This is a pricing sheet for drydock repairs and maintenance of the USCGC SCIOTO (WLR-65B) during a FY2026 drydock availability. The schedule itemizes 67 line items covering hull inspections and preservation work, propulsion system overhauls, tank cleaning and inspections, structural repairs, cathodic protection renewal, deck preservation, and miscellaneous maintenance tasks. Items are divided between tender and barge components, with pricing presented on a job-order basis (typically one job per item). The sheet includes unit pricing columns, quantity fields, and extended price calculations, though all unit prices are listed at $0.00, indicating this is a template awaiting contractor pricing input.
The cost estimate breakdown section provides labor rate assumptions by geographic location, ranging from $45 per hour in New Orleans to $67 per hour in San Francisco, with a median rate of $55 per hour. The template includes fields for composite labor rates, G&A factor (assumed at 15%), profit factor (assumed at 10%), and detailed labor category breakdowns including engineers, technicians, machinists, electricians, shipfitters, welders, painters, and supervisory/QA personnel. Additionally, the sheet accommodates material and subcontractor costs across four cost categories, enabling comprehensive cost estimation for the complete drydock availability.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMEND 00001 CGC SCIOTO.doc | DOC document | |
| Attachment 3- Past Performance Information Form.doc | DOC document | |
| SCIOTO DDFY26 SOLIICITATION.pdf | ||
| Attachment 4- Request for Clarifications.docx | DOCX document | |
| ATTACHMENT 2 SCIOTO SPECIFICATIONS.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOS&S
| PRICING SCHEDULE FOR: |
| USCGC SCIOTO (WLR-65B) DRYDOCK AVAILABILITY FY2026 |
| ITEM | DESCRIPTION | UNIT PRICE | UNIT | QTY | EXTENDED PRICE |
| D-001 | Fire Prevention Requirements - Drydock | NSP | JOB | 1 | NSP |
| D-002 | Hull Plating, U/W Body, Inspect - Tender | $0.00 | JOB | 1 | $0.00 |
| D-003 | Hull Plating, U/W Body, Ultrasonic Testing - Tender | $0.00 | JOB | 1 | $0.00 |
| O-004 | U/W Body, Preserve, 100 percent - Tender | $0.00 | JOB | 1 | $0.00 |
| O-005 | U/W Body, Preserve, Partial, Condition A | $0.00 | JOB | 1 | $0.00 |
| O-006 | U/W Body, Preserve, Partial, Condition B - Tender | $0.00 | JOB | 1 | $0.00 |
| D-007 | Hull Plating Freeboard, Preserve, 100 Percent - Tender | $0.00 | JOB | 1 | $0.00 |
| O-008 | Hull and Structural Plating, General, 7.5 lbs., 3/16 in. Steel Plate, Renew | $0.00 | JOB | 1 | $0.00 |
| O-009 | Hull and Structural Plating, General, Degraded Weld, Steel, Repair | $0.00 | JOB | 1 | $0.00 |
| D-010 | Appendages, U/W, Leak Test - Tender | $0.00 | JOB | 1 | $0.00 |
| D-011 | Propulsion Shaft Rope Guards, Inspect | $0.00 | JOB | 1 | $0.00 |
| D-012 | Appendages, U/W, Internal, Preserve - Tender | $0.00 | JOB | 1 | $0.00 |
| D-013 | Voids, Non-Accessible, Leak Test | $0.00 | JOB | 1 | $0.00 |
| D-014 | Voids, Non-Accessible, Internal Surfaces, Preserve | $0.00 | JOB | 1 | $0.00 |
| D-015 | Tanks, MP Fuel Service, Clean and Inspect - Tender | $0.00 | JOB | 1 | $0.00 |
| D-016 | Tanks, Potable Water, Clean and Inspect - Tender | $0.00 | JOB | 1 | $0.00 |
| D-017 | Tanks, Dirty Oil and Waste, Clean and Inspect - Tender | $0.00 | JOB | 1 | $0.00 |
| D-018 | Propulsion Shaft Seals, Mechanical Overhaul and Inflatable Renew | $0.00 | JOB | 1 | $0.00 |
| D-019 | Propulsion Shafting, Remove, Inspect, and Reinstall | $0.00 | JOB | 1 | $0.00 |
| D-020 | Propulsion Shaft Bearings, External, Check Clearances | $0.00 | JOB | 1 | $0.00 |
| D-021 | Stern Tube Interior Surfaces, Preserve, 100 Percent | $0.00 | JOB | 1 | $0.00 |
| O-022 | Propeller, Perform Minor Repairs and Reconditioning | $0.00 | JOB | 1 | $0.00 |
| D-023 | Propellers, Remove, Inspect, and Reinstall | $0.00 | JOB | 1 | $0.00 |
| D-024 | Fathometer Transducer, General Maintenance | $0.00 | JOB | 1 | $0.00 |
| D-025 | Rudder Assembly, Remove, Inspect And Reinstall | $0.00 | JOB | 1 | $0.00 |
| D-026 | Rudders, Preserve, 100 Percent | $0.00 | JOB | 1 | $0.00 |
| D-027 | Rudder Stock Bearings Clearances, Check | $0.00 | JOB | 1 | $0.00 |
| D-028 | Spuds, Overhaul - Barge | $0.00 | JOB | 1 | $0.00 |
| D-029 | Spud Wells, Preserve - Barge | $0.00 | JOB | 1 | $0.00 |
| D-030 | Sewage Holding Tanks, Clean and Inspect - Tender | $0.00 | JOB | 1 | $0.00 |
| D-031 | Decks - Exterior, Preserve, Non-Skid Broadcast Grit System - Tender | $0.00 | JOB | 1 | $0.00 |
| D-032 | Cathodic Protection, Magnesium Anodes, Renew, - Tender | $0.00 | JOB | 1 | $0.00 |
| D-033 | Drydock - Tender | $0.00 | JOB | 1 | $0.00 |
| D-034 | Temporary Services, Provide | $0.00 | JOB | 1 | $0.00 |
| D-035 | Sea Trial Performance, Support, Provide | $0.00 | JOB | 1 | $0.00 |
| D-036 | Hull Plating, U/W Body, Inspect - Barge | $0.00 | JOB | 1 | $0.00 |
| D-037 | Hull Plating, U/W Body, Ultrasonic Testing - Barge | $0.00 | JOB | 1 | $0.00 |
| O-038 | Hull and Structural Plating, General, 7.5 lbs., 3/16 in. Steel Plate, Renew - Barge | $0.00 | JOB | 1 | $0.00 |
| D-039 | Appendages, U/W, Leak Test - Barge | $0.00 | JOB | 1 | $0.00 |
| D-040 | Hull Fittings, Weight Handling Rigging Hardware, Inspect and Test - Barge | $0.00 | JOB | 1 | $0.00 |
| D-041 | Decks – Exterior (Buoy or Construction Deck), Preserve 100% | $0.00 | JOB | 1 | $0.00 |
| D-042 | Drydock - Barge | $0.00 | JOB | 1 | $0.00 |
| D-043 | Deck Covering (Interior Wet/Dry), Renew | $0.00 | JOB | 1 | $0.00 |
| D-044 | Fire Pump, Renew - Barge | $0.00 | JOB | 1 | $0.00 |
| D-045 | Potable Water (PW) Check Valves, Reconfigure | $0.00 | JOB | 1 | $0.00 |
| D-046 | Hull Mod for SINS II Installation, Barge | $0.00 | JOB | 1 | $0.00 |
| D-047 | Sea Valves and Waster Pieces, Overhaul Or Renew | $0.00 | JOB | 1 | $0.00 |
| D-048 | Sea Strainers, Duplex, All Sizes, Overhaul | $0.00 | JOB | 1 | $0.00 |
| O-049 | U/W Body, Preserve, 100 percent – Barge | $0.00 | JOB | 1 | $0.00 |
| O-050 | U/W Body, Preserve, Partial, Condition A - Barge | $0.00 | JOB | 1 | $0.00 |
| O-051 | U/W Body, Preserve, Partial, Condition B - Barge | $0.00 | JOB | 1 | $0.00 |
| O-052 | Hull Plating Freeboard, Preserve, 100 Percent - Barge | $0.00 | JOB | 1 | $0.00 |
| D-053 | Sea Valves and Waster Pieces, Overhaul Or Renew - Barge | $0.00 | JOB | 1 | $0.00 |
| D-054 | Auxiliary Sea Water System Valves, Overhaul Or Renew | $0.00 | JOB | 1 | $0.00 |
| D-055 | Superstructure, Preserve, 100 Percent | $0.00 | JOB | 1 | $0.00 |
| D-056 | Exhaust Stacks, Exterior, Preserve | $0.00 | JOB | 1 | $0.00 |
| D-057 | Tanks, Potable Water, Clean and Inspect - Barge | $0.00 | JOB | 1 | $0.00 |
| D-058 | Boat Davit Winch, Shrink Wrap | $0.00 | JOB | 1 | $0.00 |
| D-059 | Buoy and Cargo Handling Crane, Shrink Wrap | $0.00 | JOB | 1 | $0.00 |
| O-060 | Lead-Based Paint, Perform Spot Abatement | $0.00 | SQFt | 1 | $0.00 |
| D-061 | Sewage Holding Tanks, Clean and Inspect - Barge | $0.00 | JOB | 1 | $0.00 |
| D-062 | Decks - Exterior, Preserve, Non-Skid Broadcast Grit System - Barge | $0.00 | JOB | 1 | $0.00 |
| D-063 | Keel Coolers, Clean, Inspect and Hydro - Barge | $0.00 | JOB | 1 | $0.00 |
| D-064 | Keel Coolers, Clean, Inspect and Hydro - Tender | $0.00 | JOB | 1 | $0.00 |
| D-065 | Spuds, Overhaul - Tender | $0.00 | JOB | 1 | $0.00 |
| D-066 | Spuds,Wells Preserve - Tender | $0.00 | JOB | 1 | $0.00 |
| D-067 | Cathodic Protection, Magnesium Anodes, Renew, - Barge | $0.00 | JOB | 1 | $0.00 |
| O-00A | Composite Labor Rate | Hour | 570 | 0 | |
| D-00B | GFP Report | NSP | EA | NSP | |
| O-00Z | Laydays | Day | 5 | ||
| Total Price of Definite Items | $0.00 | ||||
| Total Price of Option Items | $0.00 | ||||
| Total Price of Definite and Optional Items | $0.00 |
(9/26/2025)
Rev-0 - Page &P of &N
CostEstimateBreakdowns
| Composite Labor Rate | 55 | |||||||||||||||||||||||
| Assumed G&A Factor | 15% | |||||||||||||||||||||||
| Assumed Profit Factor | 10% | Direct Labor | Direct Material/Subs Cost | |||||||||||||||||||||
| ITEM | DESCRIPTION | UNIT PRICE | Sub-Contracted (put a "1" in the blank) | Total Labor Hours | Total Material & Subs (cost + G&A + profit) | Eng Tech | Machinest/Pipe Fitter | Electrician | Shipfitter | Welder | Firewatch | Insulator/Lagger | Painter | Gen Labor/Helper/Rigger | Supt/QA/NDT | Mat/Sub Cost 1 | Mat/Sub Cost 2 | Mat/Sub Cost 3 | Mat/Sub Cost 4 | Lab Rate | Area | WorkItemID | WIFileID | LoadData |
| 62 | Baltimore, MD | |||||||||||||||||||||||
| 52 | Biloxi, MS | |||||||||||||||||||||||
| 56 | Boston, MA | |||||||||||||||||||||||
| 50 | Charleston, SC | |||||||||||||||||||||||
| 60 | Corpus Christi, TX | |||||||||||||||||||||||
| 51 | Hampton Roads | |||||||||||||||||||||||
| 64 | Honolulu, HI | |||||||||||||||||||||||
| 55 | Houston, TX | |||||||||||||||||||||||
| 56 | Los Angeles, CA | |||||||||||||||||||||||
| 55 | Median Rate | |||||||||||||||||||||||
| 49 | Miami | |||||||||||||||||||||||
| 50 | Narragansett Bay, RI | |||||||||||||||||||||||
| 55 | New London, CN | |||||||||||||||||||||||
| 45 | New Orleans | |||||||||||||||||||||||
| 62 | NYNY | |||||||||||||||||||||||
| 49 | Panama City, FL | |||||||||||||||||||||||
| 60 | Philadelphia, PA | |||||||||||||||||||||||
| 51 | Portland, ME | |||||||||||||||||||||||
| 57 | Portland, OR | |||||||||||||||||||||||
| 55 | San Diego, CA | |||||||||||||||||||||||
| 67 | San Francisco, CA | |||||||||||||||||||||||
| 55 | Santa Barbara, CA | |||||||||||||||||||||||
| 55 | SE North Carolina | |||||||||||||||||||||||
| 65 | Seattle, WA | |||||||||||||||||||||||
| 48 | Tampa-St. Petersburg | |||||||||||||||||||||||
| 60 | Wilmington, DE |