This statement of objectives (SOO) outlines requirements for upgrading fiber optic cable in the munitions area at Kadena Air Base in Japan. The contractor must deliver fiber optic cable and install and test the cable to connect multiple buildings on the base. The contractor is responsible for providing all necessary equipment, labor, project management, and incidentals to complete the installation and testing of the cable system in compliance with telecommunications industry standards and base requirements. The period of performance is one year from date of award, with work to commence no later than September 2023.

The SOO specifies technical requirements for the fiber optic cable installation, including safety compliance, site coordination, accident reporting, work areas, traffic control, security clearances, environmental compliance, permits, drawings, testing plans, and deliverables. It provides cable footage breakdowns by zone and fiber count. Appendices further define backbone, zone 1-4, and other infrastructure requirements. Project drawings depict cable routes and locations for maintenance holes, buildings, and other aspects of the work.

View the file

Other files for this federal contract opportunity

Other files attached to FIBER OPTICS CABLE; MUNS AREA, newest first.
File Type Posted
FA527023RA113-0003_SF-30.pdf PDF
Attachment 5_Answers_20230925.pdf PDF
Attachment 5 - Answers.pdf PDF
FA527023RA113-0002_SF-30.pdf PDF
FA527023RA113-0001_SF-30.pdf PDF
Attachment 4 - Site Visit.docx DOCX document
Attachment 4 - Site Visit.docx DOCX document
Attachment 3_DFAS Japan AF EFT Submission.pdf PDF
Attachment 2_DEAMS EFT Enrollment Form Updated 10_2022.pdf PDF
FA527023RA113_Combo_Service.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

UNCLASSIFIED

STATEMENT OF OBJECTIVES (SOO)

FOR

UPGRADE OF FIBER OPTIC CABLE IN

MUNITIONS AREA

AT

KADENA AIR BASE (AB), JP

12 SEPTEMBER 2023

Prepared By

38 ES/ENII

4064 Hilltop Road

Tinker AFB OK 73145-2713

Page | 2

1.0 SCOPE.

This Statement of Objectives (SOO) defines the requirement for the Contractor to furnish fiber optic cable (FOC) to be delivered to the 18th Communications Squadron. The contractor must also provide incidental services to install and test the FOC for each building indicated in all zones in the 18th Munitions area at Kadena AB, Japan. The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to provide a complete and workable system. The Contractor shall comply with the current Telecommunications Industry Association (TIA) telecommunication installation and testing commercial standard and base installation standards. All equipment, supplies, and materials provided shall be new and not refurbished.

2.0 BACKGROUND

The 18th Munitions Squadron manages the Air Force’s largest munitions complex, encompassing 475 facilities across 5,900 acres. The majority of the facilities currently rely on outside plant copper cables to provide network connectivity and experience ongoing issues due to cable degradation. The new fiber optic cables will allow Voice over Internet Protocol to be implemented in each facility and to migrate away from the aging direct buried copper cables. Additionally, the fiber optic cable would be able to provide a reliable network path for Intrusion Detection Systems in secure facilities throughout the munitions complex. This will allow the facilities to comply with Air Force Instruction 31-101 and Department of Defense Manual 5100.76.

3.0 REQUIREMENTS.

3.1 GENERAL REQUIREMENTS.

3.1.1 Safety Requirements

The contractor shall comply with all Federal, county, and base security and safety laws, regulations, policies, and requirements.

3.1.2 Site Coordination.

The Contractor shall meet with the base safety officer upon arrival on site for review of the specific safety requirements prior to installation. If Asbestos Containing Materials/Lead Based Paint (ACM/LBP) is positive, there will be no abatement and The Contractor will be required to wear Personal Protective Equipment (PPE) to complete the work.

3.1.2.1 Confined Space.

The Contractors and Sub-contractors entering spaces on Kadena AB are responsible for the safety of their personnel and for their own permit space program as outlined in AFMAN 91-203. All confined space operations must be coordinated with the Base Safety Office prior to start of work. The primary Contractor is responsible for all Sub-contractor confined space operations.

3.1.2.2 Accident/Incident Reporting and Investigation.

The Contractor shall record and report all facts relating to each instance of injury to either Contractor or Government personnel. Notification shall be provided to the 18 CS/SCXP Project Manager (PM) (DSN 632-3215 or E-mail:

18CS.SCXP@us.af.mil) and the Base Safety Office (DSN 634-7233) unless otherwise stated in the SOO. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to investigate of the incident, the

Page | 3

Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.

3.1.2.3 Work Area(s).

At day’s end, the Contractor shall remove all debris and surplus materials from the workplace. Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the workday. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard. The contractor shall co-ordinate with the 18 CS/SCXP to ensure that any locking manhole covers are put back in place at the end of each workday.

3.1.2.4 Traffic Control.

In the event base vehicular traffic is disrupted by trenching or horizontal directional boring, the Contractor shall notify the 18 CS/SCXP PM No Later Than (NLT) 10 calendar days in advance to inform base Security Forces and Emergency Services personnel of the planned disruptions.

3.1.2.5 Airfield Driving.

Any person operating a motor vehicle inside the airfield fence on Kadena AB shall coordinate with airfield management to obtain the required training/certifications IAW local procedures.

3.2 Security Requirements.

The Contractor shall process and provide a Site Visit Request Letter to 18 CS/SCXP within 5 calendar days after contract award. This letter shall identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who will be performing work under this SOO. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.

3.2.1 Security Clearances.

Stated work and associated products shall be performed at the UNCLASSIFIED level.

However, some of this work may take place in secure areas where Contractor employees must be escorted at all times. The Contractor must coordinate access to secure areas at least five (5) calendar days ahead of time. It is the Government’s responsibility to provide escorts.

3.2.2 Operational Security (OPSEC). “Reserved.”

3.3 Environmental Compliance.

The Contractor shall comply with the most stringent environmental federal, and local laws and regulations, and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The Contractors are responsible to know and follow all applicable Federal, Local and Air Force regulations for environmental protection, including waste disposal, sewer discharge, air emissions, and storm water requirements. The contractor shall maintain an awareness of changing

Page | 4 environmental regulatory requirements to avoid environmental deficiencies for activities on Kadena AB.

The Prime Contractor shall ensure that their subcontractors (if any) comply with these specifications.

3.4 Permits.

3.4.1 The Contractor shall be responsible to coordinate, complete and process all permits required to complete the installation IAW TIA, UFC, and Kadena AB standards.

3.4.2 All utility markings, flags, etc. shall be maintained by the contractor after the responsible work center/shop identifies/locates them.

3.4.3 FAR 52.237-2 Protection of Government Buildings, Equipment, and Vegetation (Apr 1984), states that The Contractor shall use reasonable care to avoid damaging existing buildings, equipment, and vegetation on the Government installation. If the Contractor’s failure to use reasonable care causes damage to any of this property, the Contractor shall replace or repair the damage at no expense to the Government as the Contracting Officer directs. If the Contractor fails or refuses to make such repair or replacement, the Contractor shall be liable for the cost, which may be deducted from the contract price.

3.5 Integrated Process Team (IPT).

The Contractor shall chair a monthly/or as needed (depending on the weekly report; see para 2.1.7) IPT meeting that includes Contractor representatives, the Government Contracting Officer (CO), the Cyberspace Systems Integrator-Base (CSI-B), the System Engineer(s), the Government Project Manager, and other base personnel as required. The Contractor shall provide an agenda NLT 1 working day prior to the scheduled meetings. The Contractor shall provide worldwide “Meet Me” teleconference capability for the duration of the project. The Contractor shall provide worldwide “Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute to the attendees NLT 1 working day after each meeting.

3.6 Quality Assurance.

3.6.1 A weekly report (soft copy) shall be delivered/submitted to COR by COB Monday, indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them.

3.6.2 FAR 52.212-4(a) Contract Terms and Conditions—Commercial Products and Commercial Services (Dec 2022), Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights-(1) Within a reasonable time after the defect was discovered or should have been discovered; and (2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

Page | 5

3.6.3 FAR 52.246-1 Contractor Inspection Requirements (Apr 1984), The Contractor is responsible for performing or having performed all inspections and tests necessary to substantiate that the supplies or services furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers’ parts. This clause takes precedence over any Government inspection and testing required in the contract’s specifications, except for specialized inspections or tests specified to be performed solely by the Government.

3.6.4 FAR 52.246-2 Inspection of Supplies-Fixed-Price (Aug 1996), The Contractor shall provide and maintain an inspection system acceptable to the Government covering supplies under this contract and shall tender to the Government for acceptance only supplies that have been inspected in accordance with the inspection system and have been found by the Contractor to be in conformity with contract requirements. As part of the system, the Contractor shall prepare records evidencing all inspections made under the system and the outcome. These records shall be kept complete and made available to the Government during contract performance and for as long afterwards as the contract requires. The Government may perform reviews and evaluations as reasonably necessary to ascertain compliance with this paragraph. These reviews and evaluations shall be conducted in a manner that will not unduly delay the contract work. The right of review, whether exercised or not, does not relieve the Contractor of the obligations under the contract.

3.7 Contractor Personnel.

3.7.1 Project Management.

The Contractor shall provide a PM and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.

3.7.2 Site Point of Contact (POC).

The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours for the duration of the project, up to and until final acceptance by the Government PM and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.

3.7.3 Personnel Requirements.

The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English and shall be on site to coordinate permits, clearances, and receive shipments/material related to the task order.

3.7.4 Minimum Contractor Qualifications.

All work shall be performed by an experienced Telecommunications Contractor. Each person with the contracting company needs to have a minimum of 3 years of experience in Telecommunications Systems installations.

Page | 6

3.8 Warranty

The Contractor shall provide a one-year warranty or manufacturer’s standard commercial warranty, whichever is longer. This warranty shall include a one-year workmanship warranty. The warranty period shall start from the date of system and/or project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.

3.9 Manuals and Practices.

The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new equipment.

3.10 List of equipment to be used.

The contractor shall provide an itemized list of equipment that will be used during the installation of the project.

3.11 Project Residue.

All residue from this project shall be disposed of off base and in accordance with Federal, local and base environmental laws and regulations. All residue produced by horizontal directional boring operations (i.e., slurry) shall be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor’s expense, IAW federal and local environmental laws and regulations. Under no circumstances will the contractor stage or store boring residue in slurry ponds or other containment areas on Kadena AB.

3.12 Site Restoration.

The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. The Contractor shall comply with all base ground’s restoration requirements. Common use areas shall be restored with sod.

3.13 Service Outages.

The Contractor shall be responsible for preventing any unscheduled (i.e., cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).

3.14 Identification/Marking.

The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign (minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name and both the Contractor and Site POC's names and local telephone numbers.

3.15 Installation Schedules.

The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system. All submissions shall be delivered electronically in MS Office-compatible format NLT 10 business days after contract award and as significant schedule changes occur to be determined by the IPT.

Page | 7

3.16 Weekly Status Reports.

The Contractor shall prepare a Weekly Status Report and distribute to the Government CO, CSI-B, the System Engineer(s), the Government Project Manager, and other base personnel as required. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.

3.17 Drawings

3.17.1 As-Built Drawings.

The 18 CS/SCXP shall supply existing system Drawings, and the Contractor shall provide updated Drawings in Visio for building and rack elevation; Visio and .pdf for OSP. These Drawings shall depict the entire pathway and details of the installation, including but not limited to labeling, cables, innerducts and maintenance holes/handholes, conduits, maintenance loops, distances, bores, trenches, building entrances. Detailed butterfly Drawings will also be required. If the existing cable diagram or butterfly Drawings are not available; the contractor shall create the missing cable diagram/ butterfly Drawings to include all the components used in this project. The Contractor shall record/deliver geospatial data of new outside plant distribution system.

3.17.2 Butterfly Drawings.

The Contractor shall record and submit butterfly, cable path and building penetration Drawings information for all new installations including butterfly Drawings for all maintenance holes and pull boxes that contain new or reused FOC. Drawings shall record the path and arrangement of new and reused fiber optic cables, splices, and the arrangement duct banks, ducts, inner-duct and shall show maintenance hole orientation with respect to geodetic north. Drawings shall be submitted in an easily read electronic format such as pdf. Scanned data sheets or legible Drawings are acceptable.

3.18 Geospatial Deliverables.

The Contractor shall collect and record geospatial data and provide as-built documentation (shape files) of all new installed maintenance hole/duct system components and new cable components (including metadata) compatible with the Cyberspace Infrastructure Planning System Visualization Component (CVC) drawing system. Data points shall be recorded at the center of each manhole/hand-hole lid and at intervals not to exceed 25 feet along cable routes. Sufficient data points shall be recorded to capture any change in direction along the route. All Global Positioning System (GPS) coordinates shall have +/- 3 feet accuracy for all readings. The government will review the shape files and transcribe the information to the CVC system. Provide geospatial data via CD as Environmental Systems Research Institute Shape files. Shape files shall be delivered within 30 days of project completion.

3.19 Test and Acceptance/Installation Test Plan.

The Contractor shall provide a test plan as to how the system shall be pre-tested, in-progress-tested and post-tested. Draft Cut-over Test Plan shall be submitted NLT 10 calendar days after contract award. Government comments will be provided after review of the draft. A final plan will be submitted 30 calendar days before the actual cut-over date. The Contractor shall test the system to demonstrate to the Government quality assurance representative that the system is fully operational and meets or exceeds the specified requirements and that the system is fully ready to be placed into service. These tests shall be accomplished prior to the system being placed into service.

Page | 8

3.19.1 Testing.

The Contractor shall conduct on-site testing IAW Original Equipment Manufacturers (OEM) installation manuals, practices, and the appropriate vendor’s test procedures. The Contractor shall furnish all test equipment and personnel required to conduct all required testing. During any testing phase, the Government reserves the right to perform any of the contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing.

The Contractor shall participate with the Government in testing the complete communications system. When any system, subsystem, component, or requirement test fails to meet the requirements of the test, Government acceptance and payment will be withheld until such time as the cause of the failure is corrected to the Government’s satisfaction. After appropriate corrective action has been taken, all tests including those previously completed, related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance.

3.19.2 In-progress Testing.

3.19.2.1 Excavations.

All excavations shall be inspected for compliance with applicable installation and safety directives, and installation plan procedures. After material is placed, the contractor shall inspect and document the installation prior to backfilling. In addition, the designated government representative shall be allowed to inspect the installation prior to backfilling.

3.19.2.2 Splices.

All splices shall be tested for cable faults and splicing errors as they are completed. All cable faults and/or splicing errors detected shall be corrected after the completion of each splice point test and prior to sealing the closure. The contractor's Quality Control Manager (QCM) and the designated government representative shall inspect all splices prior to sealing the closure. If, for any reason, moisture contaminates a splice, all modules and/or connectors shall be replaced and the entire splice.

3.19.2.3 Fiber Optic Tests.

All strands of all fiber optic cables shall be tested in accordance with TIA 526-7, Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant, or equivalent. As a minimum, the following tests shall be performed. Both Optical Time Domain Reflectometer (OTDR) and Optical Power Meter tests will be used for all end-to-end circuits. Between FODPs, bi-directional testing at 1310 nm and 1550 nm is required. For incomplete circuits that end in Maintenance Holes, only one-way OTDR testing is required.

3.19.2.4 Optical Attenuation.

End to end attenuation tests shall be conducted on all fiber optic cable strands. All fiber optic cable strands shall be tested in accordance with TIA 526-7 Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant, or equivalent.

3.19.2.5 Distance.

Test to determine the installed cable length between optical patch panels. All strands of all fiber optic cables shall be tested.

Page | 9

3.20 Acceptance/Installation Test Report.

The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan NLT 10 business days after Government Witness Testing is complete.

3.21 Final Acceptance.

The Contractor shall schedule a final project walk-through with the Base POC, including Quality Assurance Officer and PM. The walk-through should be scheduled 5 calendar days prior to acceptance. The contractor shall route the Air Force Technical Order 747 after the base has signed the test report and the walk-through has been completed.

3.22 Deliverable Summary.

All deliverables, including but not limited to the below, are subject to Government acceptance and approval and shall be produced using recommended software tools/versions as accepted by the Government.

4.0 GENERAL INFORMATION.

4.1 Period of Performance.

The fiber optics upgrade must be completed within one (1) year from date of award. The start date must commence no later than September 2023.

4.2 Place of Performance.

The place of performance is Kadena AB, Japan.

4.3 Hours of Operation.

The Contractor shall routinely work during normal duty hours (0730 to 1630). However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the 18 CS/SCXP and approved by the Contracting Officer at least 10 calendar days in advance.

4.4 Holidays/Down Days.

The Contractor shall not perform under this contract on federal holidays: New Year’s Day, Martin Luther King, Jr.’s Day, Washington’s Birthday, Memorial Day, Juneteenth National Independence Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day.

4.5 Base Support.

The Contractor shall identify any base support requirements (for example, laydown and storage areas) necessary to complete this project in their proposal. The contractor shall return all government furnished lay-down and storage areas to their original condition upon completion of the project.

RAMOS, ODINI NIKOLAI R CIV USAF PACAF 18 CONS/PKA

I listed the federal holiday here. Please double check if I missed anything.

WILLIAMS, ANTHONY B TSgt USAF PACAF 18 CS/SCXP Confirmed all federal holidays are listed.

Page | 10

5.0 Appendix A: APPLICABLE STANDARDS.

5.1 The following list is not all-exclusive. The Contractor shall comply with applicable commercial code and standards. The most recent version of the applicable standard at the time of solicitation will be used.

5.1.1 AFMAN 91-203 – Air Force Consolidated Occupational Safety Instruction

5.1.2 OSHA CFR 29 Part 1910-268 – Telecommunications

5.1.3 NEMA TC 2- Electrical Polyvinyl Chloride (PVC) Tubing and Conduit

5.1.4 TIA-606-D Administration Standard for Telecommunications Infrastructure

5.1.5 TIA-568-E Commercial Building Telecommunications (568C.1, 568C.2, 568C.3)

Cabling Standard

5.1.6 TIA-607-D Commercial Building Grounding (Earthing) and Bonding Requirements for

Telecommunications

5.1.7 TIA-526-7- Measurement of Optical Power Loss of Installed Single-mode Fiber Cable

Plant

5.1.8 TIA-569-E - Commercial Building Standard for Telecommunications Pathways and

Spaces

5.1.9 TIA-570-D –Residential Telecommunications Infrastructure Standard

5.1.10 TIA-758B Customer-owned Outside Plant Telecommunication Infrastructure Standard

5.1.11 BICSI TDM Manual - Building Industries Consulting Services International

Telecommunications Distribution Methods (TDM) Manual

5.1.12 BICSI – Outside Plan Design Reference Manual

5.1.13 RUS Bulletin 345-65 (PE-33) – Specification for Shield Bonding Connectors

5.1.14 RUS Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable

5.1.15 RUS Bulletin 1751F-643 - Underground Plant Design

5.1.16 RUS Bulletin 1751F-644 - Underground Plant Construction Telecommunications

Engineering Shield Continuity and Construction Manual (TE&CM) 451.2

5.1.17 RUS Bulletin 1751F-801 – Electrical Protection Fundamentals

5.1.18 RUS Bulletin 1753F-151 (515b) - Specifications and Drawings for Underground Cable

Installation

5.1.19 RUS Bulletin 1753F-201 (PC-4) – RUS Standard for Acceptance Tests and

Measurements of Telecommunications Plant

5.1.20 RUS Bulletin 1753F-207 (PE-87) – REA Specification for Terminating Cables

5.1.21 NFPA 70 - National Electric Code

5.1.22 Unified Facilities Criteria 3-260-01

5.1.23 Unified Facilities Criteria 3-580-01

5.1.24 FGDC-STD-007.3-1998 - Geospatial Positioning Accuracy Standards Part 3: National

Standard for Spatial Data Accuracy

Page | 11

6.0 Appendix B: Backbone Requirement

6.1 SCOPE.

This Statement of Objectives (SOO) defines the requirement for the Contractor to furnish 24-strand Backbone single mode (SM) armored fiber optic cable (FOC) to be delivered to the 18th Communications Squadron. The contractor must also provide incidental services to install and test the FOC for the following buildings. From B44702 to B42432, 49401 in the 18th Munitions (MUNS) area at Kadena AB, Japan.

6.2 SPECIFIC REQUIREMENTS.

As indicated in this SOO and attached Project Drawing, the Contractor shall EFI&T the Backbone SM FOC for B42432 and B49401in the 18th MUNS Area. All associated fiber distribution panel (FODP), splicing and termination shall be included with the installation.

6.3 OUTSIDE PLANT REQUIREMENTS.

6.3.1 Existing Maintenance Holes.

The Contractor shall be responsible for pumping out maintenance holes/handholes.

Water from maintenance holes/handholes shall be drain onto grass, when possible, to act as a natural filter; then it may be pumped out onto the surrounding ground, as long as there is no impact to roads, driveways, or vehicle traffic. Mud and debris shall be disposed of IAW base requirements. If Contractor comes across a manhole with contaminated water, the Contractor shall coordinate with the environmental office in Base CE.

6.3.2 Measurements.

Any distances provided in this SOO are approximations and should NOT be used for ordering materials or determining duct lengths.

6.3.3 Cable Footage Breakdown

Zone Fiber Strand Count Approx. Footage (ft)

Backbone 24 6500

6.3.4 Underground Utilities Markings. N/A

6.3.5 Closures for Cable Splicing in Maintenance Holes.

Intermediate cable splices shall be minimized and consist of fusion splices in a high quality re-enterable splice case. Only splice closures intended for underground applications shall be used in the underground system. The Contractor shall use standard re-enterable fiber splice closures. The closures shall have adequate strength to protect the splice and maintain cable shield electrical continuity in the below ground environment.

The Government quality inspector shall have the opportunity to inspect the inside of the splice case before closure pressure testing and encapsulation is performed. A coil of 25 feet of cable shall be provided on each cable entering and leaving a splice case in a MH or HH.

6.3.6 Splice Connectors.

Page | 12

All splicing shall be performed in accordance with Rural Utilities Service (RUS) Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable. The contractor shall use pic-a-bonds, 3M 710 splice connectors, or equivalent, for all copper splices.

6.3.7 Labeling.

The Contractor shall label all equipment and cables they install, and cables identified for re-use in accordance with TIA-606-D and as directed by the 18 CS/SCXP.

6.3.8 New Ducts.

New ducts shall be permanently labeled on the wall of each building/Maintenance hole (MH)/Handhole (HH) indicating the connecting building/Maintenance hole/Handhole at the other end of the duct (for example, “To MH-306H”). The same information shall appear on the Contractor’s completed as-built-drawings.

6.3.9 Fiber Optic Distribution Panel (FODP) Marking.

Each FODP shall be stenciled/marked with black ink or paint or adhesive backed decals in letters and numbers. The cover of all new FODPs shall be labeled to conform to the system used by local maintenance personnel to identify FODPs that terminate fiber. If the manufacturer has not identified the sequence in which ports on FODPs (pigtail modules) are counted, the Contractor shall provide designation labels/strips to identify the sequence in which they are counted. Each splice tray shall be marked to identify the fiber count contained in the splice tray. The marking shall identify the FODP by number (building number), cable number, and count.

6.3.9.1 Example (FODP): FODP 44702 - 42432, 1-24

6.3.10 FOC Tags.

All tags shall be permanently labeled, easily visible and corrosion resistant. Install cable tags in all maintenance holes/hand-holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a maintenance-hole, put a tag on the cable, approximately 2 feet from each duct entrance. Information on the cable tag shall identify cable by size, type, cable number and count. Tagging and labeling of new cables shall be IAW the following:

6.3.10.1 Example (Fiber Optic Tag):

24L8.3F/ FO 44702 - 42432, 1-24// First line: “24” stands for Fiber Count. “L” stands for Loose Tube Buffer or (“T”) for Tight Tube Buffer. “8.3” stands for Single Mode. “F” stands for Filled Core (otherwise leave blank)// Second line and following: “FO” stands for Fiber Optic cable. “44702 - 42432” stands for From Building Number 44702 to 42432. “1-24” stands for Cable/Strand Count.

6.3.11 FOC Terminations.

Fiber optic cables shall be terminated on new fiber optic distribution panels using fusion spliced factory pigtails with LC connectors.

6.4 FOC Maintenance Loop.

The Contractor shall install a minimum of a 50-foot fiber optic cable maintenance loop at the first MH from the building, at each splice point MH location and at every third manhole. The maintenance loop shall be properly labeled and securely supported by two cable hooks. Cable hooks are to be positioned so the highest one supports the underside

Page | 13 of the top of the coil and the bottom hook supports the underside of the bottom of the coil. The maintenance loop shall have a cable tag. The same information shall appear on the Contractor’s completed as-built-Drawings.

6.4.1 New Maintenance Holes/Hand holes. N/A

6.4.2 Lockable Manhole Covers. N/A

6.4.3 Cable Racks and Cable Rack Supports.

Cable racks shall be installed in maintenance holes and hand holes as required - this includes new and existing MHs/HHs. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case. Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips. All cables shall be supported using racking clips, cable racks, and cable hooks.

6.4.4 Underground Conduit System.

The Contractor shall comply with the applicable standards during the installation of an underground conduit system including, but not limited to, TIA, UFC, and BICSI standards.

6.4.5 Excavation/Building Penetrations

All wall penetrations, including inside buildings, shall be restored to meet the required UFC standards for structural and fire ratings.

6.4.6 Requirement Installation.

This section describes the underground maintenance hole/conduit system, flexible geotextile multiple cell fabric inner-duct and fiber optic cable installation requirements.

The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure in according with TIA-758-B. Each cable installation shall be coordinated with the 18 CS/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion.

See Project Drawing below for reference and estimated distances of existing and proposed infrastructure and cables routes. This is only a proposed design. The Contractor may make any recommendations pertaining to the accomplishment of this requirement in their proposal.

6.4.7 Infrastructure Installation.

The contractor shall install the following new infrastructure. All new locations and distances are approximations.

6.4.8 New Network Cabinet.

All new equipment cabinets shall be lockable and compatible with existing lockable cabinets. Coordinate with the 18CS/SCXP to ensure a common lock/key in all cabinets matching existing locks/keys. Equipment cabinets shall have sufficient ventilation, cable pathway access, and space to allow for maintenance and operation of the equipment.

Page | 14

Consideration must be given to wall mounted cabinets to ensure the long-term ability of the cabinet to be mounted, to stay attached to the wall and for the required clearances to service all cabling and equipment installed with the cabinet. Rail settings within cabinets must be secured, be in a level condition and be positioned so all installed hardware and cables interfacing the hardware do not obstruct the closing of doors when door is in its final position. Existing/previously installed cabinets shall be re-used to the maximum extent possible.

6.4.8.1 Grounding and Bonding

All new and existing racks/cabinets housing equipment for this project, as well as all ladder rack/and cable tray shall be bonded and grounded to the Equipotential Ground Plane IAW TIA-607-B. All Equipment racks and cabinet rails shall be Telecommunications style rails that are unpainted and have drilled and tapped mounting holes IAW DISN Implementation Standards, Ch. 2.7.20 to 2.7.26.

Equipment cabinets shall be capable of containing any standard equipment shelves for communications equipment per the current revision of EIA/ECA-310.

The Contractor shall test any new or extended ground at the cabinet/rack and at the new grounding/bonding points. The government reserves the right to test and validate newly installed grounds to ensure they meet compliance.

6.4.8.2 Bushings

All penetrations into the rack/cabinet must be reamed, filed, and have an installed bushing or grommet material. No exposed metal edges shall come in contact with telecommunication cabling.

6.4.8.3 A.C. Power

Each new equipment cabinet shall have a dedicated 110/120 20A power circuit originating from existing breaker panel. All electrical work shall be labeled at the circuit panel with room and rack identification and at the equipment end with panel and circuit information. All electrical component work shall be performed in compliance with the NEC, UL Listing, and all local, base, and federal codes, requirements, and regulations.

6.4.8.4 New Pull Box/NEMA 4 Enclosure.

The Contractor shall install one NEMA 4X enclosure on the outside wall of B42432. The Contractor shall determine the size of the enclosure needed to satisfy the particular requirement at that location based on the quantity of conduits coming into the enclosure. The contractor shall provide the same quantity of 4” ID sleeve(s) through the building wall. The entry enclosure and riser conduits shall be painted to match the color of the building exterior in the area where it is mounted Coordinate with 18 CS/SCXP.

6.5 New Fiber Optic Distribution Panel (FODP).

The Contractor shall install three 24-port FODPs. One in the B44702, one in B42432, and one in B49401. The location of FODPs shall be provided by 18 CS/SCXP. The FODPs shall be Corning Closet Connector Housing, or an equivalent model, that will provide sufficient capacity for the number of fiber strands being installed.

Page | 15

6.5.1 Duct bank Infrastructure.

The Contractor shall install approximately 50 feet of 2x4” conduit schedule 80 from MH- 510-19-9I to B42432. Coordinate with 18 CS/SCXP for detail.

6.5.2 Geotextile Innerduct (or Innerduct)

The Contractor shall install 3”x3 Geotextile Innerducts as shown in the table below. Each three cell shall have a separate thread color and one of the three cells shall be detectable.

Install the following 3” 3-cell Geotextile Inner-ducts

From To Approx.

Distance (Feet)

Quantity NOTES

MH 510-19-9I B42432 50 3 In one of new 4” conduit

MH 510-27-6 B49401 225 3 In vacant 4” conduit

6.5.3 Fiber Optic Cable Installation.

The Contractor shall install SM, loose buffer tube, water blocked, outside plant (OSP) FOC suitable for underground applications. The intent is to install the cable in one continuous length, to the extent that it is practical. The cable shall meet RUS 7 CFR

1755.900 criteria; shall comply with industry standards with regard to manufacturers’ cable marking, jacket, rip cords, water blocking, fiber color coding, jacketing materials, etc. In addition, the FOC shall comply with industry standards with regard to mode field diameter, core cladding concentricity, attenuation, and dispersion characteristics at 1310 nm and 1550nm. All fiber optic cables shall be installed in new/existing geotextile innerduct or innerduct.

6.5.4 From B44702 to B42432

The Contractor shall install approximate 6,700 feet of 24-strand SM FOC (Maintenance loop included) from B44702 to B42432. Terminate 24-strand SM FOC in the new 24-port FODP in the B44702 and in the new 24-port FODP in B42432. Coordinate with 18 CS/SCXP for detail. Reference Project Drawing.

FROM TO

Approx.

Distance (Feet)

Notes

B44702 MH 8 20 In available Geotextile innerduct

MH 8 MH-510-19-14 165 In available Geotextile innerduct

MH-510-19-14 MH-510-19-13 215 In available Geotextile innerduct

MH-510-19-13 MH-510-19-12 485 In available Geotextile innerduct

MH-510-19-12 MH-510-19-11 480 In available Geotextile innerduct

MH-510-19-11 MH-510-19-10 480 In available Geotextile innerduct

Page | 16

MH-510-19-10 MH-510-19-9 430 In available Geotextile innerduct

MH-510-19-9 MH-510-19-9A 505 In available Geotextile innerduct

MH-510-19-9A MH-510-19-9B 400 In available Geotextile innerduct

MH-510-19-9B MH-510-19-9C 455 In available Geotextile innerduct

MH-510-19-9C MH-510-19-9D 360 In available Geotextile innerduct

MH-510-19-9D MH-510-19-9E 360 In available Geotextile innerduct

MH-510-19-9E MH-510-19-9F 485 In available Geotextile innerduct

MH-510-19-9F MH-510-19-9G 460 In available Geotextile innerduct

MH-510-19-9G MH-510-19-9H 480 In available Geotextile innerduct

MH-510-19-9H MH-510-19-9I 480 In available Geotextile innerduct

MH-510-19-9I B42432 50 In new Geotextile innerduct

6.5.5 From MH-510-27-27-6 to B49401

The Contractor shall install approximately 250 feet of 24-strand SM FOC (Maintenance loop included) from MH-510-27-27-6 to B49401. Coordinate with 18 CS/SCXP for detail. Reference Project Drawing.

6.5.6 SPLICING in MH-510-27-6

The Contractor shall splice 24-strand SM FOC (going to B49401) to existing 36-strand SM FOC. NOTE: The Contractor shall verify un-used 24-strand SM FOC at MH-510-27- 6-6. Coordinate with 18 CS/SCXP for detail. Reference Project Drawing

Page | 17

6.6 Backbone Drawings

Page | 18

Page | 19

Page | 20

7.0 Appendix C: Zone 1 Requirement

7.1 SCOPE.

This Statement of Objectives (SOO) defines the requirement for the Contractor to furnish 12-strand single mode (SM) fiber optic cable (FOC) to be delivered to the 18th Communications Squadron.

The contractor must also provide incidental services to install and test the FOC for the following buildings. From B46810 to Zone 1 (B46205, B46212, B46213, B46214, B46215, B46216, B46217, B46218, B46219, B46220, B46303, B46304, B46305, B47565 & B47566) in the 18th Munitions (MUNS) area at Kadena AB, Japan.

7.2 SPECIFIC REQUIREMENTS.

As indicated in this SOO and attached Project Drawing, the Contractor shall EFI&T 12-strand SM FOC from B46810 to Zone 1 (B46205, B46212, B46213, B46214, B46215, B46216, B46217, B46218, B46219, B46220, B46303, B46304, B46305, B47565 & B47566) in the 18th MUNS Area.

All associated fiber distribution panel (FODP), splicing and termination shall be included with the installation.

7.3 OUTSIDE PLANT REQUIREMENTS.

7.3.1 Existing Maintenance Holes.

Water from maintenance holes/handholes shall be drain onto grass when possible to act as a natural filter; then it may be pumped out onto the surrounding ground, as long as there is no impact to roads, driveways, or vehicle traffic. Mud and debris shall be disposed of IAW base requirements. If Contractor comes across a manhole with

7.3.2 Measurements.

7.3.3 Cable Footage Breakdown

1 12 9200

48 2000

72 500

96 1250

192 750

7.3.4 Underground Utilities Markings. N/A

7.3.5 Closures for Cable Splicing in Maintenance Holes.

Page | 21 quality re-enterable splice case. Only splice closures intended for underground applications shall be used in the underground system. The Contractor shall use standard re-enterable fiber splice closures. The closures shall have adequate strength to protect the splice and maintain cable shield electrical continuity in the below ground environment.

The Government quality inspector shall have the opportunity to inspect the inside of the splice case before closure pressure testing and encapsulation is performed. A coil of 25 feet of cable shall be provided on each cable entering and leaving a splice case in a MH or HH.

7.3.6 Splice Connectors.

All splicing shall be performed in accordance with Rural Utilities Service (RUS) Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable. The contractor shall use pic-a-bonds, 3M 710 splice connectors, or equivalent, for all copper splices.

7.3.7 Labeling.

7.3.8 New Ducts. N/A

7.3.9 Fiber Optic Distribution Panel (FODP) Marking.

in letters and numbers. The cover of all new FODPs shall be labeled to conform to the system used by local maintenance personnel to identify FODPs that terminate fiber. If the manufacturer has not identified the sequence in which ports on FODPs (pigtail modules) are counted, the Contractor shall provide designation labels/strips to identify the sequence in which they are counted. Each splice tray shall be marked to identify the fiber count contained in the splice tray. The marking shall identify the FODP by number

7.3.9.1 Example (FODP): FODP 44702 - 42432, 1-24

7.3.10 FOC Tags.

tags in all maintenance holes/hand-holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a maintenance-hole, put a tag on the cable, approximately 2 feet from each duct entrance. Information on the cable tag shall identify cable by size, type, cable number and count. Tagging and labeling of new cables shall be IAW the following:

7.3.10.1 Example (Fiber Optic Tag):

24L8.3F/ FO 44702 - 42432, 1-24// First line: “24” stands for Fiber Count. “L” stands for Loose Tube Buffer or (“T”) for Tight Tube Buffer. “8.3” stands for Single Mode. “F” stands for Filled Core (otherwise leave blank)// Second line and following: “FO” stands for Fiber Optic cable. “44702 - 42432” stands for From Building Number 44702 to 42432. “1-24” stands for Cable/Strand Count.

7.3.11 FOC Terminations.

Page | 22

7.4 FOC Maintenance Loop.

the first MH from the building, at each splice point MH location and at every third manhole. The maintenance loop shall be properly labeled and securely supported by two cable hooks. Cable hooks are to be positioned so the highest one supports the underside of the top of the coil and the bottom hook supports the underside of the bottom of the

7.4.1 New Maintenance Holes/Hand holes. N/A

7.4.2 Lockable Manhole Covers. N/A

7.4.3 Cable Racks and Cable Rack Supports.

includes new and existing MHs/HHs. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case. Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured

7.4.4 Underground Conduit System. N/A

7.4.5 Excavation/Building Penetrations

7.4.6 Requirement Installation.

geotextile multiple cell fabric inner-duct and fiber optic cable installation requirements.

The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure in according with TIA-758-B. Each cable installation shall be coordinated with the 18 CS/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion.

See Project Drawing below for reference and estimated distances of existing and proposed infrastructure and cables routes. This is only a proposed design. The Contractor

7.4.7 Infrastructure Installation.

7.4.8 New Network Cabinet. N/A

Page | 23

7.4.8.1 New 2” LB Type Building Entrance

The Contractor shall install one each 2” LB Type or equivalent for new conduit entrance on the exterior wall of each B46205, B46212, B46213, B46214, B46215, B46216, B46217, B46218, B46219, B46220, B46303, B46304, B46305, B47565 & B47566. The location of LB Type shall be provided by 18 CS/SCXP.

7.4.8.2 New Backboard

The Contractor shall install the new backboard in each B46205, B46212, B46213, B46214, B46215, B46216, B46217, B46218, B46219, B46220, B46303, B46304, B46305, B47565 & B47566. The location of new backboard will provide by 18

CS/SCXP.

Newly installed backboards (BB) shall be AF-standard in accordance with TIA- 569-C. The BB must be 0.75”-thick fire-retardant wood/plywood, with two coats of white, fire-resistant paint and the manufactures fire rated stamp must remain visible. The new BB must be as large as possible to accommodate wall mounted equipment. The contractor must verify/coordinate with 18 CS/SCXP before determining the size and location of the new BB

7.5 New Fiber Optic Distribution Panel (FODP).

The Contractor shall install the following FODPs. The location of FODPs shall be provided by 18 CS/SCXP. The FODPs shall be Corning Closet Connector Housing, or an equivalent model, that will provide sufficient capacity for the number of fiber strands being installed.

• 192-port FODP in B46810, in the existing Network Cabinet

• 12-port FODP in B46205, wall mounted on the new backboard

• 12-port FODP in B46212, wall mounted on the new backboard

• 12-port FODP in B46213, wall mounted on the new backboard

• 12-port FODP in B46214, wall mounted on the new backboard

• 12-port FODP in B46215, wall mounted on the new backboard

• 12-port FODP in B46216, wall mounted on the new backboard

• 12-port FODP in B46217, wall mounted on the new backboard

• 12-port FODP in B46218, wall mounted on the new backboard

• 12-port FODP in B46219, wall mounted on the new backboard

• 12-port FODP in B46220, wall mounted on the new backboard

• 12-port FODP in B46303, wall mounted on the new backboard

• 12-port FODP in B46304, wall mounted on the new backboard

• 12-port FODP in B46305, wall mounted on the new backboard

• 12-port FODP in B46205, wall mounted on the new backboard

• 12-port FODP in B47565, wall mounted on the new backboard

• 12-port FODP in B47566, wall mounted on the new backboard

7.5.1 Duct bank Infrastructure. N/A

7.5.2 Geotextile Innerduct (or Innerduct)

Page | 24

Distance

(Feet)

Quantity NOTES

HH-510-6A MH-510-6B 325 3 In vacant 4” conduit

MH-510-6B MH-510-6C 455 3 In vacant 4” conduit

MH-510-6C B46220 75 1 Overrides in the existing conduit

MH-510-6C MH-510-6D 400 3 In vacant 4” conduit

MH-510-6D B46219 75 1 Overrides in the existing conduit

MH-510-6D MH-510-6E 235 3 In vacant 4” conduit

MH-510-6E MH-517-6F 235 3 In vacant 4” conduit

MH-517-6F B46218 205 1 Overrides in the existing conduit

MH-517-6F MH-517-6G 175 3 In vacant 4” conduit

MH-517-6G B46217 95 1 Overrides in the existing conduit

MH-517-6F HH-517-4 465 3 In vacant 4” conduit

HH-517-4 B46205 195 1 In vacant 4” conduit

HH-517-4 HH-517-3 375 3 In vacant 4” conduit

HH-517-3 HH-517-2 85 3 In vacant 4” conduit

HH-517-2 HH-517-1 385 3 In vacant 4” conduit

HH-517-1 HH-517 405 3 In vacant 4” conduit

HH-515 B46305 155 1 Overrides in the existing conduit

MH-510-8 B46213 150 1 Overrides in the existing conduit

MH-510-8 MH-510-9 365 3 In vacant 4” conduit

MH-510-9 MH-510-10 365 3 In vacant 4” conduit

MH-510-9 B46303 225 1 Overrides in the existing conduit

MH-510-9 B46214 225 1 Overrides in the existing conduit

MH-510-10 B46215 365 1…