This document contains a Quality Assurance Surveillance Plan (QASP) for neurophysiology services and related requirements for the Department of Veterans Affairs Nebraska-Western Iowa Health Care System. The contractor must maintain licenses, certifications, and education for clinical staff. Key performance standards include maintaining on-call coverage without lapses, completing mandatory training, and properly onboarding and replacing key personnel. Performance will be evaluated on quality of care, privacy and regulatory compliance, and accurate invoicing by the 10th of each month. Contractors must acknowledge and agree to the QASP terms.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1: Quality Assurance Surveillance Plan (QASP)
The contractor will be evaluated in accordance with the following:
1. PURPOSE
This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:
• What will be monitored?
• How monitoring will take place.
• Who will conduct the monitoring?
• How monitoring efforts and results will be documented.
This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance.
This QASP is a “living document” and the Government may review and revise it on a regular basis. However, the Government shall coordinate changes with the contractor through contract modification. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.
2. GOVERNMENT ROLES AND RESPONSIBILITIES
The following personnel shall oversee and coordinate surveillance activities.
a. Contracting Officer (CO) – The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment under this contract. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.
Assigned CO: Matthew Dale, NCO 23 Assigned CS: Shanna Comparato, NCO 23
b. Contracting Officer’s Representative (COR) – The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The COR shall keep a quality assurance file. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.
Assigned COR: Donald L. Todd, NWI Surgery Service
3. CONTRACTOR REPRESENTATIVES
The following employee(s) of the contractor serve as the contractor’s program manager(s) for this contract:
Primary Program Manager:
Alternate Program Manager:
(All Government and Contractor personnel listed above may be changed at any time by written notice to all other parties. A modification will not be needed).
4. PERFORMANCE STANDARDS
The contractor is responsible for performance of ALL terms and conditions of the contract. CORs will provide contract progress reports quarterly to the CO reflecting performance on this plan and all other aspects of the resultant contract. The performance standards outlined in this QASP shall be used to determine the level of contractor performance in the elements defined. Performance standards define desired services. The Government performs surveillance to determine the level of Contractor performance to these standards.
The Performance Requirements are listed below in Section 6. The Government shall use these standards to determine contractor performance and shall compare contractor performance to the standard and assign a rating. At the end of the performance period, these ratings will be used, in part, to establish the past performance of the contractor on the contract.
5. METHODS OF QA SURVEILLANCE
Various methods exist to monitor performance. The COR shall use the surveillance methods listed below in the administration of this
QASP.
a. Direct observation. 100% surveillance:
b. Periodic inspection. Inspections scheduled and reported quarterly per COR delegation or as needed.
c. Validated user/customer complaints.
d. Random sampling.
e. Verification and/or documentation provided by Contractor.
NWI Neurophysiology QASP Performance Measures
Measure PWS Reference
Performance Requirement
Standard Acceptable Quality Level
Surveillance Method
Met AQL/DID NOT
MEET AQL-
CPAR RATING/ADD
COMMENTS
Licensing / Registrations / Certifications / Education
Section 5 (see 5.2, 5.3, 5.4)
Contractor personnel have and maintain all license / education / certification requirements
100% of care provided within clinical standards of care
100% Documents submitted by Contractor, random sampling.
On-Call Services Section 8 Timely and compliant on-call services
100%- no lapse in on-call services
98% timely response IAW 8.3.
0% responses more than 60 minutes late
Direct observation
Mandatory Training Section 17.3 Completion of all required initial / annual training requirements
100% 100% Periodic inspection
Key Personnel Section 9 Onboard and replace Key Personnel IAW PWS requirements
100% 100% Documents submitted by Contractor
Quality of Care Section 15 Follows quality of care requirements IAW PWS
100% 100% Direct observation, complaints
Privacy / Confidentiality /
HIPAA
Sections 19 and 20
Follows all PWS requirements and all applicable laws, regulations, policies, including timely report of any violations
100% 100% Documents submitted by contractor, direct observation
Invoicing B.1 Contract Administration Data at #3 (not part of PWS, see page 3 of contract for this)
Contractor submits accurate invoicing NLT the 10th of the following month IAW language in B.1, #3
100% 95% of invoices submitted on time and accurately. All errors / late invoices received / corrected within 30 days of original deadline
Documents submitted by contractor, direct observation, random sampling
6. CPAR RATINGS ASSIGNED TO QASP ITEMS:
Metrics and methods are designed to determine rating for a given standard and acceptable quality level. The following ratings shall be used (Reference: CPARS User Manual: https://www.cpars.gov/documents/CPARS-Guidance.pdf.
EXCEPTIONAL: Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Note: To justify an Exceptional rating, you should identify multiple significant events in each category and state how it was a benefit to the GOVERNMENT. However, a singular event could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
VERY GOOD:
Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Note: To justify a Very Good rating, you should identify a significant event in each category and state how it was a benefit to the GOVERNMENT. Also, there should have been NO significant weaknesses identified.
SATISFACTORY:
Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Note: To justify a Satisfactory rating, there should have been only minor problems, or major problems the contractor recovered from without impact to the contract. Also, there should have been NO significant weaknesses identified.
MARGINAL:
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
Note: To justify Marginal performance, you should identify a significant event in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. A Marginal rating should be supported by referencing the management tool that notified the contractor of the contractual deficiency (e.g. Management, Quality, Safety or Environmental Deficiency Report or letter).
UNSATISFACTOR
Y: Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Note: To justify an Unsatisfactory rating, you should identify multiple significant events in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT.
However, a singular problem could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An Unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g. Management, Quality, Safety or Environmental Deficiency Reports, or letters).
DOCUMENTING PERFORMANCE
https://www.cpars.gov/documents/CPARS-Guidance.pdf
a. The Government shall document positive and/or negative performance. Any report may become a part of the supporting documentation for any contractual action and preparing annual past performance using CONTRACTOR PERFORMANCE
ASSESSMENT REPORT (CPAR).
b. If contractor performance does not meet the Acceptable Quality level, the CO shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the CO shall document the discussion and place it in the contract file. When the COR and the CO determines formal written communication is required, the COR shall prepare a Contract Report (CR), and present it to CO. The CO will in turn review and will present to the contractor's program manager for corrective action.
The contractor shall acknowledge receipt of the CR in writing. The CR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CR will also state how long after receipt the contractor has to present this corrective action plan to the CO. The Government shall review the contractor's corrective action plan to determine acceptability. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance and the acceptability of the Contractor’s corrective action plan.
Any CRs may become a part of the supporting documentation for any contractual action deemed necessary by the CO. See Sample on following page.
7. COR AND CONTRACTOR ACKNOWLEDGEMENT OF QASP
SIGNED:
COR NAME/TITLE DATE
SIGNED:
CONTRACTOR NAME/TITLE DATE
CONTRACT REPORT
1. CONTRACT NUMBER 2. REPORT NUMBER FOR THIS DISCREPANCY
3. TO: (Contracting Officer) 4. FROM: (Name of COR)
5. DATES
a. CR PREPARED
b. RETURNED BY
CONTRACTOR:
c. ACTION COMPLETE
6. Issue Identified (Describe in detail. Include reference to PWS Directive; attach continuation sheet if necessary.)
7. SIGNATURE OF COR Date:
8. SIGNATURE OF CONTRACTING OFFICER Date:
9a. TO (Contracting Officer) 9a. FROM (Contractor)
10. CONTRACTOR RESPONSE AS TO CAUSE AND ACTIONS TO PREVENT RECURRENCE. (Cite applicable quality control program procedures or new procedures. Attach continuation sheet(s) if necessary.)
11. SIGNATURE OF CONTRACTOR REPRESENTATIVE Date:
12. GOVERNMENT EVALUATION.
13. GOVERNMENT ACTIONS
14. CLOSE OUT
NAME TITLE SIGNATURE DATE
CONTRACTOR
NOTIFIED
COR
CONTRACTING
OFFICER
| Various methods exist to monitor performance. The COR shall use the surveillance methods listed below in the administration of this QASP. |
| a. Direct observation. 100% surveillance: |
| a. The Government shall document positive and/or negative performance. Any report may become a part of the supporting documentation for any contractual action and preparing annual past performance using CONTRACTOR PERFORMANCE ASSESSMENT REPORT (CPAR). |
| b. If contractor performance does not meet the Acceptable Quality level, the CO shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the CO shall document the discussion and p... |