Technical Specifications for

Acton Road Gravel

BUREAU OF LAND MANAGEMENT

5001 Southgate Drive Billings, Montana 59101

January 2021

ACTON ROAD GRAVEL

TABLE OF CONTENTS

TABLE OF CONTENTS

SPECIFICATIONS PAGE NO.

SECTION MT-01009 – GENERAL INFORMATION & REQUIREMENTS..1 – 4

SECTION MT-01505 - MOBILIZATION........................1 – 1

SECTION MT-02201 - WATERING............................1 – 2

SECTION MT-02233 – CRUSHED AGGREGATE BASE COURSE.......1 – 3

SECTION MT-17301 – ROAD MAINTENANCE....................1 – 5

GENERAL INFORMATION AND REQUIREMENTS

MT-01009-1

SECTION MT-01009

GENERAL INFORMATION AND REQUIREMENTS

PART 1: GENERAL

1.01 SUMMARY:

A. Description of Work: Furnishing labor, equipment, supplies, and materials, to:

• Re-establish road typical section and grade on 4.88 lane miles of road.

• Provide adequate soil moisture when and where natural conditions are not suitable to conduct road maintenance activities.

• Furnish, spread, and compact Crushed Aggregate Base Course as awarded and directed by the Contracting Officer Representative.

B. Location: Work under this Contract is located approximately 27 miles north of Billings, Montana at the Acton Recreation area in Yellowstone County, Montana, near the Towns of Acton, Montana and Broadview, Montana. The work location is shown on the maps.

C. Drawings and Maps: The drawings and maps designate the type and quantity of work required at the project location.

1.02 REFERENCES:

A. Referenced Specifications/Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/standards referred to herein may be procured by the Contractor, from the following:

ASTM American Society for Testing and Materials 1916 Race Street Philadelphia, PA 19103

FP Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects Superintendent of Documents Government Printing Office Washington, DC 20402

Fed. Spec. Federal Specification/Standard General Services Administration Specifications Branch Room 6039, GSA Building

MT-01009-2

Seventh and D Streets, S.W.

Washington, DC 20407

MDT Standard Specifications for Road and Bridge Construction, 2014 Edition Montana Department of Transportation Contract Plans Section 2701 Prospect Avenue Helena, MT, 59620

MUTCD Manual on Uniform Traffic Control Devices for Streets and Highways Superintendent of Documents Government Printing Office Washington, DC 20402

OSHA Occupational Safety and Health Administration's Standards U.S. Department of Labor Occupational Safety and Health Administration Denver Area Office 333 West Colfax Avenue Denver, CO 80204

*Federal Specifications and catalogs may be obtained at Business Service Centers of Regional Offices of the General Services Administration. (Washington, DC; Boston, MA; New York, NY;

Philadelphia, PA; Atlanta, GA; Chicago, IL; Kansas City, MO; Fort Worth, TX; Denver, CO; San Francisco, CA; and Auburn, WA.)

1.03 PROJECT SCHEDULE/SEQUENCE OF OPERATIONS

A. Submit a project schedule for review after the Notice to Proceed to illustrate the sequencing and time allotted for the road work, and each portion of the road work, in order to achieve completion of the work within the time limit specified in the contract. The schedule shall include the following:

1. Breakdown of grading, to allow monitoring of progress of work.

2. Sequence of graveling, grading, and compaction operations with start dates, duration, and finish dates.

3. When requested, the Contractor shall submit an updated schedule within 3 working days.

1.04 VALUE SCHEDULE

A. The Value Schedule shall be presented at the Pre-work Conference.

MT-01009-3

The Value Schedule shall contain similar itemization to the progress schedule, so that adherence to the work schedule, as well as appropriate progress payment amounts, can be readily determined.

The Value Schedule shall indicate the dollar value of each major work item. Estimated quantities of major work items are shown on the Drawings and Bid Value Schedule, and at a minimum, the submitted Value Schedule shall include similar detail for all work to complete the project.

1.05 QUALITY ASSURANCE:

A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.

B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.

1.06 PROJECT/SITE CONDITIONS:

A. Access to the Work: Access to the work is by state, county, and Bureau of Land Management (BLM) roads.

B. Environmental Considerations:

1. The aesthetic values of the sites and surrounding areas are of prime importance. The contractor shall take all care necessary to preserve all plant life and other natural features. Travel of motor vehicles and heavy equipment shall be limited to existing roads and parking areas. Soil disturbance shall be limited as much as practical. No off-road travel is permitted except for minimal turn-around areas. Any surface damage outside the project areas shall be corrected by the Contractor at their expense.

2. All vehicles and equipment shall be power washed before transportation to the sites, to prevent the spread of weed seeds.

3. While working along stream areas or wetlands, precaution shall be taken to avoid spilling materials into the stream.

PART 2: PRODUCTS

(There are no applicable requirements).

PART 3: EXECUTION

MT-01009-4

3.01 PROJECT MEETINGS:

A. Pre-Work Conference:

1. A pre-work conference will be held prior to the start of work.

The Contractor will be notified in advance of meeting time, date, and location. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.

2. The Contractor, Subcontractors, and the persons responsible for coordination of the work shall be present at the meeting.

3. The Contractor shall be prepared to summarize and explain procedures planned for the project, and present the construction schedule and value schedule.

B. Progress Meetings:

1. Meetings shall be held at the project site, or as determined by the Contracting Officer.

2. Meetings may be called by either the Contracting Officer or the Contractor. Requests shall state who should attend and include an agenda.

C. Final Inspection:

1. Meeting shall be held at the project site, or as determined by the Contracting Officer.

2. The Contractor shall notify the Contracting Officer in writing at least 5 working days before the completion date so the Government can schedule final inspection.

3. The Contractor shall require the superintendent to be present during this inspection.

PART 4: MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT:

A. Units: The work described in this section will not be measured for payment.

4.02 BASIS OF PAYMENT:

A. Payment: No direct payment for the work described under this section will be made. The Contractor shall include consideration

MT-01009-5

for this item in the bid price for other items of the Contract.

END OF SECTION

MOBILIZATION

MT-01505-1

SECTION MT-01505

MOBILIZATION

PART 1: GENERAL

1.01 SUMMARY:

A. Section Includes: Preparatory work and operations, including those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; and for other work and operations which must be performed, or costs incurred prior to beginning work on the various work items on the project site.

PART 2: PRODUCTS

(There are no applicable requirements).

PART 3: EXECUTION

(There are no applicable requirements).

PART 4: MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT:

A. Units: Progress payments will be made as follows:

1. Mobilization will be measured and paid for once the work commences for the site per the following completion of work:

a. When 5 percent of the amount is earned from the total contract amount, 50 percent of the amount bid for mobilization will be paid.

b. When 10 percent of the amount is earned from the total contract amount, 100 percent of the amount bid for mobilization will be paid.

4.02 BASIS OF PAYMENT:

A. Payment: Prices and payment will be full compensation for the work described in this section. No modification and adjustments shall be allowed for costs and changes to mobilization despite changes in fuel or transportation costs. Payment will be made under:

Pay Item Pay Unit

MT-01505(1) Mobilization Lump Sum

WATERING

MT-02201-1

SECTION MT-02201

1.1 SUMMARY:

A. Section Includes: Distributing and applying water required for compaction of aggregate base course, for dust control, and when directed by the Contracting Officer for achieving satisfactory moisture conditions during maintenance operations.

1.2 REFERENCES:

A. American Association of State Highway and Transportation Officials

AASHTO T 239-86 Moisture Content of Soil and Soil-Aggregate in

Place by Nuclear Methods (Shallow Depth)

B. American Society for Testing and Materials

ASTM D698 Standard Test Methods for Laboratory Compaction

Characteristics of Soil using Standard Effort.

1.3 PROJECT/SITE CONDITIONS:

A. Water Source: The Contractor is responsible for obtaining a water source for filling operations that complies with all federal, state, and local laws. Water sources located on Bureau of Land Management will be approved on a case by case basis by the Contracting Officer. Submit the water source selection to the Contracting Officer for approval prior to the start of construction.

2.1 MATERIALS:

A. Water: Shall be clean and free from deleterious materials.

2.2 EQUIPMENT:

A. Requirements: Provide necessary pumping equipment and water trucks.

Water trucks shall be equipped with a pressure pump and spray bar of adequate capacity and design to ensure uniform application of water in the amounts designated. Provide manufacturer’s certification of the storage volume of each water truck used on the project.

MT-02201-2

3.1 APPLICATION:

A. Requirements: Water shall be applied in such a manner to ensure uniform moisture content.

B. Compaction: The amount of water added or applied shall be sufficient to obtain the percent relative compaction required.

Materials to be compacted shall be within 3% of the laboratory theoretical optimum moisture content for that material during compaction.

C. Dust Control: Water dry material to prevent dust on the project site, waste site, and haul roads to the waste sites.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT:

A. Units: Water for compaction of aggregate base course or dust control will not be measured for payment. Watering directed by the Contracting Officer for achieving appropriate moisture during maintenance operations will be measured and paid for per gallon rounded to the nearest 1000 gallons.

4.2 BASIS OF PAYMENT:

A. Payment: No direct payment for watering for the compaction of aggregate base course or dust control will be made. The Contractor shall include consideration for this item in the bid price for other scheduled items of the Contract. For Watering directed by the Contracting Officer, the accepted quantities will be paid for at the Contract price per unit of measurement, respectively, for the pay item shown in the Bid Schedule. Price and payment shall be full compensation for furnishing and delivering all material, including source selection and approval, labor, equipment, tools, and incidentals necessary to complete the work described in this section. Payment will be made under:

Payment Pay Unit

MT-02201(1) Watering Directed By The Contracting Officer. . .Gallons

CRUSHED AGGREGATE BASE COURSE

MT-02233-1

SECTION MT-02233

1.01 SUMMARY:

A. Section Includes: Contractor to supply crushed aggregate base course material and delivery. The material is to be transported and spread meeting the requirements of SECTION MT-17301 on the Heag Road at the Bureau of Land Management Acton Recreation Site located near Acton, Montana and Broadview, Montana: see attached drawings.

The material and delivery shall be in accordance with the specifications and drawings.

1.02 CERTIFICATE OF CONFORMANCE:

A. Certification: Contractor to submit one copy of written certification that the Supplier-furnished crushed aggregate base course material to be delivered, spread, and compacted conforms to the requirements of this specification section.

Supplier shall include in the submittal test results from a

Certified Geotechnical Laboratory. Samples shall be obtained from the stockpile of material to be used on this project at the time of delivery. The certified test results are:

1. Sieve Analysis according to ASTM C136 and C117.

2. Atterberg limits according to ASTM D4318.

3. Percentage of Mechanically Fractured Particles according to MT- 217.

4. Material proctor compaction test information for optimal moisture content and maximum dry density according to ASTM D698.

2.01 MATERIALS: Shall be in conformance with the following

requirements:

A. General: Aggregate materials shall be free from vegetative matter, snow, ice, and other deleterious substances, and shall not contain an excess of thick or elongated particles.

B. Crushed Aggregate Base Course: Aggregate base course material to be delivered to this project shall meet the following gradations, MT-02233-2 including added binder or blending material if necessary, to meet the requirements:

1 INCH GRADATION & REQUIREMENTS:

Sieve Size Percent Passing

1 inch 100 percent

No. 4 30-70 percent No. 8 25-60 percent No. 200 3-12 percent

1. The Maximum liquid limit for the material passing the No. 40 sieve is 35.

2. The Plasticity Index for the material passing the No. 40 sieve shall be between 0 and 6.

3. At least 35 percent by weight of the aggregate retained on the

No. 4 sieve must have at least one mechanically-fractured face.

Test for determining percentage of mechanically fractured particles shall be according to MT-217.

2.02 TRUCKS & DELIVERY REQUIREMENTS:

A. Delivery: Contractor shall deliver material or have a supplier deliver the material by truck with a minimum truck capacity of 10 cubic yards each capable of dumping material in a spread windrow.

1. The aggregate base course material shall be spread and compacted on the road as directed by the Government in the field.

B. Delivery Dates: Contractor shall schedule material delivery dates so that the material can be placed, spread, and compacted the same day that the material arrives on site. Contractor shall keep the Contracting Officer informed of material delivery dates and times, and provide them with a minimum of 48 hours’ notice of any deliveries that may vary from the Contractor’s original schedule.

PART 3: MEASUREMENT AND PAYMENT

3.01 METHOD OF MEASUREMENT:

MT-02233-3

A. Units: The work described in this section for crushed base course aggregate will be measured and paid for by the ton of material transported, spread, and compacted on Heag Road near the Acton Recreation Site. Determination of quantities shall be as follows:

1. Loose Material hauled shall be weighed at a certified scale and tickets given to the Government.

3.02 BASIS OF PAYMENT:

A. Payment: The accepted quantities will be paid for at the Contract price per unit of measurement, respectively, for the pay item shown in the Bid Schedule. Price and payment shall be full compensation for furnishing and delivering all material, including all test requirements, labor, equipment, tools, and incidentals necessary to complete the work described in this section. Payment will be made under:

Payment Pay Unit

MT-02233(1) Crushed Aggregate Base Course. . . . . . . . . . . Ton

ROAD MAINTENANCE

MT-02233-1

SECTION MT-17301

1.01 WORK INCLUDED:

A. Description: Work consists of smoothing, scarifying, processing, and shaping existing road to restore typical sections as designated on the drawings; restoring proper drainage; remixing existing aggregates; and spreading and compacting new crushed aggregate base course to the designated typical sections.

B. Related Sections:

General Information and Requirements SECTION MT-01009 Mobilization SECTION MT-01505 Crushed Aggregate Base Course SECTION MT-02233 Watering SECTION MT-02201

1.02 DEFINITIONS

A. Smoothing is dragging the grader blade across the road to level the surface and drag excess material away. Smoothing does not cut the surface crust.

B. Reshaping the road surface requires cutting through the crust to remove potholes, washboards, and ruts. The material is mixed to provide a blend of different size aggregates, and distributed across the roadway.

C. Scarifying is breaking up the old surface crust, using the ripper teeth of the grader.

D. Processing is mixing the aggregate material to incorporate or remove moisture and blend the various sizes of material.

E. Spreading is evenly distributing the new crushed aggregate base course across the roadway at a depth in accordance with the typical section and drawings.

F. Compacting the new crushed aggregate base course involves using equipment and machinery to compress the aggregate in the roadway until it reaches a density value a minimum of 95% its theoretical maximum density at a moisture content within 3% of optimum.

1.03 PROJECT CONDITIONS:

A. Moisture Conditions: Whenever the Contractor or the Contracting Officer determines that the moisture conditions prevent obtaining a satisfactory job, work will stop and will not be resumed until moisture conditions are favorable, or until the Contracting Officer requests watering of the road to achieve appropriate moisture conditions.

Measurement and payment for Watering directed by the Contracting

MT-02233-2

Officer shall be per SECTION MT-02201. This requirement may be waived when the Contracting Officer requests grading be done by a specified date.

B. Public Safety and Signing: The Contractor and any contractor suppliers shall exercise due caution and care when operating equipment to prevent undue conflict with public users of the road.

1. A reflectorized "Slow Moving" vehicle symbol shall be attached to the rear of all appropriate equipment.

2. Post warning signs on both ends of the section of road being worked

on. Signs shall be moved as needed so that a sign does not precede the machinery more than one mile. Signs shall be of the size, style, and color required in the current edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways - MUTCD".

3. Berms, windrows, or other obstructions shall not be left in the roadway overnight or on weekends.

1.04 QUALITY ASSURANCE:

A. Failure Criteria: Not limited to the following:

1. Compaction of new road base course. The new road base course surface shall be compacted to 95% of the theoretical laboratory maximum density (as determined by ASTM D698) while the material is within 3% of the optimum moisture content. Density testing may be performed by BLM personnel at the Contracting Officer’s discretion using a Nuclear Densometer.

2. Formation of pools of moisture on road surfaces. Site drainage shall be considered to be of prime importance.

3. Settlement of fill. All material placed as fill shall be compacted to a minimum of 95% the theoretical laboratory maximum density (as determined by ASTM D698) within 3% of the laboratory optimum moisture content. Density testing may be performed by BLM personnel at the Contracting Officer’s discretion using a Nuclear Densometer.

4. Flow of moisture toward, or entrapment against, cattleguard and culvert foundations.

5. Grading of material into cattleguard grids or pits, road ditches, streams, rivers, wetlands, springs, or other waterways.

(There are no applicable requirements.)

MT-02233-3

3.01 INSTALLATION

A. Ditches: Ditch cleaning is not required in this contract. The contractor shall avoid driving machinery and vehicles in road ditches. Any ruts created in the ditches, loss of vegetation in the ditches, or damage to the ditch slopes caused by the contractor will be repaired and reseeded at no cost to the Government.

B. Culverts: Culvert cleaning is not required in this contract. In the event culverts, end sections, or both are damaged due to actions of the Contractor, repairs or replacement shall be made at no cost to the Government.

C. Slough Material: Slough material may be bladed across the road, provided it is not deposited in potholes, washes, or ruts in the roadbed. The material shall not be side-cast into streams, streambeds, creeks, wetlands, or springs.

D. Scarification: Where potholes, washboards, or ruts are over 1” deep, scarify to a minimum depth of 3-4 inches below the road surface, process the material, and reshape the surface.

E. Road width: Road widths shall be those from the designated typical sections as shown on the project drawings.

F. Grades: Grades shall be maintained according to the designated typical sections as shown on the project drawings, or maintained as uniform slopes where elevations change. Abrupt changes in slopes shall be rounded.

G. Blading: Blading of road surfaces will be done to minimize the loss of aggregate material. High blading, which is merely filling depressions with loose material, will not be acceptable. Berms or ridges shall not be left along the shoulders, except where required for safety. During the blading operation, material shall not be graded into cattleguard pits. All loose rock larger than 3 inches shall be removed from the roadbed.

1. Double lane roads will be crowned at 3%, except on corners. Corners will be superelevated per the direction of the COR. Make smooth transitions between the crown and superelevated cross sections.

2. Sections of roads constructed with roadside ditches shall be bladed and reshaped to drain the water from the roadbed. The cross section shall match the designated typical sections as shown on the project drawings and follow Part 3.01.G.1.

H. Spread the new crushed aggregate base course evenly across the road to widths and depths in accordance with the typical sections detailed on

MT-02233-4

the construction drawings, or at the discretion of the Contracting Officer.

I. Sufficiently compact the new crushed aggregate base course using a smooth drum roller or equivalent. Compact the new crushed aggregate base course to a minimum of 95% the theoretical laboratory maximum density (as determined by ASTM D698) within 3% of the laboratory optimum moisture content.

J. New Road Base Course Material: All road base course material transported to the site will be used to surface the road. Depths may vary depending on the portion of the road and its need, as directed by the Contracting Officer. If the Contracting Officer feels that the road is sufficiently surfaced and meets the minimum requirements of the typical sections of the drawings, a small amount of material may be added to the existing gravel pile near the Acton Recreation Area parking lot for future maintenance projects, as directed by the Contracting Officer.

K. Disposal of Unsuitable Material: Unsuitable material, including rock and boulders that cannot be used in road embankment, shall be disposed of away from the road, pads, or parking lots. Unsuitable material shall not be left as berms or ridges and shall not be left where it can block flow to ditches or culverts. The material shall not be side-cast in road ditches, cattleguard grids or pits, streams, streambeds, creeks, wetlands, or springs. Coordinate disposal efforts with the Contracting Officer for approval.

PART 4: MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT

A. Units: The work described in this section and on the Work Data Sheet will be measured and paid for per Lane Mile for Road Maintenance. Total road lane miles equals linear miles of road multiplied by number of lanes. A lane is defined as any road segment less than 15’ in width.

Any road segment over 15’ wide is considered 2 lanes.

B. Units: The work described in this section to smooth, scarify, process, and shape existing road to restore typical sections as designated on the drawings; restoring proper drainage; and remixing existing aggregates will be measured and paid for by the Lane Mile under MT-17301(1) Road Maintenance. This work is to include all materials, equipment, labor, tools, and incidentals.

C. Units: The work described in this section to spread and compact new crushed aggregate base course to the designated typical sections will be paid for by the Lane Mile under MT-17301(2) Road Maintenance - CABC.

This work is to include all materials, equipment, labor, tools, and incidentals, excluding the crushed aggregate base course which will be paid under MT-02233(1) Crushed Aggregate Base Course.

MT-02233-5

4.02 BASIS OF PAYMENT

A. Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:

Pay Item Pay Unit

MT-17301(1) Road Maintenance . . . . . . . . . . . . . . . Lane Mile

MT-17301(2) Road Maintenance - CABC . . . . . . . . . . . . Lane Mile

Acton Road Gravel - Specifications.pdf
Acton Road Gravel - Specifications.pdf
2021 Acton Road Gravel - 00000 - SPECIFICATIONS COVER SHEET.pdf
2021 Acton Road Gravel - 00001 - TOC.pdf
2021 Acton Road Gravel - 01009 - GENERAL INFORMATION & REQUIREMENTS.pdf
Acton Road Gravel - Specifications
Acton Road Gravel - Specifications.pdf
2021 Acton Road Gravel - 01505 - MOBILIZATION.pdf
2021 Acton Road Gravel - 02201 - WATERING.pdf
PART 1: GENERAL