This Statement of Work (SOW) details a construction project to replace the roof on Building 33 at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The project involves replacing 4,020 square feet of roofing, including the vestibule, with a total performance period of 90 calendar days. Specific roofing materials include TPO membrane, FR-50 slip sheet, 5/8" CDX Plywood sheathing, crickets, metal scuppers, and a parapet metal cap.
The solicitation is anticipated to be 100% set aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) under NAICS code 238160, with a small business size standard of $19M. The project is valued between $500,000 and $1,000,000, with the solicitation expected to be issued on July 14th, 2025, via SAM.gov. The contractor will be responsible for providing all equipment and supplies, delivering as-built drawings and an O&M manual within 30 days of substantial completion, and using a secured FTP site for electronic document transmission.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 4 B33 Roof As Built 668-25-107.pdf | ||
| 36C26025R0078.docx | DOCX document | |
| Attachment 2 Specifications 668-25-107 V2.pdf | ||
| Attachment 3 Roof ACM Survey 668-25-107.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK FOR CONSTRUCTION SERVICES
Replace Building 33 Roof Mann-Grandstaff VA Medical Center
Spokane, WA May 27, 2025
Attachments to this document include the following. Contact the CO if any items are missing.
• B33 Roof As-Built Drawing
• MGVAMC Building 33 Roof ACM Survey
• Project Specifications
1. General Provide construction services to include labor, materials, tools, equipment, transportation, supervision, and other services necessary for Project 668-25-107, Replace Building 33 Roof at the Mann-Grandstaff VA Medical Center, Spokane, Washington. Total project period of performance shall be 90 calendar days.
2. Statement of Work
2.1 This project will replace 4020 SF of roofing on Building 33 to include the vestibule in accordance with the provided project drawings and project specifications. Replacement to include TPO membrane, FR-50 slip sheet, 5/8” CDX Plywood sheathing, crickets, metal scuppers, and the parapet metal cap.
See Bldg 33 Roof drawing for roof construction.
2.2 Provide commissioning services for the roof replacement.
3. Performance of Work
3.1. Where conflicts exist between this SOW and the project specifications or project drawings, this SOW takes precedence.
3.2. Document transmission.
3.2.1. VA email servers limit file sizes to 5MB per message.
3.2.2. Construction Contractor shall provide a secured File Transfer Protocol (FTP) site to transfer all contract electronic submittals. The contractor shall send a corresponding email to the COR stating a file is ready for review for each electronic submittal FTP upload, an automatic email from the FTP site is sufficient. The FTP site shall be accessible by VA staff using Government Furnished Equipment (GFE).
3.3. As-Built Drawings and Operation and Maintenance (O&M) Manual.
3.3.1. The contractor shall deliver the as-built drawings and owner’s manual to the COR no later than thirty (30) days after substantial completion.
3.4. The government does not guarantee the accuracy or completeness of any of the information provided in the attachments to this SOW. The contractor shall make assessments to determine existing conditions prior to the inception of work.
3.5. The contractor will not have access to any Government-Furnished Equipment.
All equipment and supplies used under the terms of this contract shall be the responsibility of the contractor.