Attachment 1 - SOW.pdf
PDF 63 KB Posted
- Attached to
- 414 CTS Det 1 Bamboo Eagle Facility Support
- Solicitation number
- F3G5BA5113AL01
About this file
This Statement of Work (SOW) details facility support requirements for Exercise Bamboo Eagle 25-3, a training operation by the 414th Combat Training Squadron, Detachment 1 (RF-R) in August 2025. The contractor must provide an airfield location within flight range of planned training scenarios, supporting 4 HH-60W helicopters, 1 GA team, and an MX team for 11 days. Specific requirements include providing hangar space, fixed-base operator (FBO) support, 24/7 facility access with <1 hour response time, mobile restrooms, janitorial services, parking for 4 aircraft, crash recovery and fire response teams, and HAZWASTE disposal services. The contractor must follow FAA guidelines, maintain facility security, comply with state and local regulations, and ensure a safe work environment. The government will provide communications systems for the exercise.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Notice of Intent to Sole Source.pdf | ||
| F3G5BA5113AL01 SSJ_redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
414 CTS Det 1 Bamboo Eagle Facility Support
BACKGROUND: The 414th Combat Training Squadron, Detachment 1 (RF-R) has a requirement to conduct Exercise Bamboo Eagle 25-3 for 11 days during August of 2025. RF-R requires the rental of an airfield, facility and other supplies that will be required to safely conduct training operations. RF- R requires the rental of an airfield location within flight range of planned training scenarios that will provide open airspace during that time and allows for the safe training for 4 HH-60Ws, 1 GA team, and MX team ISO Bamboo Eagle 25-3.
1 SCOPE: The contractor shall furnish the airfield, facility, and support functions to include portable restrooms, facility use, hangar use, flightline vehicle usage, and fuel truck usage. The Government will provide all communications systems necessary.
2 DESCRIPTION OF WORK: The contractor shall provide the use of facilities, hangar space, and airfield for the duration of the exercise. RF-R to conduct training operations.
2.1 Contractor shall be required to provide hangar space for equipment, FBO (fixed-base operator) support. The Contractor shall grant the RF-R the right by an airport to operate at the airport and be provided aeronautical services such as fueling, hangar, tie-down and parking, office space/equipment, and support with the hangar space as required. Contractor shall provide airfield and facility access 24 hrs/7 days a week with the response time of <1 hour, for the duration of the exercise. The Contractor shall provide all facilities outlined to include the hangar and mobile restrooms parked near the aircraft. The contractor shall provide professional janitorial services to maintain a safe, hygienic work environment. The Contractor shall provide parking locations for 4 aircraft. The Contractor shall provide crash recovery and fire response teams.
2.2 Airfield Access. The Contractor shall provide full access to a dedicated airfield parking during the full duration of the training session. The Contractor shall ensure the Government is granted sole use of the hangar and apron for the duration of the training session.
2.3 HAZWASTE Disposal. The contractor shall provide HAZWASTE disposal services in compliance with all applicable environmental regulations.
3 QUALIFICATIONS: Contractor shall follow all required Federal Aviation Administration (FAA) guidelines.
4 SECURITY: The Contractor shall maintain its own security for the airfield for the duration of the rental each year.
5 CODES: Contractor shall maintain the facilities in accordance with their own state and local regulations.
6 ACCESS HOURS: RF-R will have 24-hour access, 7 days a week during the duration of the annual rental.
7 SAFETY: The contractor’s on-site staff shall comply with safety requirements as they pertain to work being accomplished.