The file's text, extracted by GovTribe without its formatting.
MTNF Tree Planting SOI
| Attachment 1 - Schedule of Items - Mark Twain NF Planting IDIQ 2022-2027 | | | | |
| EACH OFFEROR SHALL IDENTIFY THEIR QUOTED UNIT PRICE AND TOTAL LINE ITEM PRICE FOR EACH FISCAL YEAR TO BE CONSIDERED FOR CONTRACT AWARD. BOTH WORK LINE ITEMS MUST BE INCLUDED IN THE QUOTE. QUOTES THAT DO NOT PROVIDE PRICING FOR BOTH LINE ITEMS FOR ALL FISCAL YEARS INDICATED WILL NOT BE CONSIDERED. | | | | |
| Task/Sub Task | Quantity | Unit | Unit Price | Total Line Item Price |
| Unit: Mark Twain NF | Forest-wide Fiscal Year 2022 (FY22) | | | |
| 1.1 Full Pine Tree Planting | 594 | Acres | $ | $ |
| 1.2 Supplemental Pine Planting | 133 | Acres | $ | $ |
| Total Acres | 727 | Acres | | |
| Total for First Year (FY22) | | | | $ |
| Unit: Mark Twain NF | Forest-wide Fiscal Year 2023 (FY23) | | | |
| 1.1 Full Pine Tree Planting | 1000 | Acres | $ | $ |
| 1.2 Supplemental Pine Planting | 300 | Acres | $ | $ |
| Total Acres | 1300 | Acres | | |
| Total for Second Year (FY23) | | | | $ |
| Unit: Mark Twain NF | Forest-wide Fiscal Year 2024 (FY24) | | | |
| 1.1 Full Pine Tree Planting | 750 | Acres | $ | $ |
| 1.2 Supplemental Pine Planting | 400 | Acres | $ | $ |
| Total Acres | 1150 | Acres | | |
| Total for Third Year (FY24) | | | | $ |
| Unit: Mark Twain NF | Forest-wide Fiscal Year 2025 (FY25) | | | |
| 1.1 Full Pine Tree Planting | 1000 | Acres | $ | $ |
| 1.2 Supplemental Pine Planting | 400 | Acres | $ | $ |
| Total Acres | 1400 | Acres | | |
| Total for Fourth Year (FY25) | | | | $ |
| Unit: Mark Twain NF | Forest-wide Fiscal Year 2026 (FY26) | | | |
| 1.1 Full Pine Tree Planting | 750 | Acres | $ | $ |
| 1.2 Supplemental Pine Planting | 200 | Acres | $ | $ |
| Total Acres | 950 | Acres | | |
| Total for Fifth Year (FY26) | | | | $ |
Grand Total (for all five years) $