STATEMENT OF WORK
For
Choctafaula Ranger Residence Floor Leveling and Foundation Stabilization Project
Tuskegee National Forest
NATIONAL FORESTS IN ALABAMA
TABLE OF CONTENTS
Section Page Number
Scope of Work …………………………………………………………….. 3
Background ……………………………………………………………….…... 3
Schedule of Work ……………………………………………………………. 3
Work Requirements …………………………………………………………... 3
Location Map ……………………………………………………………….… 4
Vicinity Map ………………………………………………………………..…. 5
Foundation Plan ……………………………………………………………. 6
Schedule of Items …………………………………………...………………. 7
STATEMENT OF WORK
For
Choctafaula Ranger Residence, Floor Leveling and Foundation Stabilization Project
Tuskegee Ranger District
SCOPE OF WORK:
Choctafaula Ranger Residence, Floor Leveling and Foundation Stabilization Project: Provide all equipment, labor, materials, and other incidentals necessary to level the existing floor of the residence. The work shall include, and not limited to installing additional treated wood floor beams and anchors to support the residence to prevent shifting and sagging and stabilize the existing foundation by providing additional treated posts, floor joists, anchors, and straps.
The Forest Service is requesting quotes for the work requirements specified below. The Contractor is advised to make site visits prior to submitting quotes. It is expected the successful vendor shall perform the job in accordance with standard practices.
BACKGROUND:
The Tuskegee National Forest, Tuskegee Ranger District covers approximately 11,252 acres in Macon County, Alabama. The Choctafaula Ranger Residence is located near the district office at 125 National Forest Road 949, Tuskegee AL 36083. Directions to the Tuskegee Ranger District: Follow I-85 North, take exit 42, turn right and travel 2 miles to National Forest Service Road 949.
SCHEDULE OF WORK:
The duration of the project shall be 30 calendar days from the Notice to Proceed.
WORK REQUIREMENTS:
It is expected the successful vender shall perform the job in accordance will all specification and applicable State and county laws and ordinances.
PROJECT VICINITY MAP:
TUSKEGEE
NATIONAL
FOREST
PROJECT SITE MAP: TUSKEGEE NATIONAL FOREST
FOUNDATION PLAN