Replacement of existing furnaces and water heaters
Solicitation number
140P1424R0002
Issued by

About this file

This scope of work document outlines the requirements for replacing heating, ventilation, and air conditioning systems at a national park housing duplex. The scope calls for removing existing furnaces and water heaters and installing new higher efficiency equipment, including split type heat pumps sized between 2.5 to 5 tons, compatible thermostats, ductwork, piping insulation, and controls to provide heating, cooling, and hot water for each apartment. The contractor must follow all applicable codes and standards, obtain necessary permits, and coordinate work with the national park authorities. Additional requirements specified include developing a project schedule and safety plan, submitting shop drawings and manuals, providing training, and warranting workmanship for two years. The solicitation number and opportunity for this scope of work is provided to replace systems at the Fossil Butte National Monument housing duplex.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOSSIL BUTTE NATIONAL MONUMENT

KEMMERER, WY

SCOPE OF WORK

REPLACE HOUSING WATER HEATERS, FURNACES, AND INSTALL HVAC SYSTEMS

FOBU

PMIS 321004

NATIONAL PARK SERVICE

INTERMOUNTAIN REGION

Table of Contents

1Project Overview4
1.1Location and Facilities4
1.2Project Description4
2Summary of Requirements and Objectives4
3Codes and Standards4
4Approved Equivalents5
5Product and Material Specifications5
5.1Split Type Heat Pump Systems (5 tons or less)5
5.2Thermostat / Controllers6
5.3Ductwork and Accessories6
5.4Common Piping for HVAC6
5.5Mechanical Systems Insulation7
5.6Water Heaters7
6Sequences of Operation7
7Shop Drawings8
8Pre-functional Testing8
9Start-up and Functional Testing8
10Operation and Maintenance Manual9
11Training9
12Additional Requirements9
12.1Project Schedule9
12.2Safety9
12.3Security10
12.4Quality Assurance10
12.5Travel10
12.6Progress Payments11
12.7Project Meetings11
12.8Substantial Completion and Final Inspection11
12.9Warranty Information12
13Site Coordination12
13.1Existing Conditions and Coordination12
13.2Special Construction Conditions12
13.3Staging Areas12
13.4Work Zones13
13.5Protection of the Public13
13.6Parking of Work Vehicles13
13.7Temporary Materials and Equipment Services13
13.8Hot Work Permit13
13.9Smoking14
13.10Electricity14
13.11Water14
13.12Sanitary Facilities14
13.13Hauling Restrictions14
13.14Waste Management14
14Submittals14
15Final Deliverables15

Project Overview Location and Facilities Fossil Butte National Monument (FOBU) is near Kemmerer, Wyoming, north of Interstate 80 on U.S. Highway 30. The monument is a day-use area; overnight accommodations are available in Kemmerer and Diamondville and camping is allowed on adjoining Bureau of Land Management (BLM) public lands. National monument facilities include the visitor center, two self-guided interpretive hiking trails, a picnic area, maintenance building, seasonal housing duplex, and a 7.5-mile scenic drive. Many visitors stop at the national monument enroute to Dinosaur National Monument, Yellowstone National Park, or Grand Teton National Park.

This project takes place in the FOBU housing duplex located at 1129 County Road 300 Kemmerer, WY 83101. The building where work will be performed is a duplex that will require two separate units operating off two separate water supply hookups and two separate electricity meters. Each unit will be supplying the needs of one apartment. Each apartment is two bedrooms, two bath, with kitchen, dining, and common room and is about 1000 ft². Park staff refer to each apartment geographically east and west. For this SOW, the work in each apartment is the same and these terms are only necessary for order of work.

Project Description This Scope of Work (SOW) is for the replacement of existing furnaces and water heaters as well as the install of Heating, Ventilation, and Air-conditioning (HVAC) systems at the FOBU housing duplex. Existing systems have exceeded their design life. This project replaces existing equipment with higher efficiency equipment.

The Contractor shall be responsible for all necessary work to achieve required project outcomes, including labor, equipment, tools, personal protective equipment (PPE), coordination with Authorities Having Jurisdiction (AHJ), internal construction permits, incidental design, travel, and other related expenses.

Summary of Requirements and Objectives Project requirements are described in this SOW. The Contractor shall site verify all existing conditions and submit shop drawings in accordance with this SOW prior to commencing work on site. The objective is for the contractor to provide and install new equipment that will provide sufficient heating, cooling, and hot water to each of the apartments in the duplex. All new equipment will be at a minimum Energy Star rated.

Codes and Standards The Contractor is responsible for securing all needed permits and for ensuring compliance with all federal, state, and local codes and design standards, latest editions, including the following. If discrepancies are found between the SOW and codes or standards as referenced in this SOW, the codes or standards shall govern, unless noted otherwise.

A. International Building Code (IBC, International Code Council) (Most current edition) B. International Mechanical Code (IMC, International Code Council) (Most current edition) C. International Plumbing Code (IPC, International Code Council) (Most current edition) D. National Electrical Code (NFPA 70) (Most current edition) E. National Fire Protection Association Codes (NFPA) F. American Society of Heating, Refrigerating, and Air-Conditioning Engineers Standards (ASHRAE) G. Air-Conditioning, Heating, & Refrigeration Institute Standards (AHRI) H. Sheet Metal & Air Conditioning Contractors’ National Association Standards (SMACNA) I. National Environmental Balancing Bureau Standards (NEBB) J. National Electrical Equipment and Medical Imaging Manufacturers (NEMA) K. Occupational Safety and Health Administration (OSHA)

Approved Equivalents A. Contractor proposed equivalents shall be submitted for review during the solicitation period as Requests for Information (RFI). Proposed equivalents shall not be reviewed after the solicitation period.

Product and Material Specifications

HVAC Systems (2.5-5 tons or ~40,000 BTU’s) A. General: HVAC systems comprising indoor air handling units, condensing gas furnace, evaporator coil and compatible outdoor single stage air conditioner.

B. Indoor Units

1. General: Remove, dispose of, and replace current Carrier model 59SC5A. New unit must fit inside current furnace closet space.

2. Use existing electric hookups. Contractor must install to code any new power supply necessary.

3. Use existing drain hookups.

4. Route all piping to exterior through floor or ceiling. No exposed piping will be seen inside rooms.

5. All holes in flooring, ceiling, and walls, will be sealed and rodent proofed.

6. New units will be large enough to each provide heating and cooling for a 1000 ft² apartment.

7. New unit must fit inside 30”x30” room with 80” ceiling.

8. New Unit positioning must allow for easy filter change.

9. Acceptable Manufacturers of furnace: Carrier Model 59TP6B, Lennox ML296V.

C. Outdoor Units

1. Placement of external units will be coordinated with COR in order to be free from snow and ice in inclement weather.

2. In the instance a concrete pad is needed for external units, Park Service will complete necessary Earthwork, forming, pouring, and finishing of concrete.

3. All piping and wiring will be insulated and rodent proofed.

4. Any holes going into duplex will be rodent proofed.

5. Acceptable Manufacturers: Carrier 24SCA4.

Thermostat / Controllers A. General: Thermostat/Controllers shall be fully compatible with all installed systems and shall be selected to achieve the sequences of operations described later in this SOW. Contractor shall provide all required components, sensors, accessories, wiring, interface modules, etc. as required for a fully operational system in accordance with this SOW. Provide one thermostat/controller for each installed system.

B. Key Characteristics: Fully programmable. Variable capacity heating and cooling functionality. Continuous fan operation functionality. Seven-day scheduler.

C. Accessories: Manufacturer outdoor air temperature sensor. Provide and install in accordance with manufacturer requirements.

D. Thermostat must be lockable and Wi-Fi ready so Park Staff may remotely monitor and control units.

E. Acceptable Manufacturers: Honeywell T6 Wi-Fi or Approved Equivalent

Ductwork and Accessories A. Contractor will utilize existing ductwork and exhaust piping to the greatest extent possible.

B. A hot work permit will be obtained from Park staff prior to any soldering, grinding, or work that requires open flame or sparks.

Common Piping for HVAC A. All piping materials shall be compatible for temperature, pressure and service.

B. Condensate drains: PVC Schedule 40, ASTM D 2665, NSF approved, type DWV. Fittings PVC, ASTM D 3311 Joints Screwed or solvent weld, ASTM D2564. Provide water seals in the condensate drain from all mechanical units. Connect drains to existing plumbing.

C. Refrigerant piping: Seamless copper tubing, hard drawn, Type K or L, conforming to ASTM B88. ASME B16.22 for solder-joint fittings. UL 109 for flared tube fittings. All field assembled line sets shall be installed in accordance with equipment manufacturer instructions.

D. Provide sleeves where piping passes through walls, floors, roofs, and partitions. Secure sleeves in proper position and location during construction. Provide sleeves of sufficient length to pass through entire thickness of walls, floors, roofs, and partitions. Provide not less than 0.25 inch space between exterior of piping or pipe insulation and interior of sleeve. Firmly pack space with insulation and caulk at both ends of the sleeve with plastic waterproof cement which will dry to a firm but pliable mass or provide a segmented elastomeric seal.

E. Pipe Hangers and Supports: Install hangers, supports, clamps and attachments as required to properly support piping from the building structure, not services.

Mechanical Systems Insulation A. Refrigerant pipework: Insulation shall be a flexible, closed-cell elastomeric pipe insulation, conforming to ASTM C534 Grade 1, Type I. Insulation materials shall be manufactured without the use of CFC’s, HFC’s or HCFC’s. Insulation materials shall have a flame-spread index of less than 25 and a smoke-developed index of less than 50 as tested in accordance with ASTM E 84.

Water Heaters A. Remove and dispose of existing water heaters.

B. Install new propane fired water heaters in place of removed units.

C. New water heater must fit inside 30”x31” room with 96” ceiling. Doorway into room is 80”.

D. Minimum capacity is 40 gallons.

E. Contractor will perform any alteration to gas lines necessary to accommodate new units.

F. Contractor will start up and verify no leaks exist and water heater is fully functional.

Sequences of Operation A. General: The Contractor shall provide all required components, accessories, wiring, interface modules, etc. as required for a fully operational system in accordance with this SOW.

B. AC-1, AC-2

1. Occupied Period

a. Ventilation Control

1) Fans shall operate automatically throughout the occupied period.

b. Space Temperature Control

1) Units shall operate under their own controls to meet indoor temperature set points, inclusive of compressor and electric coil staging.

2) Controls shall utilize multi-stage compressors and or electric coils to meet load.

2. Unoccupied Period

a. Ventilation Control

1) Fans shall operate only when there is a call for cooling or heating (unoccupied set points).

b. Space Temperature Control

1) Units shall operate under their own controls to meet indoor temperature set points (unoccupied set points).

2) Controls shall utilize multi-stage compressors (as applicable) and or electric coils to meet load.

Shop Drawings A. Submit the following shop drawings at a minimum:

1. Mechanical/Plumbing: Provide details of demolition, relocation, and new installation works for all ductwork, pipework, equipment, etc. Shop drawings shall clearly show all proposed works and fully demonstrate coordination with existing conditions and other trades. They shall also clearly identify connection points to existing services.

2. Electrical: Schematic details of all changes to existing electrical services and connection points between new work and existing.

B. It is acceptable to submit a single set of shop drawings that include all trades as noted above as long as these drawings clearly detail the required information. Shop drawing approval is at the discretion of the Government. The Government may request additional information be provided or revised submissions as necessary until satisfied, at no additional cost.

C. Shop drawings are not to be less than 8 1/2 by 11 inches nor more than 30 by 42 inches. Prepare drawings to accurate size, with scale indicated. Provide sufficient detail to show coordination of all new works with existing conditions.

D. Drawings are to be suitable for reproduction and be of a quality to produce clear, distinct lines and letters with dark lines on a white background.

E. Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown. Include the nameplate data, size and capacity on drawings. Also include applicable federal, military, industry and technical society publication references.

F. Submit drawings in PDF format.

Pre-functional Testing A. The Contractor shall provide pre-functional testing for designated mechanical equipment using manufacturer forms, checklists, or installation and operation manuals. Pre-functional testing shall be performed by the installing Contractor and shall demonstrate satisfactory installation in accordance with manufacturer’s requirements. Pre-functional testing shall be complete prior to functional testing.

Start-up and Functional Testing A. The Contractor shall conduct equipment start-up and functional testing in accordance manufacturer requirements. Submit record of start-up and functional testing.

Operation and Maintenance Manual A. Provide an Operation and Maintenance (O&M) Manual within fourteen (14) days after project completion. The O&M Manual shall include the following at a minimum:

1. All approved submittals.

2. Manufacturer maintenance instructions for all installed equipment.

3. Table of manufacturer, model, and serial number of all installed equipment.

Training A. The Contractor shall submit a proposed training agenda for park facility maintenance staff. This agenda shall include all relevant topics for the operation and maintenance of installed systems, including the following at a minimum:

1. Thermostat/controller operation.

2. Heating system operation.

3. Cooling system operation.

4. Water heater operation.

5. Manufacturer recommended maintenance for all installed systems.

6. Troubleshooting.

7. Safety.

B. The Contractor shall provide onsite training to park facility maintenance staff in accordance with the approved training agenda. The Contractor shall provide a record of training attendance. Training shall be provided by individuals thoroughly trained in the operation and maintenance of installed systems. The Contractor shall coordinate training schedule with the COR.

Additional Requirements Project Schedule A. The Contractor shall develop a detailed project schedule. This schedule shall include key milestones of the project, including start and finish dates, as well as proposed work times. The Contractor shall submit this schedule for review and approval prior to work proceeding. The Contractor shall actively maintain and update the schedule as required by the COR.

Safety A. The Contractor shall submit the following prior to work proceeding and maintain a copy onsite during the project:

1. Safety Data Sheets (SDS)

2. Project specific site safety plan. This plan shall include the following at a minimum:

a. Description of work.

b. Nomination of project management staff, including site safety representative.

c. Contact information for project management staff.

d. Contact and location information for local emergency services.

e. Description of anticipated high safety risk activities, including activity hazard analyses and safety control measures.

f. Site protection and traffic control measures, including sketches to illustrate provisions.

B. Contractor shall be responsible for complete and strict compliance with the park policies.

C. The Contractor shall fully comply with 29 CFR 1926.

D. The Contractor shall provide temporary safety barriers, as necessary, to provide a safe, hazard-free space for workers, pedestrians, and vehicles during construction.

E. The Contractor shall install protective measures to contain dust and debris during construction to assure a safe and irritant free work environment for building occupants. Return all areas to the original condition at the conclusion of work.

F. The Contractor shall remove and dispose of excess materials, debris, or waste at an approved off-site location in accordance with applicable Local, Tribal, State and Federal laws and regulations, and pay any related fees. Burning or burial of materials is not permitted.

Security A. The Contractor shall secure new equipment and materials. Limited storage space is available in the maintenance yard for Contractor. However, the location of trailers, storage, sheds and staging areas shall be approved by the COR.

B. The Contractor shall comply with all park security policies.

Quality Assurance A. The Contractor shall develop and maintain a quality program to ensure services are performed in accordance with commonly accepted commercial practices. The quality of all work shall be the responsibility of the Contractor. Inspect and test all work as needed to ensure that the quality of materials, workmanship, work, finish, and functional performance is in compliance with the SOW.

B. The Government shall periodically evaluate the Contractor’s performance in accordance with this SOW.

C. All new equipment shall conform to the manufacturer’s instructions and guidelines for installation and start-up.

D. Contractor shall warranty workmanship and labor for a minimum of two years.

Travel A. Contractor shall be responsible for all travel related expenses for this project, including mobilization of equipment, tools, materials, manpower, lodging, meals, and per diem.

Progress Payments A. Progress payments during work will be based on the percentage of work completed.

B. 25% Initial payment.

C. 50% When work completed.

D. 25% Upon approval of final inspection.

Project Meetings A. Pre-construction meeting: The CO will arrange an on-site pre-construction meeting with the Contractor. Notes of the meeting shall be recorded by the Contractor and will be distributed after the meeting. The meeting agenda shall include the following as a minimum:

1. Park rules and regulations.

2. Correspondence procedures.

3. Progress meetings.

4. Lines of authority.

5. Roles and responsibilities.

6. Submittal process.

7. Project schedule.

8. Progress payments.

9. Acceptance/rejection of the work.

10. Modifications.

11. Accident Prevention Plan and accident reporting.

12. Medical emergency processes, availability, emergency numbers, and contacts.

13. Park permits, burning work waste, rules of the road, alcohol use, housekeeping, firearms, pets, natural and cultural resource concerns.

14. Visitation, access, and public relations.

Substantial Completion and Final Inspection A. Submit written certification that project, or designated portion of project, is substantially complete, and request, in writing, a final inspection. Upon receipt of written request that project is substantially complete, the CO will proceed with inspection within 10 calendar days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.

B. When work is determined to be substantially complete, the COR will prepare a list of deficiencies ("Punch List") to be corrected before final acceptance. The CO will issue a Letter of Substantial Completion. If work is not determined to be substantially complete, the CO will notify the Contractor in writing. After completing work, the Contractor shall resubmit certification and request a new final inspection.

C. If, following final inspection, the work is determined to be substantially complete, CO will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 15 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the CO may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Work clause of the contract.

Warranty Information A. Contractor will warranty workmanship to be free of faults for a minimum of two years. Optional extended warranties will be considered.

B. Manufacturer’s warranty shall be for a minimum of ten years for all installed equipment. Optional extended warranties will be considered.

Site Coordination Existing Conditions and Coordination C. The Contractor shall fully inform themselves regarding any and all peculiarities and limitations of the spaces available for the installation of all work and materials furnished and installed under the contract. Coordinate with all other trades, as well as with existing conditions, in advance of the work, including requirements for openings, recesses and chases in the walls, partitions, framing or openings and routing of piping, conduit, etc. relative to each trade to alleviate conflicts.

Special Construction Conditions A. The project may be completed while the housing duplex remains occupied. Scheduling of work shall be in close cooperation with the Facility Manager. The building tenants shall have no unplanned functional disruptions resulting from the Contractor’s planning and execution of project work and requirements.

B. Work will be scheduled between 0800 and 1700 Monday – Saturday.

C. Contractor requests to work afterhours shall be approved by the Contracting Officer’s Representative (COR). Requests to work outside normal business hours shall be submitted in writing to the COR and Facility Manager not less than 48 hours in advance of the proposed after-hours work.

Staging Areas A. Work sites shall be limited to the smallest feasible area. Ground disturbances and site management shall be carefully controlled to prevent undue damage to vegetation, soils, and archeological resources and to minimize air, water, soil, and noise pollution.

B. Confine storage of work materials and equipment to immediate vicinity of project site, unless directed otherwise by the COR. All staging areas shall be returned to pre-work conditions once work is complete. Standards for this, and methods for determining when the standards are met, shall be developed in consultation with the COR. If used, all temporary water, sewer, sanitary facilities, electric and other utilities and utility connections shall be completely removed upon project completion.

Work Zones A. Do not disturb portions of project site beyond areas in which the work is indicated. Work zones may require work barrier fencing, chain link, plastic or portable fencing as directed by the COR. The fencing shall define the work zone and confine activity to the minimum area required for work. All protection measures shall be clearly stated in the work documents, and workers will be instructed to avoid conducting activities beyond the work zone as defined by the work zone fencing.

B. Confine limits of work to the smallest safe and efficient working areas. Prevent compaction of soils by equipment, and do not damage existing plantings or their root systems. All left over construction material shall be disposed of by Contractor.

C. Establishment of a construction camp shall not be permitted.

Protection of Public A. The Contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with MUTCD-2003 as applicable.

Parking of Work Vehicles A. Parking of vehicles shall be limited to existing parking lot, in designated areas close to the jobsite, and within approved staging area.

B. Ample space will be left available for emergency vehicles to access buildings in the event of an emergency.

Temporary Materials, Equipment and Services A. Temporary materials may be new or used but shall be adequate in capacity for the required usage, shall not create unsafe conditions, and shall not violate requirements of applicable codes and standards.

Hot Work Permit A. A Hot Work Permit is required for any welding, cutting, brazing, soldering or any work that generates sparks or excessive heat. Contractor shall provide at least a 24-hour advanced notice to obtain a Hot Work Permit. A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include providing and maintaining fire protection equipment and establishing and maintaining safe torch cutting and welding procedures.

Smoking A. Smoking at the work site is restricted to a designated smoking area. Due to drought conditions and the danger of wildland fire, smoking privileges may be revoked at any time if COR deems necessary to reduce the risk of wildfire.

Electricity A. FOBU will provide electric at location for construction. Only 120V supply is available at this location for standard outlets. Contractor is responsible for other electric needs.

Water A. Water is available from all taps in the duplex.

Sanitary Facilities A. Restrooms are available in the duplex if unoccupied. Restroom cleaning will be the responsibility of the contractor.

B. If both apartments are occupied, it is recommended that the contractor secure a portable unit to be placed in coordination with COR. Costs will be the responsibility of the contractor.

Hauling Restrictions A. Comply with all legal and local load restrictions in the hauling of materials.

Waste Management A. Contractor will remove all waste generated from the project and properly dispose of off-park.

Submittals A. Submit the items listed below for review and approval within 14 calendar days of contract award (unless otherwise noted). Government review comments will be returned within 7 calendar days after receipt of submittals.

1. Schedule of values

2. Project schedule

3. Safety data sheets

4. Safety plan

5. Shop drawings

6. Product data

a. Heat system product data

b. Electrical disconnects

c. Air filters

d. Thermostat / Controllers

e. Volume Control dampers

f. Door Grilles (including color options), if changing from existing.

g. Temperature sensors

h. Piping insulation

7. Pre-Functional testing forms/checklists

8. Functional test report

9. Training agenda (submit prior to training)

Final deliverables A. Contractor shall provide the following within seven (7) calendar days of project completion and prior to final inspection. Submit draft versions of these items electronically (PDF). Once reviewed and approved, provide deliverables in two (2) 3-ring binders with section dividers for each deliverable. Final deliverables shall include a thumb drive with all approved deliverables in electronic form (PDF). Contractor shall provide the following PRIOR TO FINAL PAYMENT.

1. Warranty Certificates – 2 hard copies and 1 digital (PDF)

2. Operation and Maintenance Manual - 2 hard copies and 1 digital

3. Record of training attendees image1.wmf