This statement of work describes a construction project to upgrade the parking lot and access road at the Bayview Trailhead in South Lake Tahoe, California. The project includes building an 88-space parking lot and access road, with option items for a sediment basin and pavement markings. Work will involve roadway excavation, aggregate base placement and asphalt paving. The estimated value is between $250,000 and $500,000, with an anticipated start date of May 16, 2023. The contractor must begin work within 10 days of the notice to proceed. Restrictions require maintaining public access to the trailhead and allowing permit holder use of the northern parking area. Construction will be restricted on federal holidays and allowed only during daylight hours Monday through Friday, with weekend or off-hours work requiring advance approval. This is a total small business set-aside being conducted by the Department of Agriculture Forest Service under solicitation 127EAW23R0015.

View the file

Other files

File Type Posted
127EAW23R0015 Amendment 1.pdf PDF
Terrain Photo (21).jpeg JPEG file
Terrain Photo (9).jpeg JPEG file
Terrain Photo (10).jpeg JPEG file
Terrain Photo (29).jpeg JPEG file
Terrain Photo (27).jpeg JPEG file
Terrain Photo (1).jpeg JPEG file
Terrain Photo (5).jpeg JPEG file
Terrain Photo (26).jpeg JPEG file
Terrain Photo (11).jpeg JPEG file
Terrain Photo (4).jpeg JPEG file
Terrain Photo (15).jpeg JPEG file
Terrain Photo (6).jpeg JPEG file
Terrain Photo (22).jpeg JPEG file
Terrain Photo (32).jpeg JPEG file
Terrain Photo (14).jpeg JPEG file
Terrain Photo (18).jpeg JPEG file
Terrain Photo (16).jpeg JPEG file
Terrain Photo (8).jpeg JPEG file
Terrain Photo (2).jpeg JPEG file
Terrain Photo (25).jpeg JPEG file
Terrain Photo (33).jpeg JPEG file
Terrain Photo (19).jpeg JPEG file
Terrain Photo (23).jpeg JPEG file
Terrain Photo (17).jpeg JPEG file
Terrain Photo (3).jpeg JPEG file
Terrain Photo (7).jpeg JPEG file
Terrain Photo (20).jpeg JPEG file
Terrain Photo (31).jpeg JPEG file
Terrain Photo (28).jpeg JPEG file
Terrain Photo (30).jpeg JPEG file
Terrain Photo (12).jpeg JPEG file
Terrain Photo (24).jpeg JPEG file
Terrain Photo (13).jpeg JPEG file
Attachment 2 Bayview Drawings.pdf PDF
Attachment 5 FP14.pdf PDF
Attachment 4 Fire Plan 2022.doc DOC document
Attachment 3 Wage Determination.pdf PDF
127EAW23R0015.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section C – Construction 12-05-01

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

Scope of Contract The Bayview Trailhead Parking Upgrades Project includes the construction of an 88-space parking lot and corresponding access road within the Bayview recreation area in South Lake Tahoe, CA. Option items include the construction of a sediment basin and painting of pavement markings. The work includes, but is not limited to roadway excavation, aggregate base placement, and asphalt placement.

Prior to the beginning of this project, the government will be responsible for tree and stump removal as well as clearing and grubbing and pavement removal within the limits of this contract. One lane of access to the northern portion of the site will remain open during construction and pedestrian access to National Forest Lands will be maintained. This project will require coordination with the Bayview Trailhead special use permit holder.

Project Location From the Lake Tahoe Basin Management Unit’s Supervisor’s Office: travel northeast on College Ave.

toward Al Tahoe Blvd. for 305 feet, turn left onto Al Tahoe Blvd. for 0.4 miles, turn left onto Lake Tahoe Blvd. for 2.0 miles, turn right onto CA-89 N / Emerald Bay Rd. for 7.6 miles, turn left onto Bayview Trailhead Road (38.94716° N, 120.099446° W)

NOTE: Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. In no event shall failure to inspect the site constitute grounds for a claim after contract award. (See Section L, 52.236-27, SITE VISIT.)

Price Range

Project Magnitude: $250,000 and $500,000.

Estimated Start Date May 16, 2023

Contractor must begin work within 10 days of the effective date of the Notice to Proceed.

Restrictions on Work

1. Bayview Trailhead will remain open to the public during construction. The contractor will be required to allow permit holder personnel and the public to access to the northern parking area, and trailhead during daylight hours. The area may be closed to public traffic while placing asphalt.

2. In accordance with the fire plan, if included in Section J.

3. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable damage.

4. See Section H for information on ground disturbance restrictions and the winterization plan.

5. Construction activities will be restricted on all federal holidays. The job site must be in a condition to allow for heavy public use during these periods. See section H for holiday periods.

6. Work will be allowed during daylight hours Monday-Friday.

7. Weekend activities and alternate work hours may be approved by the CO on a case by case basis. A request to work on weekends or alternate hours must be submitted 7 days prior to scheduling to provide adequate time for review.

Worker's Compensation Insurance

The Contractor shall provide evidence of Worker's Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.

Camping and Housing (see also Section H, Camping Permit Compliance)

Camping is not permitted in US Forest Service campgrounds. Contractor [ ] will [X] will not be permitted to camp elsewhere on US Forest Service land. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.

Maps

INCLUDED WITH DRAWINGS

Drawings and Specifications

Project Drawings: The following drawings are part of this solicitation:

Bayview Trailhead Parking Lot Upgrades Project (9 Sheets)

Specifications:

[ X ] Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-14 (US Customary Units) This document is incorporated by reference and is available on the web in in PDF format.

https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf

Special Project Specifications are physically incorporated within this solicitation.

The following Standard and Special Project Specifications are applicable to this contract:

Supplemental Standard Specifications for Construction of Roads and

Bridges on Federal Highway Projects, FP-14 (US Customary Units) Revision Date

101 Terms, Format, and Definitions 01-22-2020 102 Bid, Award, and Execution of Contract 11-09-2016 103 Scope of Work 11-09-2016 104 Control of Work 11-09-2016 105 Control of Material 06-29-2020 106 Acceptance of Work 07-18-2017 107 Legal Relations and Responsibility to the Public 07-18-2017 108 Prosecution and Progress 11-09-2016 109 Measurement and Payment 02-22-2019 155 Schedules for Construction Contracts 11-09-2016

The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.