This is a Statement of Work (SOW) for HVAC replacement services at the National Weather Service (NWS) Weather Service Office (WSO) in Yap, Federated State of Micronesia.

The contractor must replace two existing 10-ton Carrier packaged cooling units (PCU-1 and PCU-2, Model 50TC-D12A1Q5A1A0A0, 208/230V, 3-phase, 60Hz, R-410A refrigerant) with new equipment matching or exceeding the existing specifications, installed in the same location and footprint. Additionally, the contractor must install a new HVAC control system using an Open Protocol framework with lead/lag rotation, occupancy override, fail equipment/component monitoring, and proof of operations capabilities. The control system must match or improve upon the current Carrier system and follow the specified sequence of operations detailed in Figure 5. Both PCU replacement and control system installation require calibration/balancing to maintain appropriate air flow and building temperature. The Operations and Telecommunications/Power rooms must remain operational throughout work, with all outages coordinated and approved by the onsite Facility Technician and Technical Point of Contact (TPOC). Individual unit replacement is recommended to maintain cooling via the alternate unit.

The contractor must deliver all materials undamaged with no on-site forklift availability. Contract duration is 270 days from award date. Work hours are 8:00 AM to 5:00 PM Yap local time, Monday through Friday, excluding federal holidays. The contractor must attend a mandatory Post Award Conference within 10 business days of award and submit a draft project schedule at that conference, with a final schedule due 10 business days thereafter. Submittals include equipment specifications, certifications, manufacturer warranties, shop drawings, field commissioning test reports, O&M manuals with local service entity listings, and a one-year contractor installation warranty. Training on system operation and two equipment manuals with warranty documentation must be provided. All work must comply with applicable federal and local environmental, health, and safety regulations and relevant standards (AHRI, ASHRAE, ANSI, ASTM, EPA, NFPA, UL). Final site cleanup and proper disposal of waste materials per FSM and Yap State EPA requirements are required.

View the file

Other files for this federal contract opportunity

Other files attached to HVAC Replacement WSO Yap, newest first.
File Type Posted
Sol_1305M326Q0349.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

HEATING, VENTILATION, and AIR CONDITIONING (HVAC) REPLACEMENT

WEATHER SERVICE OFFICE (WSO) YAP

1.0 GENERAL

The Mission Statement of the National Weather Service (NWS) is to provide weather, hydrologic, and climate forecasts and warnings, and impact-based decision support services, for the United States, its territories, adjacent waters and ocean areas, for the protection of life and property and enhancement of the national economy. In support of this mission, the NWS Pacific Region (PR), Facilities Engineering Branch (FEB), provides facilities support and maintenance throughout the PR.

1.1 BACKGROUND

The existing air conditioning system servicing the Weather Service Office (WSO) Yap main building is failing and at the end of its useful service life. The system is redundant and comprised of two (2) 10-ton packaged air conditioning units or Packaged Cooling Units (PCUs) .

1.2 SCOPE

The NWS seeks to replace the packaged air conditioning systems PCU-1 and PCU-2 and also install a compatible new control system.

1.3 OBJECTIVE

Replace PCU-1 and PCU-2 with new equipment to match the existing equipment, and install a new control system to control both units.

1.4 APPLICABLE DOCUMENTS

1.4.1 Compliance Documents

The Contractor must comply with all local and federal environmental, health, and safety regulations while conducting this work at the WSO Yap. In addition, the Contractor must ensure that all work and products are in compliance with applicable certifications/codes/standards (e.g., Air-Conditioning, Heating, and Refrigeration Institute (AHRI), American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE), American National Standard by the American National Standards Institute (ANSI), American Society for Testing and Materials (ASTM), Environmental Protection Agency (EPA), National Fire Protection Association (NFPA), Underwriters Laboratories (UL)) and contract clauses.

2.0 SPECIFIC REQUIREMENTS/TASKS

2.1 Replace Existing Packaged Units

Note: The Operations (OPS) and Telecommunications/Power (COMM/PWR) rooms air conditioning system must remain operational at all times. Any outage must be first coordinated and approved by the onsite Facility Technician, with notification made to the Technical Point of Contact (TPOC). To minimize cooling outages, it is recommended that the packaged units be replaced individually to allow cooling to be maintained by the other unit.

2.1.1 Existing packaged unit equipment information.

Note: See Figures 1 through 4 for current layout and photos of existing equipment.

- PCU-1, Carrier Model 50TC-D12A1Q5A1A0A0, Serial 1513G10251, 208/230V, 3ph, 60Hz, R-410A

- PCU-2, Carrier Model 50TC-D12A1Q5A1A0A0, Serial 1513G10252, 208/230V, 3ph, 60Hz, R-410A

2.1.2 Install two (2) new 10-ton packaged cooling units in the same location and footprint as the removed equipment . The new units must meet or exceed the specifications of the existing equipment.

2.1.3 Calibrate/balance the system to provide the appropriate air flow and space temperature throughout the WSO Yap building.

2.2 Install New HVAC Control System

Note: Outages must be minimized and must be first coordinated and approved by the onsite Facility Technician, with notification made to the TPOC.

2.2.1 Existing Control System.

- Carrier

2.2.2 Install a new HVAC control system for the packaged cooling units. The control system must operate using an Open Protocol framework to allow system and component flexibility, adaptability, interoperability, and ease of maintenance. The system must have an “Occupancy Override” feature, to allow for lead/lag rotation, fail equipment/component monitoring, and proof of operation(s). System operation must be as shown in Figure 5, “Sequence of Operation” and must match or better the current system.

2.2.3 Calibrate/balance the system to provide the appropriate air flow and space temperature within the WSO Yap building.

Figure 1 – WSO Yap HVAC Layout 2002

Figure 2 – Existing PCU-1 (Right) and PCU-2 (Left)

Figure 3 – Existing PCU-1

Figure 4 – Existing PCU-2

Figure 5 – HVAC Sequence of Operation

2.3 Submittals

a. Equipment make, model, specifications, certifications/approvals, detailed drawings, technical literature, etc. (prior to ordering)

b. Miscellaneous Material (e.g., detectors, switches) – Make, model, specifications, certifications, technical literature, etc. (prior to ordering)

c. Manufacturer’s warranty. (prior to ordering)

d. Shop Drawings – Provide an installation drawing showing location/layout.

(record drawing after accepted installation)

e. Field Commissioning Test Reports.

f. Operation and Maintenance (O&M) manuals, including list of authorized local service, maintenance, and service entities.

g. Contractor’s 1-year warranty for installation.

2.4 Delivery, Storage and Handling

a. Delivery: Deliver materials/products to site in an undamaged condition and per contract requirements.

b. Storage: Store materials/products to provide protection from damage.

c. No forklift is available on-site.

2.5 Final Cleanup

The Contractor must remove waste materials, debris, and equipment components from the work site. Dispose of everything in a legally and acceptable manner in accordance with Federated State of Micronesia (FSM) and Yap State Environmental Protection Agency (EPA) laws and guidelines.

3.0 OTHER APPLICABLE CONDITIONS

3.1 TEMPORARY CEASE WORK

During the contract period, there may be a time where extreme weather conditions warrant a cease work. The Contracting Officer (CO) is the only person who can direct the Contractor to cease work. The Contractor will be given a 48-hour notice to temporarily cease all work by the CO. This notice can be via telephone call or email. The telephone call or email must have a verbal or written response from the Contractor within 24 hours of the proposed cease work.

3.2 SECURITY

The Contractor and/or workers will need to sign in as “visitors” on the Sign-In sheet for every work day that they are there. The Contractor must be responsible for safeguarding all:

Government equipment, information and property provided for Contractor use. At the close of each work period, Government facilities, equipment and materials must be secured.

3.3 PERIOD OF PERFORMANCE

The period of performance will be 270 days from the date of award.

3.4 PLACE OF PERFORMANCE

The place of performance is at the WSO Yap located adjacent to the Yap International Airport, Yap Island, FSM, 96943.

3.5 HOURS OF OPERATION

Work hours must be between the hours of 8:00am to 5:00pm Yap local time, Monday thru Friday, except on federal holidays and any other day off designated by Federal Statute, by Executive Order, by Presidential proclamation, or unless otherwise determined and agreed upon by the station Official-in-Charge (OIC) and Contractor (e.g., weekend work, work outside of normal hours). Federal holidays include:

New Year's Day Juneteenth Veteran’s Day Martin Luther King's Birthday Independence Day Thanksgiving Day President's Day Labor Day Christmas Day Memorial Day Columbus Day

3.6 POST AWARD CONFERENCE

The Contractor must attend a Post Award Conference no later than 10 business days after the date of award. The purpose of the Post Award Conference, which will be chaired by a TPOC, is to discuss technical and contracting objectives of this contract and review the Contractor's draft project plan. The Post Award Conference will be held via video-teleconference (e.g., Google Meet).

3.7 PROJECT SCHEDULE

The Contractor must provide a draft Project Schedule at the Post Award Conference for Government review and comment. The Contractor must provide a final Project Schedule to the TPOC no later than 10 business days after the Post Award Conference. The Contractor must develop a Project Schedule that does not impede facility access nor compromise the security of the facility or safety of the site staff at the WSO Yap.

4.0 CONTRACTOR FURNISHED PROPERTY

The Contractor must furnish all materials, equipment and services necessary to fulfill the requirements of this contract.

5.0 TRAINING

Contractor must provide training on the operation of the new systems. Provide two (2) equipment manuals including warranty documentation.

6.0 CONTACT LIST

Facility Technician (on site)

TBD

NWS TPOC

NWS PRH Senior Facilities Engineering Technician, TPOC

NWS WFO Guam Facilities Engineering Technician, TPOC

Contract Project Engineer, Non-Federal TPOC

END OF STATEMENT OF WORK