The file is a Schedule of Services spreadsheet for a Defense Logistics Agency (DLA) Distribution fire department maintenance contract. The solicitation (SP330025Q0148) covers preventive and corrective maintenance services for four fire department vehicles, including semi-annual vehicle maintenance, annual ladder and hose certifications, and 24/7 towing support. The contract is structured with a base year and four option years, each valued at $22,500.00, for a total contract value of $112,500.00.

The maintenance services are divided into firm-fixed-price and time-and-materials components. Firm-fixed-price services include semi-annual preventive maintenance on vehicles and annual maintenance on ladders and fire hoses. Time-and-materials services encompass corrective maintenance, replacement parts reimbursement, and 24/7 towing support. The contract allows for reimbursement of actual replacement part costs without additional fees or handling charges. The contract is marked as CUI (Controlled Unclassified Information) and is restricted to federal distribution, with Brian Keckler listed as the point of contact.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ExecSmry

CUI
EXECUTIVE SUMMARY
DLA SUSQUEHANNA PA
FIRE DEPARTMENT (4) VEHICLES, HOSES AND LADDERS PM AND CM SERVICES + 24/7 TOWING
DISTRIBUTION - Grand Total$112,500.00
BASE YEAR$22,500.00
OPTION YEAR 1$22,500.00
OPTION YEAR 2$22,500.00
OPTION YEAR 3$22,500.00
OPTION YEAR 4$22,500.00
CUI
Controlled By: DLA Distribution J7-AF
CUI Category(s): PROCURE; SSEL
Distribution / Dissemination Controls: FED ONLY
POC: Brian Keckler brian.keckler@dla.mil

&"Times New Roman,Regular"SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104

BASE YEAR

DLA DISTRIBUTION
ITEMDESCRIPTIONQTYU/IUNIT PRICETOTAL PRICES
DDSP Fire Equipment (4) Vehicles + Ladders + Hoses2EA
Firm-Fixed-Price
0001Semi-Annual Preventive Maintenance (PM) on the (4) vehicles, or in accordance with the manufacturer's PM schedule
2JB$0.00
0002Annual Preventive Maintenance (PM) on the ladders
1JB$0.00
0003Annual Preventive Maintenance (PM) on the fire hose
1JB$0.00
Total Firm-Fixed-Price$0.00
Time & Materials5,000EA$1.00$5,000.00
0004Corrective Maintenance (CM).

Based on corrective maintenance service hours estimates.

See SOW.

Regular hours / hourly rate -
OT hours / hourly rate -
0005Replacement Parts for CM.
CM replacement parts estimate only. Contractor will be reimbursed for the actual cost of replacement parts ONLY with no additional fees or handling charges. See SOW.15
Replacement Parts costs.15,000EA$1.00$15,000.00
000624/7 Towing Support2,500JB$1.00$2,500.00
See SOW

Total Time & Materials $22,500.00

YEARLY TOTAL $22,500.00

&"Times New Roman,Regular"SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104

OY1

DLA DISTRIBUTION
ITEMDESCRIPTIONQTYU/IUNIT PRICETOTAL PRICES
DDSP Fire Equipment (4) Vehicles + Ladders + Hoses2EA
Firm-Fixed-Price
1001Semi-Annual Preventive Maintenance (PM) on the (4) vehicles, or in accordance with the manufacturer's PM schedule
2JB$0.00
1002Annual Preventive Maintenance (PM) on the ladders
1JB$0.00
1003Annual Preventive Maintenance (PM) on the fire hose
1JB$0.00
Total Firm-Fixed-Price$0.00
Time & Materials5,000EA$1.00$5,000.00
1004Corrective Maintenance (CM).

Based on corrective maintenance service hours estimates.

See SOW.

Regular hours / hourly rate -
OT hours / hourly rate -
1005Replacement Parts for CM.
CM replacement parts estimate only. Contractor will be reimbursed for the actual cost of replacement parts ONLY with no additional fees or handling charges. See SOW.15
Replacement Parts costs.15,000EA$1.00$15,000.00
100624/7 Towing Support2,500JB$1.00$2,500.00
See SOW

Total Time & Materials $22,500.00

YEARLY TOTAL $22,500.00

&"Times New Roman,Regular"SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104

OY2

DLA DISTRIBUTION
ITEMDESCRIPTIONQTYU/IUNIT PRICETOTAL PRICES
DDSP Fire Equipment (4) Vehicles + Ladders + Hoses2EA
Firm-Fixed-Price
2001Semi-Annual Preventive Maintenance (PM) on the (4) vehicles, or in accordance with the manufacturer's PM schedule
2JB$0.00
2002Annual Preventive Maintenance (PM) on the ladders
1JB$0.00
2003Annual Preventive Maintenance (PM) on the fire hose
1JB$0.00
Total Firm-Fixed-Price$0.00
Time & Materials5,000EA$1.00$5,000.00
2004Corrective Maintenance (CM).

Based on corrective maintenance service hours estimates.

See SOW.

Regular hours / hourly rate -
OT hours / hourly rate -
2005Replacement Parts for CM.
CM replacement parts estimate only. Contractor will be reimbursed for the actual cost of replacement parts ONLY with no additional fees or handling charges. See SOW.15
Replacement Parts costs.15,000EA$1.00$15,000.00
200624/7 Towing Support2,500JB$1.00$2,500.00
See SOW

Total Time & Materials $22,500.00

YEARLY TOTAL $22,500.00

&"Times New Roman,Regular"SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104

OY3

DLA DISTRIBUTION
ITEMDESCRIPTIONQTYU/IUNIT PRICETOTAL PRICES
DDSP Fire Equipment (4) Vehicles + Ladders + Hoses2EA
Firm-Fixed-Price
3001Semi-Annual Preventive Maintenance (PM) on the (4) vehicles, or in accordance with the manufacturer's PM schedule
2JB$0.00
3002Annual Preventive Maintenance (PM) on the ladders
1JB$0.00
3003Annual Preventive Maintenance (PM) on the fire hose
1JB$0.00
Total Firm-Fixed-Price$0.00
Time & Materials5,000EA$1.00$5,000.00
3004Corrective Maintenance (CM).

Based on corrective maintenance service hours estimates.

See SOW.

Regular hours / hourly rate -
OT hours / hourly rate -
3005Replacement Parts for CM.
CM replacement parts estimate only. Contractor will be reimbursed for the actual cost of replacement parts ONLY with no additional fees or handling charges. See SOW.15
Replacement Parts costs.15,000EA$1.00$15,000.00
300624/7 Towing Support2,500JB$1.00$2,500.00
See SOW

Total Time & Materials $22,500.00

YEARLY TOTAL $22,500.00

&"Times New Roman,Regular"SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104

OY4

DLA DISTRIBUTION
ITEMDESCRIPTIONQTYU/IUNIT PRICETOTAL PRICES
DDSP Fire Equipment (4) Vehicles + Ladders + Hoses2EA
Firm-Fixed-Price
4001Semi-Annual Preventive Maintenance (PM) on the (4) vehicles, or in accordance with the manufacturer's PM schedule
2JB$0.00
4002Annual Preventive Maintenance (PM) on the ladders
1JB$0.00
4003Annual Preventive Maintenance (PM) on the fire hose
1JB$0.00
Total Firm-Fixed-Price$0.00
Time & Materials5,000EA$1.00$5,000.00
4004Corrective Maintenance (CM).

Based on corrective maintenance service hours estimates.

See SOW.

Regular hours / hourly rate -
OT hours / hourly rate -
4005Replacement Parts for CM.
CM replacement parts estimate only. Contractor will be reimbursed for the actual cost of replacement parts ONLY with no additional fees or handling charges. See SOW.15
Replacement Parts costs.15,000EA$1.00$15,000.00
400624/7 Towing Support2,500JB$1.00$2,500.00
See SOW

Total Time & Materials $22,500.00