Attachment 1 Requirement Description IDS and AFNET Fiber Cable.pdf
PDF 6 MB Posted
- Solicitation number
- W50SLF24Q11AY
- Issued by
-
Department of the Army National Guard
About this file
This document is a Statement of Objectives (SOO) that describes the requirements for installing an Intrusion Detection System (IDS) and fiber lines for an AFNET circuit at two locations in Hawaii for the Hawaii Air National Guard.
The key requirements include:
- Installing an IDS and fiber lines at the 150th EWS at PMRF Barking Sands, Kekaha, Kauai, Hawaii. This includes installing fiber conduit, fiber optic cable, smart sensors, access control hardware/software, cameras, and connecting to the base security infrastructure.
- Installing fiber lines for an AFNET circuit at the 150th EWS, including running fiber optic cable, installing networking equipment and patch panels, and replacing existing CAT5e cabling with CAT6e.
- Installing an IDS at the ARMAG Temporary Facility, 109th EWS, JBPHH (Hickam), Honolulu, Hawaii, with similar requirements as the 150th EWS IDS.
The related federal contract opportunity is solicitation number W50SLF24Q11AY, with quotes due by 10:00 a.m. Hawaii Standard Time on September 27, 2024. The contract will be awarded by the Department of the Army National Guard.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUIREMENT DESCRIPTION
1. Install an Area Intrusion Detection
System (IDS) at 150th EWS, PMRF Barking Sands, Kekaha, Kauai, Hawaii
2. Install Fiber Lines for AFNET Circuit at 150th EWS, PMRF Barking Sands, Kekaha, Kauai, Hawaii
3. Install an Area Intrusion Detection System (IDS) at 109th EWS, JBPHH (Hickam), Honolulu, Hawaii
Scope of Work The Contractor shall provide all labor, materials, and equipment necessary to install, terminate, test and provide technical support that includes programing equipment/keypads for the newly installed system to be accredited. Design must be approved by the Contracting Officer prior to installation.
Work requirement and location are as follows:
1. Install an Area Intrusion Detection System (IDS) at 150th EWS, PMRF Barking Sands, Kekaha, Kauai, Hawaii
2. Install Fiber Lines for AFNET Circuit at 150th EWS, PMRF Barking Sands, Kekaha, Kauai, Hawaii
3. Install an Area Intrusion Detection System (IDS) at 109th EWS, JBPHH (Hickam), Honolulu, Hawaii
Deliverables The Contractor shall provide the following deliverables:
1. A design for final approval.
2. Test results of the installed premise wiring.
3. As-built drawings of the installed premise wiring.
Performance Standards The installed premise wiring shall meet the following performance standards:
1. The single mode fiber optic cable shall be installed in accordance with NECA/FOA 301, Standard for Installing and Testing Fiber Optics .
2. The RJ45 wall jacks and patch panels shall be installed in accordance with industry standards .
3. The installed premise wiring shall be tested and certified to meet or exceed industry standards .
4. The Cat6e Ethernet cable shall be installed in accordance with ANSI/TIA-568 standards.
5. Local Building codes
Acceptance Criteria The installed premise wiring shall be accepted by the Government when it meets the following criteria:
1. The installed premise wiring meets the performance standards specified in this Statement of Objectives.
2. The Contractor provides as-built drawings, test results, and a design for final approval of the installed premise wiring.
References : NECA/FOA 301, Standard for Installing and Testing Fiber Optics. : Industry standards for RJ45 wall jacks and patch panels. : ANSI/TIA-568 standards for Cat6e Ethernet cable.
1. Install an Area Intrusion Detection System (IDS) at 150th EWS, PMRF Barking Sands, Kekaha, Kauai, Hawaii
The Contractor shall design, plan, procure, install, and provide technical support and training for:
• Install fiber conduit where needed to provide, electrical and fiber communication lines to the external PL3 area Security monitoring system.
• Run fiber optics cable to all sensor locations and connect to the base (U.S.
Navy/ Lenel System) regional security monitoring infrastructure.
• Install smart sensor suite that provides 100% uninterrupted compound intrusion detection system of the perimeter fence with coverage extending a minimum 30 feet from the compound physical fence (see slide 5).
• Install Building 1116 Birdcage area doors; access and control hardware and software
• Install a smart sensor suite that provides uninterrupted intrusion detection of 100% of the compound physical perimeter fence.
• Connect and accredit the installed intrusion detection to the US NAVY secure facility intrusion detection infrastructure. Contractor must program, coordinate and connect to the base security infrastructure.
• Provide technical support for the 150 EWS security personnel for PL3 restricted area accreditation.
• Provided intrusion detection system user training to 150 EWS security personnel and key personnel.
• Install pan tilt zoom cameras able to provide 360 degree view of area indicated on slide 6. Cameras will be connected to CCTV in room 132.
See Drawing No. 1.
Under ground Fiber On existing Comm conduit (Aprox 400FT of fiber)
Exterior perimeter May required 10 cameras depending on coverage
Interior perimeter may require 7 cameras
Drawing No. 1 PMRF 150EWS Compound
Drawing No. 2 PMRF 150EWS Compound
Drawing No. 3 PMRF 150EWS Compound
2. Install Fiber Lines for AFNET Circuit at 150th EWS, PMRF Barking Sands, Kekaha, Kauai, Hawaii
1: Location: B1116 RM 131 Electrical room RM 127 Security Room (Circuit DEMARC)
A. Run/install/terminate 24 strands SM Plenum rated fiber optic cable from RM 131 to RM 127
a. Utilize existing rack space within the electrical room.
2: Location: B1116 RM 127 Security room will tie in incoming AFNET circuit and host (1) Cisco Network Switch and (1) Cisco Network router that will serve as the DN
A. Install a wall mountable 24U lockable standard-depth network rack enclosure within RM 127 Security room
B. Run/install/terminate (Qty 1) 24 strand plenum rated SM fiber optic cable (LC) from RM 127 to RM 131 Electrical room
C. Run/Install/Terminate (Qty 3) 12 strands plenum rated SM fiber optic cables (LC) to RSS D. Run/Install/terminate (Qty 1) 24 strand plenum rated SM fiber optic cable (LC) to RM 112 E. Run/Install/terminate a 48 port ethernet patch panel
i. Remove old CAT5e Cable and replace with new CAT6e cables.
1. Terminate CAT6e cable in RM127
2. Install NEW CAT6e into customer defined areas.
3: Location: B1116 RM 112 Will (1) Cisco switches; (1) 24 strand SM fiber LC patch panels; (2) 48 Port Ethernet cable patch panel (Services rooms 105 106 107 108 109 110 111, 113, 114, 115, 116, 117, 118, 119)
A. Install a 24U lockable standard-depth network rack enclosure within RM 112 B. Install outdoor/indoor plenum rated (qty 1) 24 strand single mode fiber optic cable with LC patch panel within the 24U lockable cabinet within RM112
i. (Qty 1) 24 strand SM fiber optic cable will run to Electrical room 127 (Security
Room) C. Install 96 port RJ45 Cat6e patch panel within the rm 112 D. Run new Cat 6 Plenum rated cabling to (Rooms 105 106 107 108 109 110, 111, 113, 114, 115, 116, 117, 118, 119)
i. Remove old CAT5e Cable and replace with new CAT6e cables.
1. Terminate CAT6e cable in RM112
2. Install NEW CAT6 into customer defined areas.
See Drawing No. 2.
ROOM 110
ROOM 103
ROOM 101
ROOM 102
ROOM 104
ROOM 105
ROOM 106
ROOM 107
ROOM 108
ROOM 113
ROOM 114
ROOM 115
ROOM
ROOM 121
ROOM 120 ROOM 122
ROOM 123
ROOM 117
ROOM
112 ROOM 109
ROOM 111
ROOM 118
ROOM 119
ROOM 124 ROOM 125
ROOM 126
ROOM 127
ROOM 135
ROOM 133
ROOM 132
ROOM 131
ROOM
ROOM
ROOM
ROOM 134
Drawing No. 2
2. Install Fiber Lines for AFNET Circuit at 150th EWS, PMRF Barking Sands, Kekaha, Kauai, Hawaii
3. Install an Intrusion Detection System (IDS) at the ARMAG Temporary Facility, 109th EWS, JBPHH (Hickam), Honolulu, Hawaii
The Contractor shall design, plan, procure, install, and provide technical support and training for:
• Install fiber conduit where needed to provide, electrical and fiber communication lines to the external ARMAG Security monitoring system.
• Run fiber optics cable to all sensor locations and connect to the base (U.S.
Navy/ Lenel System) regional security monitoring infrastructure.
• Install smart sensor suite that provides 100% uninterrupted compound intrusion detection system.
• Install a smart sensor suite that provides uninterrupted intrusion detection of 100% of the compound physical perimeter fence.
• Connect and accredit the installed intrusion detection to the US NAVY secure facility intrusion detection infrastructure. Contractor must program, coordinate and connect to the base security infrastructure.
• Provide technical support for the 150 EWS security personnel for ARMAG restricted area accreditation.
• Provided intrusion detection system user training to 109 EWS security personnel and key personnel.
See Drawing No. 3.
Resource Mapping Hawaii
Legend Entry Control Point
Existing Entry Control Point
Existing Fence
Restricted Area Boxes
Gate Existing Restricted Area Boxes
Restricted Area Line Restricted Area Signs
Existing Restricted Area Line
Ü
0 20 4010 60 Feet
Scale: 1:200
Camera on fence line
Camera on Building 3400
Camera in ARMAG vestibule
Drawing No. 3 ARMAG near Bldg 3400, JBPHH (Hickam)
| Scope of Work |
| Deliverables |
| Performance Standards |
| Acceptance Criteria |
| References |
| Drawing No. 1 PMRF 150EWS Compound.pdf |
| Slide 1 |
| Drawing No. 2 PMRF 150EWS Bldg 1116.pdf |
| Slide Number 1 |
| Drawing No. 3 109EWS JBPHH.pdf |
| Slide 1 |
File details come from the government source that posted it. Updated .