Attachment 1 - SOW - DDSP Circuit Repair.pdf

PDF 285 KB Posted

Attached to
DDSP Urgent High Voltage Circuit Repair - SP3300-25-Q-0277
Solicitation number
SP3300-25-Q-0277
Issued by

About this file

This Statement of Work (SOW) details high voltage electrical repair and maintenance services for the Defense Distribution Depot Susquehanna PA. The work involves mechanical and electrical services for the RED Circuit at the main depot substation, including repairing a Cooper Kyle VSA-12 15.5KV recloser device, installing new bronze bus connectors and feeds, installing animal guard deterrents, replacing substation grade arresters and fuses, and conducting comprehensive electrical testing on transformers and equipment. Work is to be performed Monday-Friday from 7:00am to 3:30pm, with potential off-duty hour requirements due to critical mission functions.

Key technical requirements include electrical testing per NETA-MTS standards, which involves insulation resistance testing, winding resistance testing, turns ratio testing, and oil sample analysis. The contractor must comply with NEC and NESC codes, EM 385-1-1 standards, and provide detailed reporting on any damages, test failures, or recommended remedies. All old materials must be removed, and final reports submitted to designated government contacts, Mr. Timothy Burke and Mr. Robert Olsen, who are also the points of contact for safety-related concerns.

View the file

Other files

File Type Posted
Attachment 2 - Wage Determination 2015-4245 rev29.pdf PDF
CSS SP3300-25-Q-0277.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Defense Logistics Agency Defense Distribution Depot Susquehanna PA

2001 mission Drive, Suite 1 New Cumberland, Pennsylvania 17070-5002

SOW

Repair RED Circuit High Voltage Switches and Assemblies at Main Depot Substation

All work and services shall be performed during regular hours of operation Monday – Friday 7:00am to 3:30pm. De-energizing and re-energizing of all circuits will be completed by inhouse facilities maintenance electricians such as isolation of 69KV feed to affected RED circuit structure and to re-energize 69KV RED circuit structure upon completion of work. Upon re-energizing RED circuit transformer and busway, a representative and or technician will be required to be on site. This work may be required to be completed during off duty hours due to critical mission functions.

RED Circuit Mechanical Work and Services

Repair existing Cooper Kyle VSA-12 15.5KV recloser device.

Remove existing and install 6 new bronze buss to flat connectors and 500 MCM or equivalent feeds to recloser device.

Install animal guard deterrents for substation grade arresters, secondary transformer bushings, and recloser device bushings. (12) Remove existing and install 3 new McGraw Edison (or pre-approved substitute) substation grade arresters.

Replace 3 New S&C 69KV 100E standard speed fuses and live parts.

RED Circuit Electrical Tests and Services

Provide electrical testing to ensure proper resistance of existing (3) 69KV RED circuit substation arrestors and existing 15.5KV substation grade arresters.

Provide electrical testing to existing Cooper Kyle VSA 15.5KV recloser device.

Provide electrical testing per NETA-MTS on existing 7500 KVA RED circuit liquid filled medium voltage transformer to include:

o Insulation resistance testing o Winding resistance testing o Turns ration testing o Oil sample testing for quality, moisture and dissolved gas in oil

Reporting

Any damage or test failures shall be noted in final report to government.

If any damage or remedies are recommended, contractor shall notify government before proceeding and note in final report to the government.

All old/used materials and equipment shall be removed by contractor.

At the completion of this project, final reports shall be returned to Mr. Timothy Burke and Mr. Robert Olsen.

Safety

All work shall be completed in compliance with NEC and NESC codes and standards.

All work shall be completed in accordance with EM 385-1-1.

Contractor will be responsible for temporary grounding for personal protection.

All safety related concerns should be directed towards Mr. Timothy Burke and Mr.

Robert Olsen.