Attachment 1 - SOW Construct Womens Health Primary Care Addition.pdf

PDF 336 KB Posted

Attached to
Y1DA--589-019, Construct Women's Health and Primary Care Addition Kansas City VAMC (VA-21-00104203)
Solicitation number
36C77623R0085
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Kansas City VAMC

4801 Linwood Blvd 14 March 2023

Kansas City, MO 64128

Project 589-019 Construct Women’s Health and Primary Care Addition

Project Design Scope of Work

1. GENERAL INTENT: The Contractor (herein referred to as “A/E”) shall provide Architect/Engineer (A/E) services to design a construction project at Kansas City VAMC in accordance with this design scope of work.

2. STATEMENT OF WORK:

A. A/E Part One Services (also known as Design Phase) for this design project includes site visits, field investigation, conduct of studies and user interviews to prepare drawings, specifications and cost estimates for all facets of work and disciplines/trades to facilitate a construction project to construct a Women’s Health and Primary Care Addition. This project shall build an 8,600 BGSF to Building 55 for Women's Health and Primary Care clinics and renovate 13,500 BGSF of adjoining space that is designated as Primary Care, Mental Health, and Radiology space.

This will create PACT compliant space in the new addition as well as provide Primary Care - Mental Health integration. The first-floor addition will provide space for Women's health and the second-floor space will provide space for primary care clinics. This project will also renovate poorly utilized space in radiology to accommodate staffing needs and a reconfiguration of PRRC space. This project will also renovate the main parking lot for this location and increase the number of parking spaces available, to include lighting, as well as provide emergency power generation for the entire facility. Other work would include an additional elevator for staff and patient transport, replace/upgrade BAS to match front end at the main campus, add humidification to building, replace fan powered boxes with VAV in renovated areas, replace exhaust fans and motor starters in renovated areas, and provide a private entrance to the Women’s Clinic. The AE shall provide drawing, specification and IGE submissions at 35% (SD), 65% (DD), 95% (CD), and Final Bid Documents (Bid) to the VA.

B. A/E Part Two Services (Option Line Items) of this design project (also known as Construction Period Services) includes responding to construction contractor Requests For Information (RFIs) during the solicitation and construction phases of the construction project, attendance at pre-bid, post-award and commissioning kick off construction project conferences, review of construction material submittals and shop drawings, approximately 2 site visits per month during construction (both scheduled and emergent) to ensure compliance with the design drawings and specifications, preparation of site visit reports, coordination with project commissioning requirements, review of any construction project modifications for cost and technical acceptability, attendance in the final acceptance inspection, preparation of the punch list and preparation of record drawings of the completed construction project based on the construction contractor’s as-built drawings. The A/E shall prepare a submittal log to be utilized by VA during construction period services and are required to review and comment on submittals and RFI’s on a web based electronic construction document management system such as Submittal Exchange. The A/E shall provide meeting minutes for weekly construction meetings throughout the duration of construction. All Part Two Services are optional line items and will not be exercised at the time of award.

4801 Linwood Blvd 14 March 2022

Kansas City, MO 64128

C. The above paragraphs constitute a basic outline of the work to be accomplished and in no way comprises all the details for design of this project. The A/E shall initiate detailed inspection of the project site to determine the needs and conditions for the design of this project.

D. The A/E shall be solely responsible for the management, including all associated labor, equipment, materials, mailing costs, and inspection, to meet the requirements of the design project. The A/E shall further provide meeting minutes for all meetings held under this design project.

3. DESIGN WITHIN FUNDING LIMITATIONS: The design shall be prepared by the A/E so as to permit the award of a construction contract, using Federal Acquisition Regulation procedures for the construction of the facilities, at a cost that does not exceed the project’s estimated construction contract price. The VAAR magnitude of construction for this project is between $10,000,000 and $20,000,000.

4. DESIGN INDEPENDENCE, FURNITURE AND EQUIPMENT: Designs for construction must produce a “complete and usable” facility or improvement when constructed. VA policy (VHA Office of Capital Assets Management, Engineering and Support memo Updated Construction Guidance and Expectations dated Sep 12, 2016) requires the A/E to certify that their design (including all bid alternates/bid deducts) is independent of any future construction project. In addition, the A/E must certify that it has produced a design that does not include furniture and equipment that will be procured separately. Equipment that can be part of the design includes those items to meet code requirements for building occupancy, items covered in the VA’s Master Construction Specifications (PG-18-1) Divisions 1 through 10, 13 through 26, or 28 through 48, non-IT equipment items covered by Division 27 and items covered by Division Numbers 12 31 00, 12 32 00, 12 34 00 and 12 36 00. The AE shall include drawings showing all furniture and equipment with designations to show who will provide and who will install (VV, VC, or CC).

The A/E shall submit as part of the Final Bid Documents submittal a signed letter on company letterhead stating the design’s independence.

5. DESIGN CRITERIA: The VA Technical Information Library (TIL) available at http://www.cfm.va.gov/til/index.asp is managed by the VA Office of Construction and Facility Management and is the master repository for all VA Numbered Standards for Construction to include design and construction specifications, procedures, standard details, BIM/CAD standards, equipment guides, space planning and design guides. The documents of the TIL shall be the minimum design criteria for all VA projects performed in the construction of new facilities and the modernization, alteration, addition, or improvement of its real property. All design documents shall be developed in accordance with the following listed Department of Veterans Affairs References, with special emphasis on items in bold:

PG-18-1 Master Construction Specifications

PG-18-3 Design and Construction Procedures [Including but not limited to: Codes, Standards, and Executive Orders]

PG-18-4 Standard Details and CAD Standards

PG-18-5 Equipment Guide List

H-18-8 Seismic Design Handbook

PG-18-9 Space Planning Criteria

PG-18-10 Design Manuals (by discipline) http://www.cfm.va.gov/til/index.asp http://www.cfm.va.gov/CFM/TIL/spec.asp http://www.cfm.va.gov/CFM/TIL/cPro.asp http://www.cfm.va.gov/CFM/TIL/sDetail.asp http://www.cfm.va.gov/CFM/TIL/equip.asp http://www.cfm.va.gov/CFM/TIL/seismic.asp http://www.cfm.va.gov/CFM/TIL/planning.asp http://www.cfm.va.gov/cfm/til/dManual.asp

Kansas City, MO 64128

[Including but not limited to: Guiding Principles checklists as indicated for Minor Projects in Sustainable Design Manual, Life Cycle Cost Analysis]

PG-18-12 Design Guides (graphical, by function)

PG-18-13 Barrier Free Design Guides

PG-18-14 Room Finishes, Door, and Hardware Schedules

PG-18-15 Minimum Requirements for A/E Submissions

PG-18-17 Environmental Compliance Manual

H-7545 VA Cultural Resource Management Procedures

The following references should also be used to complete the design documents:

▪ VA Standards Alert 017 – Infrastructure Standards for Telecommunications Spaces and all standards, guides, and manuals incorporated by reference (https://www.cfm.va.gov/til/sAlert/sAlert017.pdf)

Where conflicts exist between VA adopted codes and standards and the documents on the TIL, the A/E shall bring this to the attention of the VA. The resolution of the conflict shall be made by the authority having jurisdiction for VA to ensure consistency department wide.

6. DESIGN COLLABORATION: The A/E during this design project shall collaborate with the VHA Office of Healthcare Environment and Facilities Programs Special Engineering Program (HEFP/SEP) staff, VISN 15 and the Independent Life Safety Review Agent (LS Agent) for the project. Design submittal comments from these contractors, if concurred with by VA, shall be incorporated into the design. HEPF/SEP and/or VISN deliverables shall be coordinated with the A/E’s design submittals to ensure compliance with all requirements are met. The A/E is required to ensure all elements of the design adhere to the Life Safety Code, including recommendations for temporary construction barriers, prior to the Independent Life Safety review.

7. INDEPENDENT LIFE SAFETY REVIEW: The A/E shall incorporate any comments from the VISN 15 Safety Manager - Life Safety Review.

8. ENVIRONMENTAL PROTECTION: The A/E shall assist the VA with completion of a National Environmental Policy Act (NEPA) assessment as required by the Kansas City VAMC. If the NEPA assessment results in potential environmental impacts, the A/E shall be responsible for completing any auxiliary documentation required per PG-18-17 NEPA Interim Guidance for Projects located on the TIL (http://www.cfm.va.gov/til/etc/NEPAGuidance.pdf). Additional requirements may include, but are not limited to, Environmental Assessment, Environmental Impact Statement, and Record of Decision. The NEPA analysis and concluding documentation must be completed by the Final Bid Documents submittal.

9. PHYSICAL SECURITY: The A/E must include a certified physical security specialist. The specialists must be involved with the design beginning with the concept phase and the qualifications must be submitted to the COR for review and approval prior to the concept/basis of design phase. The specialists shall meet the specific requirements listed in the Physical Security Design Manual for Mission Critical Facilities located on the TIL (http://www.cfm.va.gov/til/PhysicalSecurity/dmPhySecMC.pdf). The A/E shall ensure that all aspects of the applicable VA Physical Security Design Manual (Mission Critical Facilities) are incorporated into the design and shall prepare a written report acknowledging compliance as required by the VOC. The A/E must inform the COR of any physical security items that will be difficult http://www.cfm.va.gov/cfm/til/dGuide.asp http://www.cfm.va.gov/CFM/TIL/accessibility.asp http://www.cfm.va.gov/cfm/til/room/RoomFinishes.pdf http://www.cfm.va.gov/til/aeDesSubReq.asp http://www.cfm.va.gov/til/etc/NEPAGuidance.pdf http://www.va.gov/vapubs/viewPublication.asp?Pub_ID=584&FType=2 https://www.cfm.va.gov/til/sAlert/sAlert017.pdf http://www.cfm.va.gov/til/etc/NEPAGuidance.pdf http://www.cfm.va.gov/til/PhysicalSecurity/dmPhySecMC.pdf

Kansas City, MO 64128 to achieve during the concept/basis of design phase of the design and assist the VA with waiver requests as necessary.

10. SUBMITTAL REQUIREMENTS: Design submittals shall follow the requirements of Program Guide, PG-18-15, Volume C - A/E Submission Instructions for Minor and NRM Construction Program dated November 2008. This document is available on the TIL at http://www.cfm.va.gov/til/aeDesSubReq.asp.

Submittal documents shall be prominently marked “For Official Use Only (FOUO)” if they contain qualifying data as defined in VHA Memorandum 2019-11-13 Sensitive Infrastructure Data Classification – For Official Use Only (FOUO). This memo is attached to this SOW as it is hosted on a non-public VHA site (https://vaww.va.gov/vhapublications/ViewPublication.asp?pub_ID=8949).

The A/E shall deliver design submittal documents that follow the iterative phase breakdown for design work in PG-18-15 and as additionally specified below. Specific requirements for each discipline/work product listed under each phase can be found in PG-18-15; it is expected for the phase of design that each of the checked items in the SD/DD/CD columns will be completed for the submittal. The A/E shall attend a review meeting following each design submittal as indicated under the Project Schedule section of this Scope of Work. Each new submittal will incorporate all VA comments from the previous submittal.

The following submittals will be required for this project:

▪ Quality Assurance/Quality Control (QA/QC) Plan

▪ Basis of Design (BD) – 10% o In addition to the requirements in PG-18-15, a Basis of Design is required. Basis of Design is a narrative presentation of facts, sufficiently complete, to demonstrate that the project concept is fully understood, and that subsequent design details, and their ultimate presentation in the final drawings and specifications, will be based on sound architectural and engineering decisions. Conceptual drawings of the planned design and the initial cost estimate will additionally be included.

▪ Schematic Design (SD) – 35%

▪ Design Development One (DD) – 65%

▪ Construction Documents (CD) – 95%

▪ Final Bid Documents (Bid)

11. DRAWING FORMAT: All drawings shall adhere to VA project software requirements for Building Information Modeling (BIM) and Computer Aided Design (CAD) available at http://www.cfm.va.gov/til/projReq.asp. BIM software shall be Revit 2019 or the latest version available to Kansas City VAMC.

The A/E shall provide a computer 3D model and prepare various 3D renderings to present to VA throughout the design phase to adequately represent architectural, mechanical/electrical/plumbing (MEP), site conditions and other items in the design to aide with facility visualization and contractor coordination.

The project BIM model minimum requirements shall be developed to include the systems described below as they would be built, the processes of installing them and to reflect record drawing conditions (possibly incorporating into the Kansas City VAM Master Record Drawing – pending facility expertise).

http://www.cfm.va.gov/til/aeDesSubReq.asp https://vaww.va.gov/vhapublications/ViewPublication.asp?pub_ID=8949 http://www.cfm.va.gov/til/projReq.asp

Kansas City, MO 64128

The deliverable model at the SD, DD, and CD design phases shall be developed to include as many of the systems described below (but not limited to) as are necessary and appropriate at that design phase.

▪ Architectural/Interior Design

▪ Square Footage/Volume

▪ Room Names and Numbers

▪ Architectural Schedules

▪ Architectural Specialties and Woodwork

▪ Doors

▪ Windows

▪ Louvers

▪ Roof

▪ Floors

▪ Ceilings

▪ Vertical Circulation

▪ Walls/Curtain Wall Sizes, Shapes, & Material Data

▪ General Signage

▪ Schedules

▪ Furniture

▪ Equipment

▪ Structural

▪ Foundations

▪ Shafts and Pits

▪ Mechanical

▪ HVAC

▪ Plumbing

▪ Electrical/Telecommunications

▪ Power and Lighting

▪ Steam Distribution

▪ Other Engineering Data as Required

▪ Exterior Building Information

▪ Nurse Call System

▪ Asbestos/Hazardous Material Info

▪ Security System Information (Access Control, Security

Cameras, Panic Alarms, Overhead Paging)

▪ Life Safety Information (Fire Extinguishers, Wall

Ratings, Door Ratings, Fire Protection/Alarms)

▪ Departmental Ownership (By Common Name, Capital Asset Inventory Department Definition and Strategic Capital Investment Program Department Definition)

12. SUBMITTAL FORMATS: Submittals shall be submitted in electronic format and hard copy formats as listed below. Portable Document Format (.pdf), Microsoft Office Suite formats (.doc, .xls, and .ppt), Microsoft Project (.mpp) and Autodesk Revit Project (.rvt) files are acceptable. Submittals shall additionally be compliant with Section 508 of the Rehabilitation Act (29 U.S.C. '794 d); information on the requirements for accessible media can be found at http://www.section508.gov/. The A/E shall be responsible for providing:

A. Meeting/Conference Minutes: Meeting minutes for all formal meetings and conferences held with the VA; including weekly construction meetings. Meeting minutes shall be submitted within seven (7) calendar days of the meeting or conference. All documents in any of the electronic formats listed above.

▪ Minimum meeting minutes requirements:

▪ Project name, number, meeting host, Meeting Name

▪ Date, Time, meeting ID, call in number, Duration, and consecutive number of total related meetings

▪ Participant list (Name, Title, Phone number (office and Mobile), Email, Attended

Meeting (yes/no Check box)

▪ Meeting purpose, Roll call, COVID-19, and Additional Items

▪ Agenda items (Decisions, action items, and fixes or next steps)

▪ Next meeting date and time

▪ Detailed attachment list

B. Construction Cost Estimates: Construction cost estimates shall comply with Manual for Preparation of Cost Estimates & Related Documents for VA Facilities dated. This document is http://www.section508.gov/

Kansas City, MO 64128 available on the TIL at http://www.cfm.va.gov/cost/index.asp. All estimates in any of the electronic formats listed above.

C. Quality Assurance/Quality Control (QA/QC) Plan

▪ All documents in any of the electronic formats listed above.

D. Basis of Design (BD)

▪ Two (2) half-size paper bond sets of drawings – 2 to VA

▪ One (1) full-size paper bond set of drawings – 1 to VA

E. Schematic Design (SD)

▪ Two (2) half-size paper bond sets of drawings – 2 to VA

▪ One (1) full-size paper bond set of drawings – 1 to VA

▪ Two (2) paper bond sets of specifications – 2 to VA

▪ Two (2) paper bond sets of investigation reports, design calculations, space planning data and cost estimate – 2 to VA

F. Design Development (DD), and Construction Documents (CD)

▪ Memo annotating what was not upgraded and corresponding justifications.

▪ Two (2) half-size paper bond sets of drawings – 2 to VA

▪ One (1) full-size paper bond set of drawings – 1 to VA

▪ Two (2) paper bond sets of specifications – 2 to VA

▪ Two (2) paper bond sets of investigation reports, design calculations, space planning data, construction schedule, construction statement of work (SOW), and cost estimate – 2 to VA

G. Final Bid Documents (Bid)

▪ PDF and dwg files of drawings, PDF and word or excel files of specifications, and any miscellaneous design analysis documents such as submittal log and physical security compliance report.

▪ Certified memo annotating what areas/times were not upgraded and the corresponding justifications.

▪ Certified memo that the A/E design is independent of future projects and includes all equipment required for the project to be activated/full functional.

▪ Word and PDF files of specifications.

▪ Revit and AutoCAD files of drawings.

▪ Two (2) half-size paper bond sets of drawings – 2 to VA

▪ One (1) full-size paper bond set of drawings – 1 to VA

▪ Two (2) paper bond sets of specifications – 2 to VA

▪ One (1) paper bond sets of investigation reports, design calculations, space planning data, construction schedule, construction SOW and cost estimate – 1 to VA

H. Requests For Information (RFI): Requests For Information shall be submitted within three (3) calendar days of submittal to the A/E.

http://www.cfm.va.gov/cost/index.asp

Kansas City, MO 64128

I. Submittal Reviews: Submittal reviews shall be submitted within seven (7) calendar days of submittal to the A/E.

J. Site Visit Reports: Site visit reports shall be submitted within seven (7) calendar days of the visit.

All documents in any of the electronic formats listed above.

K. Modification/Change Order Requests: Modification requests shall be submitted within seven (7) calendar days of submittal to the A/E. This includes the review of the contractor’s change order/modification proposal for construction change orders, as well as the formulation of an IGCE for the modification, as requested. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes. All documents in any of the electronic formats listed above. Note - If major modification, VA will provide additional time and document format guidance.

L. Punch List: Punch list shall be submitted within seven (7) calendar days of the final acceptance inspection. All documents in any of the electronic formats listed above.

M. Record Drawings: Record drawings shall be delivered to the VA within thirty (30) calendar days after VA acceptance of the construction project. Autodesk Revit Project (.rvt) format and AutoCAD (.dwg) format.

13. PROJECT SCHEDULE/PERIOD OF PERFORMANCE: The A/E shall perform Part One Services/Design Phase work according to the schedule shown below. The A/E is also responsible for following specification Section 01 32 16.10 Architectural and Engineering CPM Schedules, which is located in SOW ATTACHMENT 3 – Architectural and Engineering CPM Schedules. If a due date on the timeline below falls on a Holiday or Weekend, the submittal shall be due the following business day. The remaining timeline will not be shifted to accommodate Holidays or Weekends.

QA/QC Submittal & Basis of Design (BD) 10% Submittal

59 calendar days after receipt of Notice of Award

QA/QC and BD 10% Submittal Review Meeting

10 calendar days after VA receipt of QA/QC & BD 10%

Submittals

35% SD Submittal

45 calendar days after acceptance of QA/QC & BD 10%

Submittals

35% SD Review Meeting

10 calendar days after VA receipt of 35% SD Submittal

65% DD Submittal

45 calendar days after VA acceptance of 35% SD

Submittal

65% DD Review Meeting

10 calendar days after VA receipt of 65% DD Submittal

Kansas City, MO 64128

95% CD Submittal

45 calendar days after VA acceptance of 65% DD

95% CD Review Meeting

10 calendar days after VA receipt of 95% CD Submittal

Final Bid Documents Submittal

10 calendar days after VA acceptance of 95% CD

Final Bid Documents Acceptance Meeting

10 calendar days after VA receipt of Final Bid Documents

Total Part One Services/Design Phase Schedule

254 calendar days

The 254 days listed in part one project schedule may fluctuate based on when 95% CD submittal meets all VA guidelines and acceptance is issued. If 95% CD submittal is not accepted due to insufficient design requirements throughout the design period and additional time is deemed necessary, it is the responsibility of the AE firm to cover all costs associated with such delays.

Part Two Services/Construction Period Services (optional Line Items) shall be performed for the length of time between the time the option(s) are exercised and acceptance of Construction Completion. The VA has 365 calendar days from final acceptance of the design to exercise the option(s) for Construction Period Services.

14. SOLICITATION SUPPORT SERVICES (OPTION ITEM)

AE shall provide solicitation support services during the construction period’s solicitation phase.

Pre-bid site visit to include meeting and project walk around. This is the meeting where contractors are invited to the job site to visually inspect the construction site in order to accurately develop a construction bid package. The AE shall be available during this entire site visit to assist the VA in answering any contractor questions. All questions shall be logged by the AE and will be submitted in writing by the contractor to the Contracting Officer. Responses may not be provided verbally onsite.

Answer any technical questions/requests for information (RFI) received from contractors over the duration of the solicitation, including questions asked during the site visit. Questions from contractors may come at multiple times and cover several or a few questions over the course of the solicitation period. Technical question responses will be provided to the Contracting Officer who will distribute the information via amendment to the solicitation. Answers to RFIs will be required from the AE within five

(5) calendar days of the date the questions are sent to the AE from either the project COR or CO. An alternate response period may be submitted for review, however, unless approved by the CO and COR, the AE is required to comply with the seven (7) calendar day requirement. Throughout the solicitation period, the AE shall provide addenda as necessary if required to revise specs and drawings. In response to any technical questions and/or addenda issued during the solicitation period, the AE shall provide any final revisions to the 100% FC CD as part of the construction contract. These documents shall be labeled Final Construction.

15. CONSTRUCTION PERIOD SERVICES (OPTION ITEM)

Kansas City, MO 64128

Construction Period Services (CPS) – CPS shall be provided for entire duration of construction Contract.

Although the AE is directed to design the construction project for a duration of five

(5) months from the effective date of the exercised option, which accounts for potential differing site conditions, design errors, and requirement changes; this duration may change with the exercising of an option line item. The AE shall provide following Construction Period Services:

Requests for Information (RFI) When necessary for contract in-scope changes to construction project requirements, prepare construction cost, completion schedule estimates and Construction Bulletins (CBs). AE RFI review time shall not exceed 7 calendar days. When CB is not for a design deficiency, VA will issue an RFP to the AE for re-design during CPS. Otherwise, CB shall be at no added cost to government. CBs include narrative cover page, stamped drawings or sketches, and edited/added specifications as well as a construction cost estimate. A full CB, if required, is due to VA within same 7 calendar day RFI response timeline. A CB is not required for simple clarifications, selections among options in contract specifications, nor for as-built markups within tolerance qualifying as “field adjustment” by Construction Contractor. CBs are required when any change occurs to scope, schedule, cost, or quality standards. CB drawings shall consist only of full-size drawing sheet edits, with numbered clouds and title bar notation in format to be given by VA. If additional details are needed, they shall be inserted into existing detail sheets. If they do not fit, a new detail sheet will be created, and cover sheet with TOC shall be updated accordingly. AE shall maintain an electronic version of Contract Set of drawings and specifications that reflects CBs through current version. From that date forward, Construction Contractor will use updated set as their as-built set for “field adjustment” markups.

Submittal Reviews Submittal reviews shall be submitted within seven (7) calendar days of submittal to the A/E. This service includes reviewing and providing comments and recommendations to government on items such as construction contractor’s quality control plan, initial and final network schedules, bar chart schedules, schedules of prices, safety plan, shop drawings (including MEP coordination drawing, shop drawings, diagrams, layouts, catalog cuts, performance and test data, samples finish chips, etc.), operation and maintenance manuals, and as-built drawings. For items that are shown as "CONDITIONAL, RE-SUBMITTAL REQUIRED", or "REJECTED" AE shall include an explanation that clearly describes reason(s) for recommended action.

Attendance at Meetings Attendance at various meetings such as pre-construction (kick-off) conference, routine quality control meetings, safety meetings, change order negotiations, claims meetings, scheduling meetings, and other conferences between government and construction contractor may be required by government. These meetings primarily pertain to weekly construction meetings but may include other various meetings, change order negotiations, claims meetings, scheduling meetings, and other conferences between government and construction contractor as may be called by government. AE should plan on a senior architect/engineer familiar with entire design, to attend each construction meeting phone call and furnish meeting minutes during the construction period.

Site Visit Reports Site visit reports shall be submitted within seven (7) calendar days of the visit. All documents in any of the electronic formats listed above.

Kansas City, MO 64128

Modification/Change Order Requests Modification requests shall be submitted within seven (7) calendar days of submittal to the A/E.

This includes the review of the contractor’s change order/modification proposal for construction change orders, as well as the formulation of an IGCE for the modification, as requested. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.” All documents in any of the electronic formats listed above. Note - If major modification, VA will provide additional time and document format guidance.

Punch List Punch list shall be submitted within seven (7) calendar days of the final acceptance inspection.

The punch list shall include pictures and estimated costs. All documents in any of the electronic formats listed above.

Record Drawings Record drawings shall be delivered to the VA within thirty (30) calendar days after VA acceptance of the construction project. AE shall prepare Record Drawing set at construction completion. Add any new drawings and review Construction Contractor’s annotated drawings.

Verify accuracy of contractor interim record drawings and as-built conditions as construction contractor document changes occur. Receive and review contractor “red-line” in preparation for production of final as-builts. Deliver electronic (AutoCAD) and hard copy record drawings to VAMC COR within 30 days of receipt of full as-built package from General Contractor. AutoCAD files shall not include external references.

Third-Party Commissioning

The A-E shall provide third party Commissioning and Commissioning Agent services and deliverables in accordance with the reference document, OCFM Whole Building Commissioning Process Manual located on the TIL (https://www.cfm.va.gov/til/Cx-RCx/CxManual.PDF). See “Commissioning Agent Tasks” in each section of the reference document. The Commissioning Agent shall be involved in all phases of the project, including both design and construction. It is anticipated that the Commissioning Agent will participate in the following: design reviews, owner’s requirements updates, design phase commissioning planning (facilitate), commissioning specification reviews (facilitate), construction project meetings, construction observation visits, equipment startup and testing, Testing Adjusting and Balancing (TAB) verification, and project commissioning (facilitate in coordination with General Contractor). The commissioning process shall be adapted to the size and complexity of the project. Deliverables shall be as described in the reference document. Additionally, the Commissioning Agent shall develop the commissioning plan, pre-functional checklists, systems functional performance test checklists, integrated system test checklists, and edited master specification templates to serve as a starting point for the commissioning process on all projects based on the following Systems to be Commissioned.

https://www.cfm.va.gov/til/Cx-RCx/CxManual.PDF

Kansas City, MO 64128

• HVAC (VA Master Specification Section 23 08 00): Direct Digital Control System, Chilled Water System, Condenser Water System, Steam/Heating Hot Water System, HVAC Air Handling System, HVAC Ventilation/Exhaust Systems, HVAC Terminal Unit Systems, Decentralized Unitary HVAC Systems, Humidity Control Systems, Hydronic Distribution Systems

• Electrical (VA Master Specification Section 26 08 00): Grounding and Bonding Systems, Electric Power Monitoring Systems, Low-Voltage Distribution System, Emergency Power Generation Systems

• Communications (VA Master Specification Section 27 08 00): Grounding and Bonding Systems, Structured Cabling System

• Electronic Safety and Security (VA Master Specification Section 28 08 00): Grounding and Bonding, Physical Access Control Systems, Access Control Systems, Security Access Detection Systems, Video Surveillance System

• Thermal and Moisture Protection (VA Master Specification Section 07 08 00): Facility exterior closure, related subsystems and related equipment.

• Plumbing Systems (VA Master Specification Section 22 08 00): Plumbing systems, subsystems and equipment.

• Site Utility Systems (VA Master Specification Section 33 08 00): Facility site utilities systems, related subsystems and related equipment

Cost Proposals The A/E shall review the Contractor's requests for information and cost proposals for construction change orders when requested by the COR. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.

16. CONTRACT OVERSIGHT: All contracts for this project shall be awarded by Program Contracting Activity Central – PCAC; only a warranted VA Contracting Officer shall have authority to change the terms and conditions of a contract. These changes may involve the contract award amount, contract period of performance, issuance of stop work orders and changes to the statement of work.

The PCAC shall designate a Contracting Officer’s Representative (COR) to monitor and manage the A/E’s performance under the design project contract. The COR shall be a representative of the Kansas City VAMC Engineering Service Project Section and have the technical knowledge required to monitor and oversee the project.

A COR from the Kansas City VAMC Engineering Service shall also be designated for the construction project contract to monitor and manage the construction contractor’s performance under the

Kansas City, MO 64128 construction project contract. This designation under the construction contract shall be considered equivalent to the industry standard of “Owner’s Representative” and does not supersede or eliminate the A/E’s responsibility for Part Two Services/Construction Period Services. The A/E ultimately shall be responsible for any errors and omissions with the design discovered during and after the construction phase.

17. OI&T INFRASTRUCTURE STANDARD FOR TELECOMMUNICATIONS SPECS: The current version for this standard is version 3.1, dated July 1, 2021 (https://www.cfm.va.gov/til/dguide/OIT- InfrastrucStdTelecomSpaces.pdf). The design for this project at Kansas City VAMC must meet the Campus Support Center (CSC) requirements of the Infrastructure Standard for Telecommunications Spaces.

The Infrastructure Standard for Telecommunications Spaces (The Standards) serves as the master reference document of criteria for Department of Veterans Affairs (VA) facility Information Technology (IT) support infrastructure. It defines the technical requirements necessary to maintain optimum reliability and efficiency within VA facilities and computing centers. IT Support Infrastructure is defined as all passive telecommunications and information technology equipment and supporting physical space and equipment.

This standard is owned and maintained by Solution Delivery (SD) Data Center and Infrastructure Engineering and questions or concerns should be directed to the following email group: OIT ITOPS SD Data Center and Infrastructure Engineering.

Users must ensure their use of this technology/standard is consistent with VA policies and standards, including, but not limited to, VA Handbooks 6102 and 6500; VA Directives 6004, 6513, and 6517; and National Institute of Standards and Technology (NIST) standards, including Federal Information Processing Standards (FIPS). Users must ensure sensitive data is properly protected in compliance with all VA regulations. Prior to use of this technology, users should check with their supervisor, Information Security Officer (ISO), Facility Chief Information Officer (CIO), or local Office of Information and Technology (OI&T) representative to ensure that all actions are consistent with current VA policies and procedures prior to implementation.

20. INFORMATION SECURITY:

The C&A requirements do not apply, and that a Security Accreditation Package is not required

21. BADGING REQUIREMENTS:

All employees of A/E firm and subcontractors shall comply with VA security management program and obtain VA badges. This will likely require fingerprinting and background checks of each individual. The employees of the A/E will obtain permission of the VA Human Resources, be identified by project and employer, and restricted from unauthorized access.

TRAINING:

All contractor employees and subcontractor employees requiring access to VA information and VA information systems shall complete VA Privacy and Information Security Awareness and Rules of Behavior Training. The contractor shall provide to the contracting officer and/or the COR a copy of the training certificates and certification of signing the Rules of Behavior for each applicable employee within 1 week of the initiation of the contract and annually thereafter, as required. Failure to complete https://www.cfm.va.gov/til/dguide/OIT-InfrastrucStdTelecomSpaces.pdf https://www.cfm.va.gov/til/dguide/OIT-InfrastrucStdTelecomSpaces.pdf

Kansas City, MO 64128 the mandatory annual training and sign the Rules of Behavior annually, within the timeframe required, is grounds for suspension or termination of all physical or electronic access privileges and removal from work on the contract until such time as the training and documents are complete.

22. REPORTING REQUIREMENTS:

The Contractor shall be required to report to the Facilities Management Service Office, Bldg. 6 2nd Floor to check in during normal working hours. After hour site investigation shall be scheduled with the VA COR. Identification badges will be sponsored by the COR and scheduled with the VA Police Service.

When the service is completed, the Contractor shall document services rendered on a legible field service report. The Contractor shall return to the same service and building to submit the field service report to the COR for signature during normal working hours or send to the COR the next business day if after hour services are performed.

16. SOW ATTACHMENTS: The following list of documents are attached to this SOW for A/E use and incorporation into the project documents:

▪ SOW Attachment 1 – Sensitive Infrastructure Data Classification For Official Use Only FOUO

▪ SOW Attachment 2 – Architectural and Engineering CPM Schedules

▪ SOW Attachment 3 – VHA Directive 1013 Prevention and Control of Seasonal Influenza with

Vaccines

▪ SOW Attachment 4 – VHA COVID-19 101 for NON Clinical Staff-Others

▪ SOW Attachment 5 – Site Map & Reference Drawings

▪ SOW Attachment 6 – Post Award Specs-Drawings Review Checklist

File details come from the government source that posted it. Updated .