This Statement of Work (SOW) details vault toilet pumping services for the Rio Grande National Forest's Columbine Ranger District. The contract covers pumping services for sixteen vault toilets located in mountainous terrain, primarily CXT Inc. and Romtec concrete buildings, with some older wood or brick structures. Services are required before and during the operating season (May 15 through October 15), with potential for winter and emergency pumping. The Blanket Purchase Agreement (BPA) will be reviewed annually, with an estimated award period from 07/23/2025 through 7/31/2026, renewable up to 5 years.
Key technical requirements include using a pumper tank with 1,500-gallon capacity, vacuum pump, 3-inch intake valve, 200 feet of hose, and specific pumping procedures. The contractor must remove vault contents when they reach 80% capacity, dispose of waste at approved facilities, and follow strict cleaning and disinfection protocols. BPA calls are limited to $250,000 annually, with individual call orders not exceeding $50,000. Invoicing will be done through the Department of Treasury's Invoice Processing Platform (IPP), and all waste disposal must comply with federal, state, and local regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 Vault Toilet Schedule of Items.xlsx | XLSX spreadsheet | |
| Attachment 3 Toilet Locations.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rio Grande Vault Toilet Pumping
Description of Requirement (including a list of any attachments)
Project SJNF Columbine Ranger District Vault Toilet Pumping
General Information
1. Scope of Work
The Contractor shall provide all labor, supplies, supervision, tools, materials, equipment, and transportation necessary to provide pumping services for sixteen vault toilets in a manner that will maintain a satisfactory facility condition and present a clean, neat, and professional appearance. The requirement is for vault toilet pumping only and does not include cleaning the restroom other than assuring pumping area is clean. The vault restrooms are mostly CXT Inc. and Romtec concrete buildings, which are self-contained toilets that do not require water, sewer, or electricity. There are also several older models wood or brick buildings.
2. Background
The Rio Grande National Forest manages many recreation sites that provide toilet facilities for the public.
Terrain features are mountainous, travel over passes on state highways and graveled forest service roads is required.
3. Description of Agreement
Multiple Blanket Purchase Agreements (BPA) may be established to provide for Vault Toilet Pumping at USDA Forest Service managed recreation sites located across Columbine Ranger District as identified in the Schedule of Items.
The BPA will be reviewed annually.
These services are normally required before and during the operating season, which normally runs from May 15 through October 15 annually. Some locations also require services at the end of each season.
Additionally, some toilets may require winter pumping. Emergency services will be performed on a call as needed basis. Occasional emergency pumping may be required outside the normal workday constraint.
Response time for any emergency will be by mutual agreement between the Government and Contractor.
The number of sites and frequency of service may be increased or decreased throughout the life of the BPA and are subject to the changes clause.
Vault capacity is identified in the schedule of items above. Vaults need to be pumped when they reach 80% Capacity, with 90% of the vault contents removed per standard commercial practices. All vault waste shall be disposed of at a commercial treatment facility off National Forest Lands. Applicable OSHA, State and Local laws and regulations will be followed. It shall be the responsibility of the Contractor to secure permission from local municipal plants to add such waste to their system with any cost to be at the Contractor’s expense.
4. Extent of Obligation
The Government is only obligated to the extent of authorized calls actually placed against this BPA by authorized personnel, against authorized items.
5. Purchase Limitations
BPA Calls should not exceed $250,000 annually.
The limitation for each individual call order under this BPA shall not exceed $50,000.
6. Individuals Authorized to Order Under this BPA
- Any Intermountain FPO Contracting Officer/Contracting Specialist/Purchasing Agent
*Government micro purchase card may be used for emergency orders not to exceed $2,500.
7. Delivery tickets
All Order under this agreement shall be accompanied by an itemized invoice and shall contain the following information:
(i) Vendor Name.
(ii) Contact information email and phone number
(iii) BPA number and BPA Call Order number
(iv) Date of service.
(v) Itemized list of services corresponding to the Schedule.
(vi) Quantity, unit price and extension of each item
Additional dump fee tickets shall be submitted with invoice. Tickets must show the location(s) from which the sewage was pumped.
8. Invoices
An individual invoice will be required for each delivery or as specified and allowed by each call. The “Submit Invoice-to” address for all orders is the Department of Treasury’s Invoice Processing Platform (IPP). The Contractor shall register and submit all invoices via IPP unless otherwise noted in an individual call. This platform is managed by the U.S. Department of Treasury and additional information is available at this website: https://www.ipp.gov/index.htm.\
Vendors register at: https://www.ipp.gov/vendors/enrollment-vendors.htm to establish an account.
9. Placement of Calls
Agency personnel authorized to place calls against this BPA MUST furnish a list of calls placed to the COR and Contracting Officer monthly.
10. Completion Date of Calls
The completion date for calls shall be established when each call is placed.
11. Payment and Acceptance
Payments will be made through (Electronic Funds Transfer (EFT) via IPP (see Paragraph 8 above) unless otherwise noted on a specific call.
12. Cancellation of BPA
The United States Government reserves the unilateral right to cancel this BPA by providing written notification to the Contractor. The Contractor may withdraw from this BPA upon written request to the Contracting Officer. Withdrawal from the BPA does not affect awarded calls.
13. Points of Contact and Mailing Address
Rebecca Schowalter US Forest Service 325 25th Street Ogden, UT 84401
14. Period of Performance
Date of Award estimated 07/232025 through 7/31/2026, and may be renewed annually not to exceed 5 years.
The agreement shall be reviewed annually and updated as necessary 30 calendar days before expiration of date to conform to the requirements of the Federal Acquisition Regulation.
15. Modifying the BPA
This Blanket Purchase Agreement shall be changed only by modifying the agreement itself and not by individual orders issued under it. Only the Contracting Officer, or their designated successor, may modify this BPA.
16.Technical Specifications
Contractor Equipment shall meet or exceed these minimum requirements:
1.Pumper tank capacity of 1500 gallons.
2.Vacuum pump.
3. 3-inch diameter intake valve and 200 feet of hose.
4. Long handled grappling device.
5. Capability of carrying extra water for cleaning purposes and for re-charging.
6. Back-up warning devices.
Pumping Procedures when an outside Manhole is Available
As long as the outside pump-out access is in excess of 20 inches in diameter (or 20 inches square) the Contractor shall not be allowed to remove the vault contents through the toilet riser.
After removing the manhole cover, use the clam rakes or long handles grabber to remove as much of the debris as possible before trying to pump out the waste. This procedure will help stir up the contents of the vault and breakup the dense concentration of waste typically located just under the toilet riser (the impact zone).
By removing most or all of the debris before pumping, the Contractor will find that the hose will not clog so often, and the liquid portion of the contents will not be removed before the thicker solids are removed.
All Debris Removed From The Vault Shall Be Placed Into A Leak Proof Container So That No Contamination To The Surrounding Ground Will Result.
If the bottom of the vault is flat, then the waste shall be removed down to within 4-5 inches of the bottom.
At this point the hose will begin to suck air (vortexing) and further removal will be slow. At this time remove any further debris that was not removed during the initial raking and removal. Using a high-pressure jet washer system, wash down the interior walls of the vault before the clinging debris has a chance to dry. If at this time there is a heavy concentration of solids on the bottom of the vault, use the high-pressure jet washer system to break up and dilute the solids and then pump this diluted waste, down again until the suction hose begins to suck too much air to make further pumping practical. The flat bottomed vault shall now be pre-charged with enough clean, fresh water to bring the depth of water up to 10 inches.
If the bottom of the vault is sloped (all vaults should be sloped a minimum of 1 inch per ft.), then pump the waste down (at the deep end) to where the hose begins to suck air. Remove any remaining debris and then go inside the building with the high-pressure jet washer system and wash the remaining waste down the sloped bottom. Wash down the vault walls from inside the building or from the outside manhole, whichever is easier. Now pump out the remaining waste and the water that was just added by the high-pressure jet washer until the suction hose begins to suck too much air to make further pumping impractical.
Pre-charge the vault with clean, fresh water so that there is 10 inches of water covering the bottom under the toilet riser. Add the recommended amount of Citrus deodorizer (or equivalent) to deodorize the remaining vault contents.
Thoroughly clean and disinfect all contaminated areas resulting from the pumping process. Either sweep or wash all waste that is deposited on the concrete surrounding the manhole cover, back into the vault if possible. The waste that runs off the edge of the concrete, onto the dirt or into the gravel edge, will be an attractant for flies, a potential health risk and an odor problem. This problem should be avoided. Clean thoroughly around the manhole cover gasket area and replace the cover. The manhole cover MUST fit with an airtight seal so that the venting process of the vault toilet is not interfered with. If there is not an airtight seal, the Contractor shall notify the COR and District Representative.
Pumping Through the Toilet Riser When There Is No outside Manhole
The Contractor shall remove the toilet riser prior to pumping or removing debris. The Contractor shall not remove debris through or pump through the toilet riser without removing the riser. Remove the debris and pump in accordance with 4-1.
Extra care shall be taken to prevent waste spillage onto the interior floor and wall surface while removing debris and while pumping. The toilet paper dispenser and toilet riser shall be protected from damage and the toilet paper shall be covered with a waterproof material prior to removing debris or pumping, in order to prevent the paper from getting contaminated.
During the final cleanup, the interior floor surface and any wall surface that was contaminated by waste shall be thoroughly disinfected. Again, every effort shall be made to sweep or wash the spilled waste back into the vault. The Contractor shall not allow the spilled waste to be washed or swept out through the front door because the waste will collect at the edge of the concrete and the dirt (or gravel) will become an attractant for flies, a possible health risk for barefoot persons and an odor problem. Thoroughly wash and disinfect both the inside and outside of the toilet riser and the seat and cover before replacing the riser. The toilet riser and seat shall be dry before the Contractor leaves the work site. Remove the waterproof covering that was protecting the toilet paper and make sure the paper did not get contaminated. If the paper did get contaminated, The Contractor shall notify the COR or District Representative. The door handles or knobs shall also be disinfected and dry before the Contractor leaves the job site.
Each unit shall be available for immediate use after the pumping and final cleanup. The Contractor shall not leave any toilet location until final cleanup is accomplished.
Offsite Disposal of Sewage and Debris
The Contractor shall be properly licensed and shall be responsible for making disposal arrangements, including disposal of all effluent, debris, and trash, and payment of all fees.
Disposal shall conform to all Federal, State and Local laws and ordinances. COR shall approve all disposal sites before pumping begins.
The Contractor shall be responsible to prevent spillage and to haul all waste material (sewage and debris) in watertight containers. Handling of all waste material shall be in accordance with all applicable health regulations.
“The Contractor shall dispose of all effluent in a State approved water disposal facility and shall furnish certifications of written evidence that only such approved facilities are used. Dumping at sanitary landfills shall not be permitted. No septic or vault waste shall be dumped on agricultural lands or private properties. Dumping shall only occur in Forest Service lagoons with written approval.”
Conduct of Personnel
The Contractor and his/her employees shall make every reasonable effort to prevent interference with the normal use and occupancy of recreation areas while engaged in the performance of the agreement. Due to the nature of the duties under the agreement, the Contractor and his/her employees shall keep themselves and equipment presentable at all times. The Contracting Officer may, in writing, require the Contractor to remove from the work site any employee the Contracting Officer deems incompetent, careless, discourteous to the public or is otherwise objectionable, or for theft, possession and/or removal of materials, supplies, equipment or any Government-owned property.
Resource Damage
Any damage or defacement that occurs to government property or land resources during the Contractor’s operations shall be repaired at the Contractor’s expense to its original condition. Onsite Inspection will be made by the COR or District Representative prior to acceptance of work.