ATTACHMENT 1 SOW 618-16-101 CONSTRUCT EVIDENCE BASED INPATIENT WARD 2K2H.pdf
PDF 99 KB Posted
- Attached to
- Z2DA--Construct Evidence Based Wards (VA-20-00046403) Federal contract opportunity
- Solicitation number
- 36A77620R0004
About this file
This document outlines a forthcoming federal contract solicitation for construction services. The Department of Veterans Affairs intends to solicit and award a firm-fixed-price contract to construct a new Evidence Based Inpatient Care ward at the Minneapolis VA Medical Center. The project scope includes full renovation of an existing ward including installation of a new air handling unit, conversion of rooms to a patient waiting area and conference room, and renovation of other areas into an office and simulation room. The solicitation will be issued as a request for proposal to Service-Disabled Veteran-Owned Small Businesses only. The contract period of performance is approximately 390 calendar days with a project magnitude between $5,000,000 to $10,000,000. The solicitation is scheduled for release on or around July 22, 2020.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
CONSTRUCT “EVIDENCE BASED INPATIENT WARD 2K/2H”
PROJECT #618-16-101
MINNEAPOLIS VA MEDICAL CENTER
A. PART I - GENERAL
A1. Scope of Contract
A. Base Bid: The Contractor shall provide all labor, materials and equipment to accomplish the “Construct Evidence Based Inpatient Ward
2k” project per construction drawings and specifications. The project shall be accomplished per contract drawings numbered 618-16-101, specification number 618—16-101. This work includes, but is not limited to:
1. Demolition:
a. Complete demolition of the existing inpatient ward 2K except as noted in the center area, indicated in the construction documents.
b. Demolition of 2H-101, 2H-102, 2H-103 and 2H-112. Some corridor walls to remain as indicted in construction documents.
c. Contractor shall remove from the VA site and dispose of all equipment and materials not scheduled to be reused. Owner retains right of first refusal on all items to be removed.
Verify with owner prior to disposal.
d. Work must be performed in a careful manner protecting from damage those items not to be removed.
2. New construction consists of, but is not limited to:
a. Full renovation of ward 2K including installation of new AHU.
b. 2H-112 renovation to a patient waiting area.
c. Renovate 2H-102 and 2H-103 and a portion of corridor C2-61 to a large conference room.
d. Renovate 2H-101 and remaining portion of corridor C2-61 to
Resident office and SIM room.
3. Scope of work changes:
a. See attached amendment.
4. Additional project specific notes:
a. Items not noted as to be demolished shall be protected from damage. Any damage not caused by the owner or deemed to be normal wear shall be corrected by the contractor with no additional time and/or money.
b. Temporary construction items such as dust walls, safety barriers, etc. shall be the responsibility of the contractor.
Obtain approval from VA staff prior to the installation of such temporary construction.
c. Coordinate with the VA COR prior to performing shutdowns of electrical power systems, HVAC equipment, chilled water systems, and fire suppression systems for modifications and tie-ins.
5. Phasing: Refer to drawings for phasing information.
Complete 2K then complete 2H.
15 days in between phases
90 days for 2H completion
A3. Tentative Schedule:
Contract award* D
Pre-construction conference D+10
Notice to Proceed D+14
Construction start D+45
Construction completion D+420
A. Schedule Objectives - The anticipated substantial completion of this project is 420 days after “Notice to Proceed” (NTP).
A4. Cost Range
The anticipated cost range for this project is between
Between $5,000,000 and $10,000,000.