This Statement of Work (SOW) details a greenhouse remodel project for the USDA Agricultural Research Service's Southeast Watershed Research Unit located in Tifton, Georgia. The project involves comprehensive renovation of Greenhouse Building 27, with multiple work components including base bid and optional bid items: base bid focuses on repairing and updating building structure (removing existing materials, pressure washing surfaces, repairing concrete block, installing stucco, replacing vent systems); Bid Option 1 covers interior flooring upgrades and drainage improvements; Bid Option 2 addresses heating, cooling, and plumbing updates; and Bid Option 3 involves updating greenhouse control systems.
Key project specifications include: total project completion within 120 calendar days, work to be performed by certified technicians, compliance with local/state/federal codes, and turn-key project delivery. The project's objective is to restore greenhouse functionality and provide space to meet USDA-ARS research mission objectives. Contractors must submit comprehensive quotes covering all labor, equipment, materials, and quality control, with specific requirements for site cleanup, debris disposal, safety planning, and material submittals. The project site is located at 123A Tobacco Road in Tifton, Georgia, with an asset identification number of 660200B027.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 5_ARS Facilities Design Standards ARS-242.1.pdf | ||
| Attachment 6_SF 24 Bond.pdf | ||
| Attachment 8_Past Performance Questionnaire.docx | DOCX document | |
| Attachment 2_Davis Bacon Act WD GA20250102.pdf | ||
| Attachment 3_ARS-371.pdf | ||
| Attachment 4_ARS-372.pdf | ||
| Sol_1232SA25R0039.pdf | ||
| Attachment 7_Experience Sheet.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Agricultural Research Service
U.S. DEPARTMENT OF AGRICULTURE
Last Updated 5/3/2025
STATEMENT OF WORK
Greenhouse 27 Remodel
Southeast Watershed Research Unit 123A Tobacco Road
Tifton, Georgia 31793
Asset ID: 660200B027
1. PROJECT INTRODUCTION
1.1. PROJECT TITLE
Greenhouse 27 Remodel
1.2. PROJECT BACKGROUND AND PURPOSE
The USDA, Agricultural Research Service (ARS), Southeast Watershed Research Unit’s mission is to develop the scientific understanding and associated technologies of watershed systems essential to maintaining/enhancing the environmental and natural resource base upon which a viable, sustainable, and productive agricultural economy depends.
The objective for this project is to remodel Greenhouse Bldg. 27 by repairing aging/damaged building infrastructure components and systems to restore greenhouse functionality and provide space to meet USDA-ARS research mission objectives.
1.3. PROJECT CONTACT PERSONS
ADMINISTRATIVE OFFICER (AO)
ENGINEER PROJECT MANAGER (EPM)/ CONTRACTING OFFICER’S REPRESENTATIVE (COR)
USDA, ARS, SEA Facilities Engineering
2. SCOPE AND OBJECTIVES
2.1. DESCRIPTION OF WORK
The Contractor must furnish all personnel, equipment, tools, materials, supervision, and quality control necessary to remodel the subject greenhouse structure and building components. All quotes should be submitted as turn-key completed work. All work will be accomplished by certified technicians and in accordance with all local, state, and federal codes and regulations. The Contractor must:
2.1.1. BASE BID – Repair/update building structure
• Remove and dispose of all materials inside each bay of the greenhouse (old tables, plastic, water hoses, etc)
• Pressure wash interior and exterior surfaces (concrete block, polycarbonate panels, etc)
• Repair damaged concrete block and seal all cracks in the block.
• Repair any damaged greenhouse framing
• Install stucco to repaired concrete block (lower interior and exterior knee walls) and apply concrete sealant/paint to prevent future moisture damage.
• Remove all evaporative cooler louver vents and replace with a vent wall with motors capable of being controlled by the building’s greenhouse control system
• Vent wall should be covered in 8mm twin wall polycarbonate panels to match the buildings exterior.
2.1.2. BID OPTION 1 – Upgrade bay interior flooring / Provide drainage
• Demo and Remove concrete walkways in all greenhouse bays
• Demo and Remove concrete cisterns and associated piping / backfill the voids and level to grade
• Form and install concrete floors in all greenhouse bays with center catch basin drain.
o Floors should be sloped to the center drain to ensure all water drains towards the center catch basin drain
• Provide and install drain tile originating from each bay of the greenhouse connected to a drain field terminating at the creek at the rear of the building o Ensure drain field has enough slope/fall to evacuate the water away from the greenhouse bays
• Provide concrete curb around the outside of the greenhouse to assist with water runoff. Concrete lip should be sloped towards the south to assist with drainage to the creek at the rear of the building.
2.1.3. BID OPTION 2: - Update Heating and Cooling/Plumbing
• Demo existing and install self-contained evaporative coolers (water walls) in each bay (6in pads, 3ft tall, approx. 25ft in length)
• Remove interior gas fired heaters in bays 1 & 3 and replace with new heaters and establish connection to existing gas supply and control circuits
• Connect existing water lines in each bay to provide water supply to self-contained evaporative coolers to be installed on the western wall of greenhouse bays. Plumbing should have 1 hose bib for customer connection
• Establish electrical connections as needed to facilitate operation
2.1.4. BID OPTION 3: - Update greenhouse control systems and components
• Remove current control boxes and controller contactor zone boxes.
• Provide and install new Wadsworth Envirostep Control boxes (one per bay)
3.2. The Contractor must prepare an overall project schedule including milestone dates for all phases of work and completion date; submit to the COR for approval. This schedule is due fourteen (14) days after contract award. The Contractor must track all work progress to ensure that the project is completed according to the schedule. Include work week schedule with daily starting and stopping time.
3.3. The Contractor must coordinate and confirm the dates for all work with the COR. If necessary, any request for a time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration and provide an updated schedule for completion. No extension of the period of performance may be given without the written authority of the CO.
3.4. Project work hours are 7:00 am and 4:00 pm, local time, Monday through Friday; federal holidays excluded. The contractor is not required to provide services on recognized Federal holidays established by Federal law (5 U.S.C. 6103). Any changes to work schedule must be submitted to CO for written approval prior to any schedule change.
4. GENERAL REQUIREEMENTS
4.1. PERMITS
The Contractor must obtain all building and trade permits necessary to include any drawings, plans, permit and inspection fees, utility location, site surveys, and any other items necessary for compliance with state, local, and federal building authorities.
4.2. SAFETY
The Contractor must submit a Site Safety Specific Plan/Accident Prevention Plan (Plan) in industry recognizable format to the COR within seven (7) days of contract award.
The Plan must include phone numbers and maps to local physician offices and the nearest hospital. The Government will review and approve the Plan before issuance of the NTP.
4.3. EXISTING INSTALLATIONS/DEMOLITION
Coordinate removal of existing installations with COR. All disturbances of existing systems must be coordinated with the COR to prevent disconnecting equipment that may jeopardize on-going research.
4.4. QUALITY CONTROL
Provide quality control to ensure that all components of project work meet the requirements of the contract specifications. Ensure that all work not acceptable or compliant with the specifications is corrected prior to inspection or review by the COR. Quality control is the exclusive responsibility of the Contractor.
4.5. PROTECTION OF WORK AND PROPERTY/SAFETY REQUIREMENTS
4.5.1. The Contractor must protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property must be repaired at the Contractor’s expense to pre-damaged condition to the satisfaction of the COR.
4.5.2. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor must furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
4.5.3. Open depressions and excavations occurring as part of this work must be adequately barricaded or fenced to prevent vehicle or pedestrian traffic into the work area.
4.5.4. Provide continuous noise and dust abatement as required to prevent disturbance and nuisance to the public and workers and to the occupants of adjacent premises and surrounding areas. Dampen or cover areas affected by demolition operations as necessary to prevent dust nuisance.
4.5.5. The contract documents may not represent all surface conditions at the site and adjoining areas. The known surface conditions are as indicated and must be compared with actual conditions before commencement of work and the cost must be included in the Contractor’s quote.
4.5.6. The Government will not furnish any labor or equipment to unload or move materials or supplies.
5. UTILIZATION OF BIOBASED PRODUCTS
The Contractor must utilize products and material based from bio-based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the Government. All supplies and materials must be of a type and quality that conform to the applicable federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at:
www.biopreferred.gov.
6. HAZARDOUS MATERIAL
The JWDSRC is not suspected to contain asbestos containing materials. Existing conditions are reflected correctly to the best of USDA’s knowledge. The USDA makes no representation, warranty, or guaranty that the conditions indicated either are representative of those conditions existing throughout the area, or that unforeseen developments may not occur, or that materials other than, or proportions different from those indicated may not exist. The Contractor must include costs for hazardous materials assessment in the quote. If hazardous materials are found to be present, it must be reported to the CO & COR for further action.
7. DISPOSAL OF REMOVED MATERIALS AND DEBRIS
7.1. The Contractor must dispose of removed, materials, waste, trash, and debris in a safe, acceptable manner, in accordance with applicable laws and ordinances and as prescribed by authorities having jurisdiction.
7.2. Burying of trash and debris on the site is prohibited. Burning of trash and debris at the site is prohibited.
7.3. Remove trash and debris from the site at frequent intervals so that its presence will not delay the progress of the work or cause hazardous conditions for workers and the public.
7.4. Removed materials, trash, and debris must become the property of the Contractor and must be removed from the project site and be disposed of in a legal manner. Location of disposal site and length of haul are the Contractor's responsibility.
7.5. The contractor should make every effort to recycle as much of the construction debris as possible.
7.6. Any waste materials encountered during the demolition that are found to contain lead, asbestos, polychlorinated biphenyls (PCB), fluorescent lamps, or any hazardous substances are to be handled and removed in accordance with local, state, and federal laws and requirements concerning hazardous waste as well as any specific hazardous waste requirements stated in different sections.
7.7. Comply with hauling and disposal regulations of authorities having jurisdiction, per federal, state, and local requirements.
8. TEMPORARY FACILITIES
Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor must maintain and protect all such utilities during the course of construction and must repair or replace any items damaged through its own negligence. Should the Contractor require any power or utility shutdowns during construction, the Contractor must obtain approval for such shutdown from the COR three (3) working days prior to the need.
9. CLEANUP
The construction site must be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor must remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
10. SUBMITTALS
Submittals on all material incorporated into the work, including shop drawings and specifications, used on this project must be submitted to the EPM, COR, and Contracting Specialist. Electronic submittals are acceptable, otherwise three (3) written submittals are required.
10.1. Project Schedule within fourteen (14) calendar days of award (see Section 3.2).
10.2. Plan within seven (7) days of award (see Section 4.2).
10.3. Any additional material, including shop drawings and specifications, used on this project.
11. INSPECTION AND ACCEPTANCE
A government representative will inspect and approve the work performed on this project.
The Contractor must schedule inspection a minimum of three (3) days in advance, in writing, to the COR and CO.
12. FINAL PAYMENT/CONTRACT CLOSEOUT
The following documents are required prior to final payment (other documents may also be required): Release of Liens, Release of Claims, Employee Payroll\Timesheets, and Invoice.