This statement of work document outlines requirements for a fiber optic cable replacement project at Andersen Air Force Base in Guam. The project requires replacing cable 101 with single-mode fiber optic cable from building B20011 to buildings B2800 and B20008, including installing new channel banks at buildings B2800 and B18015. The contractor must provide design and construction services, with submissions due 60 and 100 days after award and ready for construction documents due 14 days after approval of the 100% submission. Key requirements include installing conduit, innerducts, fiber optic cable with maintenance loops, splicing, testing, and grounding in accordance with specified standards. The contractor must also conduct surveys, develop monitoring plans for archaeological and hazardous materials, and restore sites after completion.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPLACE CABLE 101 FROM B20011 TO B2800 AND B20008 AJJY 23-1060
ANDERSEN AIR FORCE BASE, GUAM
36TH CIVIL ENGINEER SQUADRON
REPLACE CABLE 101 FROM B20011 TO
B2800 AND B20008,
DESIGN-BUILD PROJECT
PROJECT NO.: AJJY 23-1060
30 JUNE 2023
REPLACE CABLE 101 FROM B20011 TO B2800 AND B20008 AJJY 23-1060
TABLE OF CONTENTS
PART 1 STATEMENT OF WORK
PART 2 ATTACHMENTS
Attachment 1: Location & Site Maps
Attachment 2: Partial Electrical Site Plan, (Notional & Reference Only)
PART 1
STATEMENT OF WORK
Table of Contents
CHAPTERS
1. PROJECT DESCRIPTION
2. PROJECT OBJECTIVES
3. SITE ANALYSIS
4. BUILDING/FACILITY REQUIREMENTS
5. ROOM REQUIREMENTS
6. ENGINEERING SYSTEM REQUIREMENTS
1.PROJECT DESCRIPTION
1.1 OVERVIEW: This is a “Design‐Build” project to support replacement Cable 101 with fiber optic cable (FOC) from B20011 to B2800 and B20008. This includes the supply and installation of new two (2) channel banks for Tactical Air Navigation System (TACAN) B2800, and Air Traffic Control Tower (ATCT) B18015.
1.2 EXISTING OPERATIONS: The construction work activities will be performed in a manner as to NOT negatively impact the existing operational capabilities of the building occupants and adjacent facilities.
Contractor shall minimize interruption to the on‐going operations. Contractor shall coordinate for interruption of utility services. All other actions not involving interruption of services can be conducted during regular working hours. In the event work/project activities other than what is indicated in this project program is to occur simultaneously, contractor shall verify, coordinate, and may be required to phase such work/project activities.
1.3 LOCATION OF WORK: The project is located at Andersen Air Force Base, Guam. See attached site map.
2. PROJECT OBJECTIVES
2.1 SCOPE OF WORK: The contractor shall provide all labor, materials, equipment, permit and clearances, architectural and engineering services, transportation, supervision, and other incidental work required for the project. Other incidental work required includes any and all items and considerations necessary to ensure a complete and usable final product, including, but not limited to, the necessary design and construction considerations not specifically stated elsewhere in this statement of work. Complete and usable final product means that the completed final product is finished throughout and can be used to fully satisfy the requirements and the intended purpose of the project.
To support replacement cable 101 with fiber optic cable (FOC) from B20011 to B2800 and B20008. This includes the supply and installation of new two (2) channel banks for Tactical Air Navigation System (TACAN) B2800, and Air Traffic Control Tower (ATCT) B18015, see attached site plan.
2.2 WORK PHASING AND RELOCATION WORK: The work shall be phased as the current building occupants are to remain in the building and will require minimal impact to their operations. Contractor shall provide a work phasing plan/schedule that includes the temporary power supply for each facility.
Provide estimate power outage for each pad‐mounted switch to be removed and replaced.
Provide at least 30 calendar days written notice to the building facility. Planning & Coordination: Plan, coordinate and execute temporary power supply with emergency generators to affected building facilities during the removal and replacement of the pad‐mounted switches.
Contractor shall provide a work phasing plan/schedule in accordance with UFC 3‐501‐01, 2‐1.6 Scheduling and Sequencing Outages.
2.3 SPECIFIC REQUIREMENTS.
Provide and install a new 12 Strand Single Mode (SM) Fiber Optic Cable (FOC) from Information Transfer Building (ITB) 20011 to Building (B) 20008 (Military Gas Station) and B2800 (TACAN) at Andersen AFB Guam.
Provide and install new two (2) Chanel Banks for Tactical Air Navigation System (TACAN) B2800, and Air Traffic Control Tower (ATCT) B18015.
Below the underground maintenance hole/conduit system, flexible geotextile multiple cell fabric inner‐ duct and copper and fiber optic cable installation requirements. Any distances provided in this SOW are approximations and should NOT be used for determining duct lengths.
1. Excavate, compact, encase with concrete and backfill the new duct bank with 4” PVC conduit complete with spacer, wire tracer and detectable warning tape. (See attached drawings‐Notional & Reference Only).
From
To
Quantity
Approx.
Distance (Feet)
Notes
MH 34‐8 B20008 1 90 Trenching/Road cut. Stub up to new 4” LB connector
MH 34‐11 TMH A‐42 2 65 Trenching/Road cut
TMH A‐29 HH 34‐28‐1 2 20 Trenching
2. Install one each 4” LB Type or equivalent for new conduit entrance to B20008 from MH 34‐8. Seal all wall penetrations, including inside buildings, shall be restored to meet the required base fire ratings.
3. Install 3” x 3 Geotextile Inner‐ducts as shown at the table below. Each three cell shall have a separate thread color and one of the three cells must be detectable. (See attached drawings‐Notional & Reference Only).
From
To
Quantity
Approx.
Distance (Feet)
Notes
ITB 20011 MH 34‐9 3 135 In one of the existing conduits
MH 34‐8 B20008 1 90 In one of the new 4” conduit
MH 34‐11 TMH A‐42 3 65 In one of the new 4” conduit
TMH A‐29 HH 34‐28‐1 3 20 In one of the new 4” conduit
4. Provide on installed ducts left vacant with a pull tape with a waterproof, corrosion resistant, pre‐ lubricated flat woven polyester pull tape with sequential footage markings, (1250 lb. pulling strength) for future cable installations. The pull tape shall extend into the maintenance holes/hand‐holes and be secured to a cable rack or pulling iron, etc.
5. Provide cable racks in maintenance holes and hand holes as required ‐ this includes new and existing
MHs/HHs. All splices shall be supported by cable hooks under the splice case. All cables shall be supported using racking clips, cable racks, and cable hooks.
6. Provide and install single mode (SM), loose buffer tube, water blocked, outside plant (OSP) fiber optic cable (FOC) suitable for underground applications.
a. From ITB 20011 to B20008
Install approximately 750 feet (Included Maintenance Loop) of 12‐strand SM FOC from ITB 20011 to B20008. Terminate 12‐strand SM FOC in the new 24‐port FODP in ITB 20011 and in the new 12‐ port FODP in B20008. (See attached drawings‐Notional & Reference Only)
b. From ITB 20011 to B2800
Install approximately 7,300 feet (Included Maintenance Loop) of 12‐strand SM FOC from ITB 20011 to B2800. Terminate 12‐strand SM FOC in the new 24‐port FODP in ITB 20011 and in the new 12‐port FODP in B2800. (See attached drawings‐Notional & Reference Only)
7. Install cable tags in all maintenance holes/hand‐holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a maintenance‐hole, put a tag on the cable, approximately 2 feet from each duct entrance. All tags shall be permanently labeled, easily visible and corrosion resistant.
8. Install the following Fiber Optic Distribution Panel (FODP). Distribution panels shall be designed for rack mounting in 19‐in (48 cm) racks or wall mounted as required.
• ITB 20011: One 24‐port FODP in the existing rack
• B20008: One 12‐port FODP in the new backboard.
• B2800: One 12‐port FODP in the existing backboard
9. Install new backboard, AF‐standard 0.75”‐thick plywood, with two coats of white, fire‐resistant paint in B20008.
10. Terminate the newly installed fiber optic cables on new fiber optic distribution panels using fusion spliced pigtails with SC connectors or SC fusion splice direct connectors. Label all equipment and cables newly installed and cables identified for re‐use in accordance with TIA‐606‐C.
11. Provide grounding and bonding in accordance with RUS 1755.200, TIA‐607, IEEE C2, and NFPA 70 as required.
12. Restore all disturbed grounds to the “as found” condition or better after installation. The Contractor shall comply with all base grounds’ restoration requirements. Common use areas shall be restored with sod.
13. Provide a test plan as to how the Fiber Optic Cable shall be pre‐tested, in‐progress‐tested and post‐ tested.
14. Conduct tests on single mode fiber optic cable in accordance with TIA‐526‐7. During any testing phase, the Government reserves the right to perform any of the contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on‐site support during the acceptance testing. The Contractor shall participate with the Government in testing the complete communications system.
15. When any system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance and payment will be withheld until such time as the cause of the failure is corrected to the Government’s satisfaction. After appropriate corrective action has been taken, all tests including those previously completed, related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance.
16. Submit drawings with information for all new installations including butterfly drawings for all maintenance holes and pull boxes that contain new or reused FOC. Drawings shall record the path and arrangement of new and reused fiber optic cables, splices, and the arrangement duct banks, ducts, inner‐duct and shall show maintenance hole orientation with respect to geodetic north.
General Notes:
a. Pre‐Final Inspection: The contractor shall conduct a pre‐final walkthrough inspection with base personnel and publish the pre‐final inspection findings in a pre‐final inspection report. Contractor shall coordinate with government personnel no less than 14 calendar days prior to scheduled pre‐final inspection. Submit pre final DD1354 to go with the pre final inspection. This should be handed in to the Government Program Manager (PM) prior to start of pre final inspections.
b. Final Inspection: The contractor shall conduct a final inspection with base personnel and publish the findings in a final inspection report in accordance with the format specified at the pre‐construction conference. The inspection shall concentrate on the items identified at the pre‐final inspection and recorded in the pre‐final report. A final inspection will not be performed until the punch list has been resolved. The final inspection report shall certify that all items of the design have been implemented and that the construction is complete. Contractor shall coordinate with government personnel no less than 14 calendar days prior to scheduled final inspection. At the final inspection, the contractor shall present a completed DD Form 1354, Transfer and Acceptance of Real Property to the Base Civil Engineer (BCE) or other appropriate organization for signature and acceptance.
2.4 ANTITERRORISM: Comply with UFC 4‐010‐01 DoD Minimum Antiterrorism Standards for Buildings for Antiterrorism requirements.
2.5 SEISMIC REHABILITATION: NOT USED.
2.6 HAZARDOUS MATERIAL ASSESSMENT: Hazardous material assessments are required at all areas to be affected by the new work. Contractor shall perform hazardous material assessment and testing prior to start of repair work including demolition work and submit final report to the government with recommendations for abatement and remediation if needed. Areas containing hazardous materials that will not be affected by the new work must be left in place, undisturbed and encapsulated if directly exposed to personnel.
Environmental Requirements: Contractor shall ensure that all required permits are obtained before construction begins. The contractor must abide by Occupational Safety and Health Act (ACM abatement, lead‐based paint abatement, noise, confined space, etc.) or others as applicable. Coordinate with Contracting Officer with regard to consultations with the Government Environmental group regarding environmental requirements.
Comply with the following requirements:
a. Coordinate with the installation Asbestos Program Manager (APM) and Region Asbestos
Program Coordinator (APC) for any previous asbestos and lead based paint surveys.
b. Coordination must be established with APM and APC for tenant notification of abatement or sampling and work schedule which may impact the tenants.
c. Provide copies of all AHERA certifications: (asbestos worker, contractor supervisor, asbestos monitor, asbestos project designer).
d. Provide copies and proof of medical surveillance monitoring.
e. Provide copies of abatement plans, hazard communication plan for APM and APC approval.
f. All asbestos samples must be taken by a certified and current AHERA asbestos inspector.
g. All asbestos samples shall be analyzed by an accredited NVLAP lab.
h. NESHAP notification shall be provided to GEPA and copy to the Installation APM and Region's APC.
i. Waste shipment records (WSR) shall be provided to GEPA and copy to installation APMs and Region's APC.
j. Waste manifests with receipt signatures from permitted disposal facility must be provided to the APMs and APC.
2.7 SUBMITTALS:
a. SUBMITTAL REQUIREMENTS (After Award and Before Start of Construction):
1. Activity Hazard Analysis (AHA)
2. Design Quality Control Plan (DQC)
3. Contractor’s Quality Control Plan (CQC)
4. Accident Prevention Plan (APP)
5. Construction Schedule (AF 3064 or equivalent)
6. Munitions Response explosive Safety Submissions (MRESS) – Munitions and Explosives of Concern (MEC) Intrusive Investigation Work Plan (MEC field work will not be allowed to start without the Government approved MEC Plan)
7. Hazardous Material Assessment 8.Design Construction Documents: Prepare, organize, and present Design Construction
Documents. Contractor will not be allowed to start construction without the Government approved documents listed below.
Design Drawings: Prepare using AutoCAD 2016 formatted for ANSI D (22” x 34”) sheets.
The Ready for Construction submission shall be stamped and signed by the Designer of Record (DOR).
Submit all CAD files for the final drawings on CD‐ROM or DVD disks in AutoCAD 2016 format. Drawing files must be full files, uncompressed and unzipped.
Basis of Design: Each submission shall include a basis of design with all proposed materials including Design Analyses and Calculations to substantiate the design meets the RFP and all applicable codes.
Specifications: Shall be Unified Facilities Guide specifications submitted in Construction Specification Institute (CSI) 2010 format edit with SpecIntact software in accordance with UFC 1‐300‐02 Unified Facilities Guide Specifications (UFGS) Format Standard.
Contractor shall submit the number of copies as requested as defined under each required submission identified below. The basis of design, design drawings and specifications shall be included on a CD‐ROM in addition to the required hard copy for each submission. Each submission shall be submitted to the Contracting Officer or their representative for Government review and RFP concurrence.
The Contractor shall submit a copy of the Governments review comments from each prior submission with each subsequent submission. This document shall indicate the corrective action taken for each comment and or other proposed solution. Incomplete submissions will be returned to the Contractor with no additional time added to the performance period.
Electronically seal and sign all Acrobat PDF drawings, specifications, and other documents. The electronic signatures shall be printable and viewable in Adobe Acrobat Reader with no additional software.
Provide the following Design Submittal Packages:
a. 60% Design Documents Submittal: 45 calendar days following the date of delivery order.
Submit three (3) hard copies and three (3) electronic PDF format copies on CDROMs of the following: 11” x 17” half‐scale drawing sets, Specifications, Construction Schedule and Basis of Design. Allow 21 calendar days for Government review.
b. 100%/Pre‐Final Design Documents Submittal: 45 calendar days following receipt of Government review comments on the 60% design submittal. Submit two (2) hard copies and two (2) electronic PDF format copies on two (2) CD‐ROMs of the following: 11” x 17” half‐ scale drawing sets, completed specifications with cleared Section and Bracket Verification reports, Construction Schedule, Basis of Design, annotated review comments, and submittal register. Allow 21 calendar days for Government review.
c. FINAL “Ready for Construction” (RFC) Documents: 14 calendar days following receipt of
Government review comments on the 100% design and notice to proceed with Ready for Construction documents. The RFC documents include all documents required for the Final Design Documents. Submit electronic PDF format copies on three (3) CD‐ROMs of the following: Sealed and Signed 11” x 17” half‐scale Drawings, Sealed and Signed Specifications, Construction Schedule, Sealed and Signed Basis of Design, annotated Review Comments, and submittal register. Allow 7 calendar days for Government review.
The following requirements apply to the CD‐ROM:
1. Provide native and pdf files for all documents included on the CD‐ROM.
2. A .pdf file(s) of the final documents shall be provided in the following formats: The entire document shall be provided as a single combined pdf file. The pdf file shall have bookmarks for each item identified in the document's table of contents, including tables, figures, captioned photos, and appendices. The bookmark shall use the same description as provided in the table of contents. If the bookmark is lengthy, abbreviate as needed.
Bookmark to the second level (i.e. 1.1, 1.2, 1.3, etc.). Do not bookmark signature page or the list of acronyms. Each appendix, regardless of size, shall be provided as an individual pdf file. All maps, figures, and pictures shall be provided at a useable resolution. All color maps, figures, and pictures shall be provided in color.
d. DD‐1354 Transfer and Acceptance of Military Real Property:
Submit Interim DD Form 1354 to the Government for approval a minimum of 60 calendar days prior to the Beneficial Occupancy Date (BOD). If modifications to the Interim DD Form 1354 are required by the Government, the corrected version must be submitted prior to the
BOD.
e. Closeout Submittal Requirements:
1. Submit Record Drawings to the Contracting Officer or their representative in ANSI D (22” x 34”) size sheets and two CD‐ROMs containing native CADD files, electronically stamped and signed PDF of drawings, specifications, calculations, basis of design submittal register, Periodic Maintenance Inspection (PMI) plan and other (photos, support files, etc.) as applicable.
GIS Requirements: Site Map record drawings must be in standard coordinates system, in both Guam Geodetic Network and Universal Transverse Mercator (UTM) Zone 55 North, WGS84. All new and existing utilities, driveways, concrete curb, sidewalks roads, paved and unpaved surfaces, buildings, structures, poles, signs, and primary features including supporting facilities of the project within the project’s limit must be accurately noted, both in AutoCAD and GIS format.
2. Submit Facility Electronic Operation and Maintenance Support Information (eOMSI) Manual and Workbook.
2.8 SAFETY REQUIREMENTS: Submit resume and certification of all personnel who will be assigned to this project.
2.9 QUALITY CONTROL REQUIREMENTS: Submit resume and certification of all personnel who will be assigned to this project.
2.10 PERFORMANCE PERIOD: 365 calendar days.
3. SITE ANALYSIS
3.1 EXISTING SITE CONDITIONS: The sites are located on Andersen Air Force Base (AAFB).
All sites contain existing utilities include water lines, sanitary gravity sewer main, sanitary pump station, sanitary force main, storm sewer, steam, underground electric and underground telephone.
Any Government provided geotechnical data is included for the Contractor’s information only, and while it is considered to represent subsurface conditions existing on the project site anticipated at this time, it is not guaranteed to fully represent all subsurface conditions. The Contractor shall be responsible for providing the services of a geotechnical engineer to conduct any subsurface exploration, investigation, testing, and analysis that the Designer of Record deems necessary for the design and construction of the proposed facility and site improvements. The geotechnical engineer shall be registered as a Professional Engineer (Geotechnical Engineer where required by law) and experienced with soil conditions in the region where the project site is located. The geotechnical engineer shall prepare a report addressing any elements of the work requiring his services including any laboratory analysis of samples and recommendations for foundation, safety shoring, and pavement design by a professional engineer as specified and in accordance with UFC 3‐201‐01, Civil Engineering. The report shall be submitted to the Contracting Officer accompanied by a letter from the Designer of Record certifying that the Geotechnical Engineer has reviewed the construction documents and that the design reflects the recommendations of the geotechnical report.
3.2 SITE DEVELOPMENT:
Not Applicable.
3.3 EXPLOSIVE SAFETY SUBMISSION (ESS) REQUIREMENTS: If any portion of the referenced scope of work requires ground intrusion activities or excavation work, the contractor will be required to adhere to Munitions Response Explosives Safety Submission (MRESS), Guam Construction Support, Amendment 7.
Additionally, comply with the Latest Edition Specification Section 01 57 19.01 20 Supplemental Temporary Environmental Controls, Joint Region Marianas Explosives Safety Submission (JRM ESS). Provide Munitions and Explosives of Concern (MEC) Clearance in accordance with the latest Explosives Safety Submission (ESS) Munitions Response Sites Guam Construction Support Implementation in accordance with the following items:
01 MEC Services
Project Management and Planning
MEC Work Plans
Site Preparation, Mobilization/Demolition
Digital Geophysical Survey (DGM) or Handheld Manual Magnetometer Detector and Marking
After Action Reporting
02 Intrusive Investigation
MEC/MPPEH (Material Potentially Presenting an Explosive Hazard) removal, subsurface investigations and other ground penetrating work.
Provide details of ESS implementation and removal of anomalies upon construction contract award and how this work is incorporated in the project schedule. Narrative solution shall demonstrate understanding of ESS implementation in accordance with the ESS requirements. Do not exceed three (3) single‐sided, 8‐ 1/2 x 11 pages.]
DISCLAIMER: Historic anomaly averages contained within the E‐16B memo incorporated into this contract do not reflect conditions at the project site. Contractor assumes the risk that the number of anomalies encountered at the project site may differ from historic averages reflected in the E‐16B memo.
3.4 HISTORICAL, ARCHAEOLOGICAL AND CULTURAL RESOURCES:
In the event of historical artifacts encounter during excavation work, Contractor shall immediately suspend all excavation activity, protect the subject site and report the incident to the Contracting Officer via the PM. The Government will coordinate with State Historic and Preservation Officer (SHPO) for direction and guidance.
The Project Area is located within an archaeologically sensitive area. The contractor shall provide archaeological monitoring of historical, archaeological and cultural resources and be responsible for their preservation during the life of the contract. Archaeological monitoring requires the presence of an onsite qualified Archaeologist during the earth moving portions of this project. If during the trench excavation an Archaeologist detects artifacts or archaeological features that may be significant, he or she stops the work of the contractor in the area. Activities that may damage or alter such resources will be suspended, secure the area and prevent construction workers or other persons from trespassing on, removing, or otherwise disturbing such resources. Resources covered by this paragraph include but are not limited to;
any human skeletal remains or burials; artifacts, shell, bone, charcoal, or other deposits; rock or coral alignments, paving’s, wall, or other constructed features; and any indication of agricultural or other human activities. Upon such discovery or find, immediately notify the Contracting Officer so that the State Historic and Preservation Office (SHPO) may be notified and disposition of the finds should be made. The Government retains ownership and control over archaeological resources.
After the award of the contract, the contractor shall develop an Archeological Monitoring and Discovery Plan (AMDP) and submit for Government review and approval. After approval from the Government, the contractor shall submit the AMDP to the State Historical Preservation Office (SHPO) for review and approval. Notice to proceed is not authorized until approval from the SHPO is received. Provide Archaeological Monitoring/Observation of Earth Moving or Other Work that could adversely affect cultural resources within the project area. This includes data recording, data recovery, archaeological excavation, photography, laboratory analysis, and production of a written report that meets current professional archaeological standards.
4. BUILDING / FACILITY REQUIREMENTS
4.1 DESIGN AND CONSTRUCTION REQUIREMENTS: The design and construction shall be in accordance with the latest revision/edition of applicable current codes, standards, and regulations requirements of this statement of work and include Energy Star efficiency initiatives.
The term "Latest Revision/Edition" is defined as the version as of the project Solicitation Date. In case of conflict between codes, standards, regulation, and specifications, the most stringent requirements shall apply. The contractor shall ensure that all required permits are obtained before construction begins.
The following codes, standards, and regulations are applicable and form a part of this Statement of Work.
Federal/DoD criteria and guidance can be found at: https://www.wbdg.org/.
a. Unified Facility Guide Specifications (UFGS)
b. Unified Facilities Criterias (UFCs) and Facility Criterias (FCs)
c. AAFB Architectural Compatibility and Base Design Standards (ACBDS) May 2013
d. International Building Code (IBC)
e. NFPA 70 National Electric Code (NEC)
f. UFGS 01 78 24.00 20, Part 2, Facility Electronic Operation and Maintenance Support Information
(eOMSI)
g. AFMAN 91‐203 – Air Force Consolidated Occupational Safety Instruction
h. OSHA CFR 29 Part 1910‐268 – Telecommunications
i. NEMA TC 2‐ Electrical Polyvinyl Chloride (PVC) Tubing and Conduit
j. TIA‐606‐C Administration Standard for Telecommunications Infrastructure
k. TIA‐568‐E Commercial Building Telecommunications (568C.1, 568C.2, 568C.3) Cabling Standard
l. TIA‐607‐D Commercial Building Grounding (Earthing) and Bonding Requirements for
Telecommunications
m. TIA‐526‐7‐ Measurement of Optical Power Loss of Installed Single‐mode Fiber Cable Plant
n. TIA‐569‐E ‐ Commercial Building Standard for Telecommunications Pathways and Spaces
o. TIA‐570‐D –Residential Telecommunications Infrastructure Standard
p. TIA‐758B Customer‐owned Outside Plant Telecommunication Infrastructure Standard
q. BICSI TDM Manual ‐ Building Industries Consulting Services International
r. Telecommunications Distribution Methods (TDM) Manual
s. BICSI – Outside Plan Design Reference Manual
t. RUS Bulletin 345‐65 (PE‐33) – Specification for Shield Bonding Connectors
u. RUS Bulletin 1735F‐401, Standards for Splicing Copper and Fiber Cable
v. RUS Bulletin 1751F‐643 ‐ Underground Plant Design
w. RUS Bulletin 1751F‐644 ‐ Underground Plant Construction Telecommunications
x. Engineering Shield Continuity and Construction Manual (TE&CM) 451.2
y. RUS Bulletin 1751F‐801 – Electrical Protection Fundamentals
z. RUS Bulletin 1753F‐151 (515b) ‐ Specifications and Drawings for Underground Cable Installation
aa. RUS Bulletin 1753F‐201 (PC‐4) – RUS Standard for Acceptance Tests and Measurements of mm.
Telecommunications Plant
bb. RUS Bulletin 1753F‐207 (PE‐87) – REA Specification for Terminating Cables
cc. NFPA 70 ‐ National Electric Code
dd. Unified Facilities Criteria 3‐260‐01
ee. Unified Facilities Criteria 3‐580
ff. FGDC‐STD‐007.3‐1998 ‐ Geospatial Positioning Accuracy Standards Part 3:
gg. National Standard for Spatial Data Accuracy
All design drawings, specifications and calculations shall be done by/or under the direct supervision of a Professional Engineer with current National Council of Examiners for Engineering and Surveying (NCEES) registration issued from a state within the United States of America (USA) or one of its territories who shall stamp all design drawings, specifications, and calculations. The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all designs, drawings and other services furnished by the Contractor under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings and other deliveries.
The contractor shall verify all existing site conditions, dimensions and other requirements necessary to complete the project prior to commencing construction activities. The contractor shall notify the contracting officer immediately upon discovery of any expected changes required to suit conditions not identified in the contract. Restoration of damages borne by the contractor in the performance of this contract shall be made at no cost to the Government. Contractor shall be responsible for proper handling and disposal of all materials removed and/or demolished from construction site.
Neither the Government review, approval or acceptance of, nor payment for the services required under this contract shall be construed to operate as a waiver of any rights under this contract of any cause of action arising out of the performance of this contract, and the Contractor shall be and remain liable to the Government and in accordance with the applicable law for all damages to the Government caused by the Contractor’s negligent performance of any services furnished under this contract.
The Contractor is required to submit a work schedule for this project. The schedule should be developed to identify task descriptions, start and completion dates of each task, design reviews, material procurement, construction work, testing, correction if required, final testing, acceptance, utility outages if required, and other requirements necessary to deliver a complete and usable facility. The work under this project requires special attention to the scheduling and conduct of work in connection with the existing facility operations. Identify on the construction schedule each factor that constitutes a potential interruption to the facility operations. Utility outages (power, water, air conditioning, etc.) shall be approved by the Contracting Officer.
4.2 SUSTAINABLE DESIGN: Not Required.
4.3 ENERGY CONSERVATION: Not Required.
4.4 BUILDING COMMISSIONING: Not Required.
4.5 ACCESSIBILITY REQUIREMENTS:
Provide barrier‐free design in accordance with UFC 1‐200‐01, DoD Building Code (General Building Requirements).
4.6 CYBERSECURITY
Not required
4.7 INDUSTRIAL CONTROL SYSTEMS (ICS) & INFORMATION ASSURANCE (IA)
Not used.
4.8 CONTRACTOR ACCESS TO SENSITIVE AREAS: For federally controlled facilities, and/or unclassified sensitive information or unclassified IT systems, the contractor shall coordinate access requirements with the customer security manager.
5. ROOM REQUIREMENTS
Not used.
6. ENGINEERING SYSTEMS REQUIREMENTS (ESR)
Foundations Not Used Basement Construction Not Used Superstructure Not Used Exterior Closure Not Used Roofing Not Used Interior Construction Not Used Stairs Not Used Interior Finishes Not Used Conveying Systems Not Used Plumbing Not Used HVAC Not Used Fire Protection Systems Not Used Electrical Power and Lighting Equipment Not Used Furnishings Not Used
Special Construction Not Used Selective Building Demo Not Used Site Preparations Site Improvements Not Used Site Mechanical Utilities Not Used Site Electrical Utilities Not Used Site Communication Utilities
SITE COMMUNICATION UTILITIES SYSTEM DESCRIPTION
The site communication utility system consists of all telecommunications and fiber optic cabling from the existing distribution system point of connection including all connections, accessories and devices as necessary and required for a complete and usable system. This covers installations up to within 5 feet (1.5 meters) of new (or existing) building location.
GENERAL SYSTEM REQUIREMENTS
Provide a communication system complete in place, tested and approved, as specified throughout this RFP, as needed for a complete, usable and proper installation. Install all equipment in accordance with PTS and the manufacturer’s recommendations. Where the word "should" is used in the manufacturer's recommendations, substitute the word "must".
Site Preparation Perform a topographic survey of the project area that will be impacted by the work. Include the topographic survey map in all design submittals. Standard coordinates system must be in both Guam Geodetic Network and Universal Transverse Mercator (UTM) Zone 55 North, WGS84. Physically verify the location of all existing utilities, driveways, concrete curb, sidewalks, roads, paved and unpaved surfaces, buildings structures, trees, vegetation, poles, signs, and all other features have impact on the design and construction work.
Contractor must utilize ground penetrating radar and other suitable means to accurately locate any existing utilities prior to digging. Not all underground utilities may be accurately located and the Contractor must physically verify such utilities whenever these utilities influence any of the design and construction work. Provide existing spot elevations and existing contours to clearly indicate existing grades/slopes.
All new and existing utilities, driveways, concrete curb, sidewalks, roads, paved and unpaved surfaces, structures, poles, signs, and primary features including supporting facilities of the project must be accurately noted on the Site Map as‐built drawings, both in AutoCAD and GIS format.
Site Earthwork All unsuitable material and surplus excavation shall become the property of the Contractor and shall be disposed of off Government property.
Ductbanks, manholes handholes and raceways Provide a system of concrete encased ductbanks for various locations for all underground communication cabling. Install a minimum of a 50‐foot fiber optic cable maintenance loop at the first MH from the building, at each splice point MH location and at every third manhole. New ducts shall be permanently labeled on the wall of each building/maintenance hole (MH)/Handhole (HH) indicating the connecting building/maintenance hole/handhole at the other end of the duct (for example, “To MH‐306H”).
Grounding System Provide a complete grounding system for the existing communication underground distribution system.
Ground resistance shall not exceed 5 ohms. Comply with IEEE Std. 142 and NFPA 70.
Fiber Optic Distribution Panel (FODP) Marking Each FODP shall be stenciled/marked with black ink or paint or adhesive backed decals in letters and numbers. The cover of all new fiber optic distributions (FODPs) shall be labeled to conform to the system used by local maintenance personnel to identify FODPs that terminate fiber. If the manufacturer has not identified the sequence in which ports on FODPs (pigtail modules) are counted, the Contractor shall provide designation labels/strips to identify the sequence in which they are counted. Each splice tray shall be marked to identify the fiber count contained in the splice tray. The marking shall identify the FODP by number (building number), cable number, and count.
Cable Splicing All splicing shall be performed in accordance with RUS Bulletin 1735F‐401, Standards for Splicing Copper and Fiber Cable. The contractor shall use pic‐a‐bonds, 3M 710 splice connectors, or equivalent, for all copper splices.
Label Label patch panels, distribution panels, connector blocks and protection modules using color coded labels with identifiers in accordance with TIA‐606.
Testing The Contractor shall conduct on‐site testing IAW OEM’s installation manuals, practices and the appropriate vendor’s test procedures. The Contractor shall furnish all test equipment and personnel required to conduct all required testing.
Fiber Optic Tests. All strands of all fiber optic cables shall be tested in accordance with TIA 526‐7, Measurement of Optical Power Loss of Installed Single‐mode Fiber Cable Plant, or equivalent.
Optical Attenuation. End to end attenuation tests shall be conducted on all fiber optic cable strands.
Tests shall be accomplished to ensure the installed cable is within the specified parameters.
‐‐ End of Section –
PART 2
ATTACHMENT
- Location/Vicinity Maps, Page 18
- Partial Communication Site Place, (Notional & Reference Only), Page 19 - 23
Location/Vicinity Maps
Project Site
Partial Communication Site Place
Notional & Reference Only
Note: Any distances provided in this SOW are approximations and should NOT be used for determining duct lengths.