respective manufacturers, suppliers, and subcontractors.
A. Additional Data - Provide complete information for each item to certify compliance with contract documents.
1. Product or work item
2. Firm, with name of principal
3. Scope of compliance
4. Signature by an officer of the manufacturer or other individual authorized to sign documents on behalf of the company.
1.10 TEST REPORTS
Promptly submit written report of each test and inspection. Each report shall include:
(a) Date issued.
(b) Project title and number.
(c) Testing laboratory name, address, and telephone number.
(d) Name and signature of laboratory inspector.
(e) Date and time of sampling or inspection.
(f) Record of temperature and weather conditions.
(g) Date of test.
(h) Identification of product and specifications.
(i) Location of sample or test in the project.
(j) Type of inspection or test.
(k) Results of tests and compliance with Contract Documents.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SUBMITTALS 013000 -8
(l) Interpretation of tests results, when requested by Contracting Officer Representative.
PART 2 – EXECUTION
3.1 GENERAL
A. Submittals are required for the items listed in the specifications or on the drawings. The following is a partial list of submittals required: Schedules, Manufacturer's Literature, Shop Drawings, Samples, Test Reports, Warranties, Certificates, Design Calculations, MSDS, and Installation Instructions. It should not be construed as a complete list of all submittals required.
B. Submittal dates shall comply with this specification unless a more stringent date is specified. Substitutions and all requested changes will require a submittal.
3.2 SCHEDULE
A. For the following particular submittals under Division 1, the submittals must be approved prior to any work on site.
B. For the following submittals of Divisions 2 thru 26, the submittals must be approved prior to any work on site involving the corresponding specification section listed.
PART 3 – QUALITY ASSURANCE
4.1 SUBMITTALS
Submittals required include, but are not necessarily limited to, the following:
A. Contractor’s construction schedule
B. Site Specific Accident Prevention and Safety Plan
C. Site Specific Hazcom Plan
END OF SECTION 013000
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SAFETY REQUIREMENTS 013526-1
SECTION 01 35 26 - SAFETY REQUIREMENTS
1.1 SCOPE
A. The objectives of the safety and health requirements are to eliminate contract generated facility shutdowns, interruptions, injuries, illness, and incidents. When the Contractor is notified by the Contracting Officer Representative (COR) of non-compliance with the safety or health provisions of the Contract, the Contractor shall immediately, unless otherwise instructed to, correct the unsafe act or unsafe condition.
It is the Contractor’s responsibility to understand the work to be performed, perform the work in a professional manner and to protect his workforce and FAA from incidents.
B. This section identifies some of the requirements of the OSHA Construction Standard.
C. Formulation of a site specific safety plan
1.2 CONTRACTOR RESPONSIBILITY
A. General Safety Provisions - The Contractor shall bear full responsibility to provide safe working conditions for its employees and Contractors. The Contractor shall not permit any employee or subcontractor to work in surroundings or under working conditions that are unsanitary, hazardous, or dangerous to the health and safety of the employee.
B. Accident Prevention - The Contractor shall bear the responsibility of maintaining an accident prevention program such that frequent and regular inspections of the job site, materials and equipment are made by a competent person designated by the employer.
C. Use of Equipment - The Contractor shall not permit the use of any machinery, tool, material, or equipment that is not in compliance with OSHA regulations. The employer shall permit only those employees qualified by training and/or experience to operate equipment and machinery.
D. MSDS Sheets – Adhesives sealants and primers used produce odorous vapors, which are a tremendous concern with the Air Traffic Controllers. Submit applicable MSDS sheets for adhesives, paints, sealants, and other VOC producing materials and chemicals used.
E. Orientation and Training – All contractor employees must complete a site and task specific orientation and test provided by the Contractor prior to tasks in FAA facilities.
Daily Safety Meetings or Tool Box Meetings are to occur before each work shift and include all Contractor on-site employees.
F. Incident Investigation – All Contractor incidents will be communicated immediately to the FAA Resident Engineer and investigated by the Contractor. An incident report and Lesson Learned must be assembled for all incidents and transmitted to the FAA for review.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SAFETY REQUIREMENTS 013526-2
G. Auditing and Inspections – The contractor must conduct safety and health inspections by qualified and competent professionals at a frequency sufficient to identify and control task specific hazards. The FAA shall not be held responsible for safety inspections to assure Contractor conformance with the OSHA safety regulations. The FAA, however, reserves the right to notify the Contractor of any deficiencies regarding worker safety.
1.3 CONTRACTOR RESPONSIBILITY
A. All contractor tasks must be communicated to the FAA prior to the tasking being performed.
1. Preconstruction Safety Meeting – The FAA will schedule a preconstruction meeting after the Notice to Proceed. The agenda will include:
a) The FAA will identify the Contracting Officer’s Representative (COR).
The Contractor will identify his site management.
b) The FAA will review the chain of authority.
c) The FAA will review the procedure to process field decisions and change orders.
d) The FAA will review the facility safety procedures, and safety and health requirements.
e) The FAA will discuss schedules, shop drawings, product data and samples, manufacturer’s certifications of products, manpower reports, equipment deliveries and priorities schedules, procedures for maintaining record documents, use of FAA facilities by the Contractor (access parking, office area, and storage), safety and first aid procedures, security procedures and housekeeping procedures.
2. Monthly Project Schedule – A detailed schedule must be submitted to the FAA monthly. The date the schedule is due will be identified during the preconstruction safety meeting.
3. Two Week Look-Ahead Schedule – Contractor shall provide a two week look-ahead schedule to the COR. The schedule shall provide specific location where work will take place, start/stop dates and the prime/sub-contractor performing the work. The activities in the schedule shall coordinate with the Activity Hazard Analysis requirement.
4. Daily Project Scope and Schedule – A detailed daily project scope and schedule must be submitted to the FAA daily. Usually the daily scope and schedule meeting is held early morning with the COR. Hot work permits, and electrical/pneumatic/water and steam lockouts are issued daily.
All safety related schedules should be coordinated with the overall work schedule required in the specifications.
5. Safety/Activity Hazard Analysis Meeting - Activity Hazard Analysis will be part of the weekly Construction meeting. In addition to the weekly construction meeting, the facility management requires a briefing to review the Project’s Activity Hazards one week before the work shall occur. This meeting typically takes 30 minutes or less and is held on Wednesday at 1:00 pm unless a different time is agreed to by the
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SAFETY REQUIREMENTS 013526-3
COR. Contractor’s superintendent and key subcontractors (as applicable) are expected to attend and explain work activity/safety protocols.
B. The FAA will evaluate the Contractor on its safety performance, including that of its Subcontractors. The number and severity of safety and security violations will be considered in this evaluation. Contractor safety violations are cause for termination for default, may result in notification of the Contractor’s bonding company, and will affect the Contractor’s opportunity to propose on future work. Failure to correct such deficiencies may impact the Contractor’s ability to work on future FAA contracts.
1.4 OSHA REGULATIONS
A. The Contractor shall comply with the latest Occupational Safety and Heath Administration regulations (CFR 29 Part 1926) regarding safety in the work area.
B. The Contractor shall be responsible for obtaining copies of non-FAA referenced documents without additional cost to the FAA. At Contractor request, a copy of FAA directives may be obtained by contacting the Contracting Officer representative (COR).
C. The Contractor is not relieved from adhering to other OSHA requirements not listed herein. The Contractor shall consult the latest referenced OSHA documents for safety regulations.
1. Documents:
a) OSHA Documents:
1) CFR 29 Part 1926 Safety and Health Regulations for Construction
2) CFR 29 Part 1910 General Industry Standards Applicable to
Construction Industry
2. FAA Documents:
a) FAA Order 3900.49 Control of Hazardous Energy During Maintenance, Servicing and Repair.
b) FAA Order 3900.19B Occupational Health and Safety Program.
1.5 TASK SPECIFIC HEALTH AND SAFETY PLAN
All tasks are to be planned and scheduled. All plans must be written and submitted for FAA approval before tasks are performed. The Contractor must develop and implement a site specific comprehensive Health and Safety Plan (HASP) based on the scope of work, for his or her employees as well as others in the area and the properties around. It shall cover all aspects of onsite construction operations and activities associated with the contract. This plan must comply with federal safety and health standards (29 CFR 1910 General Industry, 29 CFR 1926 Construction Industry, FAA Order 3900.19B Occupational Safety and Health Program) other applicable health and safety regulations and any project-specific requirements. The Contractor must provide the Contracting Officer with a copy of this plan. Acceptance of the Contractor's HASP only signifies that the plan generally conforms to the requirements of the contract. It does not relieve the Contractor of the responsibility for providing with a safe and healthful work environment. Asbestos containing materials, lead containing coatings, polychlorinated biphenyls, noise and odors are to be controlled. Required elements of the HASP must include:
A. Provide the workplace address; name and address of the principal contractor; key personnel, phone numbers and addresses.
REPLACE PARKING LOT LIGHTS AND POLES JAN 2024
SAFETY REQUIREMENTS 013526-4
B. Estimated duration of the work
C. Coordinate the HASP with the Project Work Plan
D. Tasks are to be described in detail. All physical and chemical hazards identified, and engineering controls are to be incorporated to eliminate or reduce the hazard.
E. An Emergency Response and Contingency Plan must be assembled including, where applicable, consideration for fire, explosion, toxic or oxygen deficient atmospheres, water leakage, electrical hazards, slips, trips and falls, confined spaces, heat/cold stress, noise and odors. This should also include an Emergency Action Plan and Medical Surveillance.
F. Hazard assessment and identification of the hazards in the scope of work, hazard communication methods, and how the controls will be implemented.
G. Material Safety Data Sheets (MSDS) must be submitted to FAA for all chemicals brought on-site by the Contractor before the chemical is brought on-site.
H. Personal Protective Equipment – Hard hats (ANSI Z89.1 or equivalent) must be worn at all times where overhead hazards exist regardless of the workers activities. Shirts with at least 4-inch sleeves and appropriate pants shall be worn. Tank tops and shorts are not permitted. Loose or frayed clothing, loose or hanging long hair, ties, rings, body jewelry shall not be worn around moving machinery or other areas where they may become tangled. High visibility shirts, vests, or coats (ANSI/ISEA 107-2004) must be worn at all times while on the project site. Hearing protection must be worn when exposures exceed 85 dBA-TWA. Hard-toe footwear (ASTM F2413, or equivalent) must be worn by all workers when in the construction environment or in areas where there is a danger of foot injuries due to falling, rolling, or piercing objects. Safety glasses with rigid side shields (ANSI Z87.1, or equivalent) must be worn at all times when in the construction environment and in any area where eye hazards exist. Gloves, appropriate for the hazard, must be worn when hands are exposed to physical or chemical hazards.
I. There is a 100% Fall Protection Policy at FAA facilities. Anytime employees are working from an unprotected elevation of six feet or more, fall protection must be incorporated. Working means while traveling, stationary, or at any time exposed to a fall from a surface not protected by approved handrails, guardrails or some other approved fall prevention device. Workers in mechanical lifts, including scissors lifts, boom trucks, suspended or supported personnel baskets, articulating lifts, and other similar devices must use fall protection equipment at all times.
J. Equipment and tools must not be altered…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .