This is a Schedule of Services (SOS&S) pricing schedule for dockside availability maintenance services on the USCGC STURGEON (WPB-87336) during fiscal year 2027. The pricing template establishes rates for definite and optional maintenance items, with primary focus on main diesel engine assembly work including W-5 maintenance procedures and control system configuration updates. The contractor must provide a composite labor rate (quoted in dollars per hour) and a material markup/handling fee (quoted as a percentage) that will apply throughout the contract lifecycle for all open and inspect repair activities.
The schedule specifies that 358 labor hours are allocated for the open and inspect repair labor rate evaluation, with a fixed price ceiling applicable to these repair services. The material markup/handling fee is presented as a percentage-based charge against material costs, with the extended price calculated by multiplying the quoted percentage against actual materials used. A five-day laydays provision is included for vessel scheduling purposes. Contractors responding to this RFQ (Solicitation Number 70Z08026QPBPL0044) must complete this pricing template by entering specific labor rates and material markup percentages in the designated fields, as these rates will serve as the foundation for cost evaluation and contract performance under the Coast Guard solicitation issued in accordance with FAR Class Deviation 25-21 for commercial items.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOS&S
| PRICING SCHEDULE FOR: | |||||
| USCGC STURGEON (WPB-87336) DOCKSIDE AVAILABILITY FY2027 | |||||
| ITEM | DESCRIPTION | UNIT PRICE | UNIT | QTY | EXTENDED PRICE |
| D-001 | Main Diesel Engine Assemblies, Perform W-5 Maintenance And Update Control System Configuration | JOB | 2 | $0.00 | |
| O-00A | Composite Labor Rate | Hour | 0 | ||
| D-00B | GFP Report | NSP | EA | NSP | |
| D-00C | Travel and Perdiem | JOB | |||
| O-00Z | Laydays | Day | 5 | ||
| Total Price of Definite Items | |||||
| Total Price of Option Items | |||||
| Total Price of Definite and Optional Items | |||||
| Open and Inspect Repairs | |||||
| The Labor Rates and Material Markup/Handling Fee will be used throughout the life of the contract for all open and inspect repair items. The total extended price for both CLINs below are being used solely for the purposes of evaluating price. | |||||
| OA/G-001 | **Provide breakdown, as follows: |
Labor Rate
| Unit Price: $________; Quantity:358; Unit of Issue: Hour; Extended Price: $____________ | Hour | 358 | $0.00 | |
| OA/G-002 | Material Markup/Handling Fee |
Unit Price: $15,360.00; Quantity: 1; Unit of Issue: Percent ________%;
| Extended Price: [$.00 X percentage quoted]: $______________ | $15,360.00 | Percent | $0.00 | |
| Total Fixed Price Ceiling of Open and Inspect Repairs | $0.00 |