This is a Salient Characteristics specification document for a mobile fire pump testing and training unit required by the Department of the Air Force. The system must be a purpose-built mobile platform capable of performing true pump tests from draft with suction lift in accordance with NFPA 1911 (2017 Edition), supporting pump testing up to 3,000 GPM and allowing training operations using recycled water.

The transporter must be constructed from heavy-duty aluminum with minimum 80-inch width, weigh ≤6,500 lbs, measure ≤27 feet in length, and feature two 7,000-lb rubber torsion axles with electric brakes, four 7,000-lb stabilizing jacks, one 12,000-lb tongue jack, LED lighting, DOT-approved reflective tape, 2-inch aluminum flooring, and adjustable 2-5/16" ball or pintle hitch. The water reservoir requires minimum 3,000-gallon capacity in heavy-duty poly with T-shaped design, integrated drafting pit with four anti-swirl plates, cavitation-control baffles, water-cooling system with two 2½-inch inlets and one 4-inch warm-water discharge, and front/rear ventilators. The drafting system includes two 6-inch drafting tubes with 360° aluminum swivels (PVC unacceptable), grease fittings, ¾-inch vacuum breakers, and 17-foot and 10-foot sections of 6-inch and 2½-inch clear hard suction hose. Flow measurement systems include two 4-inch aluminum inlet manifolds with 5-inch Storz male connections, two large pitot compartments with color-coded doors, and two NFPA-compliant pressure relief valves (120 PSI drip, 135 PSI full discharge). Test instrumentation comprises a portable master monitoring station with aluminum tripod mount, four glycerin-filled calibrated gauges (0–160 PSI pitot, 0–30" vacuum, 0–400 PSI pressure), and 30-foot and 10-foot high-pressure hoses. An integrated gas-powered fire hose tester with minimum 5.5-HP engine, stainless steel manifold, and 0–600 PSI gauges must be permanently mounted and preconnected. Included accessories include mounted spare tire, full-size protective cover, gauge test kit, high-pressure pump test kit, six 50-foot sections of 3-inch double-jacket hose, multiple NST adapters, handline nozzle tester (30–500 GPM range), and gauge calibration services. Contractor access requirements stipulate that personnel obtain base identification and vehicle passes, submit written requests listing employee names and dates, comply with Air Force security procedures and Emergency Mass Notification System requirements, and return all credentials upon contract completion, with failure to comply resulting in potential withholding of final payment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Salient Characteristics for a Mobile Fire Pump Testing & Training Unit

1. General Description

The unit shall be a mobile fire pump testing and training system capable of performing true pump tests from draft, creating a suction lift requiring the use of a primer in accordance with NFPA 1911 (2017 Edition). The system must support pump testing up to 3,000 GPM and allow training operations using recycled water.

The document states the system “performs a true pump test from draft creating a suction lift requiring the use of a primer as per NFPA 1911-2017 Edition” and is designed for “flowing clean clear water… up to 3000 GPM.”

2. Transporter Requirements

The mobile transporter shall meet the following minimum characteristics:

2.1 Construction & Dimensions

• Purpose-built, heavy-duty aluminum transporter engineered for low profile, proper weight distribution, and safe towing.

• Minimum 80-inch wide heavy-duty main frame with ½-inch extruded bed railing.

• Overall dimensions (empty):

o Weight: ≤ 6,500 lbs o Height: ≤ 87 inches o Width: ≤ 102 inches o Length: ≤ 27 feet

2.2 Axles & Support

• Two 7,000-lb rubber torsion axles with electric brakes; mounted to a steel tube subframe.

• Four 7,000-lb screw-type stabilizing jacks (two per side).

• One 12,000-lb tongue jack.

2.3 Storage & Access

• Two front aluminum storage compartments, each approx. 30" W × 29" D × 44" H, with three-point latching doors.

• Minimum 24-inch space between compartments and reservoir front for spare tire and cooling access.

2.4 Lighting & Safety

• LED stop, tail, turn, ICC, and work lights.

• Rear crossbar with elevated LED lighting.

• DOT-approved reflective tape on all sides.

2.5 Flooring & Fenders

• 2-inch extruded aluminum tongue-and-groove flooring (wood or steel not acceptable).

• Aluminum tread-plate fenders with integrated steps.

2.6 Hitch

• Adjustable 2-5/16" ball or pintle-type towing connection.

3. Water Reservoir Requirements

A minimum 3,000-gallon capacity reservoir meeting the following:

3.1 Construction

• Heavy-duty poly material for all internal and external surfaces.

• “T-shaped” design, securely mounted to prevent shifting while allowing flex with transporter.

3.2 Drafting Pit & Internal Flow Control

• Integrated drafting pit with four anti-swirl plates.

• Internal cavitation-control baffles made of ½-inch or thicker poly, welded to withstand high-volume flow.

• System designed to eliminate air disturbance and maintain proper draft depth.

The document notes the reservoir includes a section that “removes cavitations/disturbance and air from the water… preventing water disturbance and air swirls causing the apparatus to lose prime.”

3.3 Cooling & Ventilation

• Integrated water-cooling system with:

o Two 2½-inch inlets o One 4-inch warm-water discharge with gate valve

• Front and rear ventilators with hinged polypropylene doors and hold-open devices.

3.4 Additional Features

• UV-rated net cover for open reservoir area.

• Removable inspection plates at all four corners.

• Rub rails on all sides.

• Rear sump drain with 2½-inch gate valve.

• Two liquid sight gauges at rear drafting pit.

4. Drafting System

4.1 Drafting Tubes & Swivels

• Two 6-inch drafting tubes with heavy-duty 45° aluminum 360° swivels (PVC not acceptable).

• Each swivel equipped with grease fittings and ¾-inch vacuum breaker controlled at rear.

4.2 Hard Suction Hose

• Two 17-ft sections of 6-inch clear hard suction hose, preconnected.

• Two 10-ft sections of 6-inch clear hard suction hose.

• Two 10-ft sections of 2½-inch clear hard suction hose.

• Aluminum hose trays with hold-down straps.

• Full-length aluminum support rails around reservoir perimeter.

• Fold-out support bars (left and right) for weight distribution during testing.

5. Flow Measurement & Discharge System

5.1 Inlet Manifolds

• Two 4-inch aluminum manifolds, one per side, color-coded.

• Each equipped with:

o 5-inch Storz male connection o Three 45° 2½-inch swivels o Quarter-turn drain valves

5.2 Pitot Compartments

• Two large pitot compartments with hinged poly doors, splash guards, diffuser tips, and quick-disconnect fittings.

• Chrome grab handles.

• Color-coded left/right.

5.3 Pressure Relief

• Two NFPA-compliant pressure relief valves (drip at 120 PSI, full discharge at 135

PSI).

6. Monitoring & Test Instrumentation

6.1 Master Monitor Station

• Portable monitoring station approx. 20" W × 18" H × 6" D.

• Aluminum tripod mount.

• Gauges (all glycerin-filled, freeze/clog resistant, calibrated with certificates):

o Two 0–160 PSI pitot gauges o One 0–30" vacuum gauge o One 0–400 PSI pressure gauge

• Color-coded bezels and hose fittings.

• Two 30-ft high-pressure pitot hoses.

• Two 10-ft high-pressure hoses for UL test ports.

• Integrated flow and conversion charts.

7. Hose Storage & Miscellaneous Equipment

• Rear storage compartment approx. 35½" W × 33¼" H × 28" D, ventilated, with three-point latch.

• Capacity for six 50-ft sections of 3-inch hose plus tools.

8. Integrated Fire Hose Tester

• Gas-powered hose tester with minimum 5.5-HP engine.

• Capable of testing hoses up to 6-inch diameter.

• Stainless steel manifold with four independently controlled ¼-turn valves.

• Master gauge (0–600 PSI) and four individual 0–600 PSI gauges.

• Includes NST caps with bleeder valves and Storz adapters.

• Permanently mounted and preconnected to reservoir.

9. Included Accessories

The system shall include, at minimum:

• Mounted spare tire with UV-rated cover

• Full-size UV-rated protective cover for entire unit

• Gauge test kit (pitot, pressure, vacuum gauges with fittings)

• High-pressure pump test kit for high-pressure apparatus

• Six 50-ft sections of 3-inch double-jacket hose (600-PSI test)

• Multiple NST adapters (6"→5", 6"→4½", 6"→4", 5" Storz→2½")

• 30° 6-inch waterway elbow for strain relief

• Rubber mallet, T-handle wrench, spanner wrenches, hydrant wrench

10. Other Equipment

• Handline nozzle tester (30–500 GPM range)

• Gauge calibration services

Contractor Access to Department of the Air Force Installations

• The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

• The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate, and [ insert any additional requirements to comply with local security procedures ] to obtain a vehicle pass.

• During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.

• When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with [insert any additional requirements to comply with DAFI 31-101, Integrated Defense, and DODMAN5200.02_DAFMAN 16- 1405 , Air Force Personnel Security Program] citing the appropriate paragraphs as applicable.

• Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

• The contractor shall provide an after-hours contact number or after-hours email in the Emergency Mass Notification System (EMNS) for each of their personnel, whose normal place of duty is on a DoD installation or within a DoD facility. The contractor shall comply with any additional requirements in DAFMAN 10-206 for emergency operational reporting. Foreign Nationals may participate and may remove https://static.e-publishing.af.mil/production/1/af_a4/publication/dafi31-101/controlled_unclassified_information.pdf https://static.e-publishing.af.mil/production/1/saf_aa/publication/dodman5200.02_dafman16-1405/dodm5200.02_afman16-1405.pdf https://static.e-publishing.af.mil/production/1/saf_aa/publication/dodman5200.02_dafman16-1405/dodm5200.02_afman16-1405.pdf themselves from the Emergency Mass Notification System at any time. To update information, personnel can access the globe icon on their system desktop screens and choose the “Access Self-Service” option.

• Failure to comply with these requirements may result in withholding of final payment.