Attachment 1 PWS - T4 Demolition Final.pdf

PDF 386 KB Posted

Attached to
W569QE26QA007 Combined Synopsis Solicitation - T4 Demolition / Ft Bliss, TX
Solicitation number
W569QE26QA007
Issued by

About this file

This is a Performance Work Statement (PWS) for T4 Demolition at Building 807 located at Fort Bliss, Texas, dated July 21, 2026. The contract is anticipated to be firm fixed price and covers complete demolition, debris removal, and ground clearing of a temporary T4 Building structure to safely accommodate a heavy-duty vehicle/trailer-mounted Commander Joint Munitions Command (CJMIC) system. The performance period is 7 days from Notice to Proceed, with work performed at 801 Chaffee Road, Fort Bliss, TX 79916 during standard business hours of 0800-1700, Monday through Friday, excluding federal holidays. The contractor must furnish all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other necessary items and non-personal services except those specified as government-furnished property or services.

The specific work includes: (1) pre-inspection and worksite preparation with utility disconnection verification; (2) safe structural demolition and removal of all debris, including tie-downs, skirting, and stairs, with proper off-post disposal at licensed facilities in compliance with OSHA standards, Fort Bliss Directorate of Public Works requirements, and environmental regulations; (3) pre-final inspection with punch list correction within three business days; and (4) final inspection and COR approval with 100 percent compliance requirements. Key personnel include a contract manager and alternate with minimum five years of construction experience and knowledge of El Paso region safety and state construction laws, who must be onsite at all times with a three-hour response time. Deliverables consist of a demolition schedule/checklist (A001) and daily progress reports (A002) submitted electronically to the Contracting Officer Representative. The contract includes standard federal requirements for personnel security clearances, background checks, employment eligibility verification via E-Verify, physical security compliance with Army Regulation 190-13, environmental compliance with AR 420-47 and Title 40 CFR Parts 260-273, and non-disclosure agreements. Contractor employees must wear standard uniforms and display visible identification badges to distinguish themselves from government employees.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

410th Ver 1 2023-10

T4 Demolition at BLG 807

21 JULY 2026

Part 1

General Information

1. GENERAL: This is a non-personal services contract under which the personnel rendering the services are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees. The United States (U.S.) Government shall not exercise any supervision or control over the Contractor’s employees performing the tasks herein. Such contract employees shall be accountable solely to the Contractor who, in turn shall be responsible to the U.S. Government.

1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform T4 Demolition at BLG 807 at Fort Bliss, Texas. As defined in this PWS except for those items specified as government furnished property (GFP) and government furnished services (GFS). The contractor shall perform to the standards in this contract.

1.2 Background: Demolish and remove of workspaces and temporary structures

1.3 Objectives: Complete demolition, debris removal, and ground clearing of the T4 Building site at Bldg 807 to safely accommodate the weight, dimensions, and operational standoff required for the heavy-duty vehicle/trailer-mounted CJMIC (Commander, Joint Munitions Command)

1.4 Scope: Contractor shall provide non-personal services of demolition, debris removal, and ground clearing to include the temporary T4 Building at BLG 807 at Fort Bliss, Texas. The contractor shall accomplish a complete demolition, debris removal, and ground clearing of the T4 Building site at Bldg 807 to safely accommodate the weight, dimensions, and operational standoff required for the heavy-duty vehicle/trailer-mounted CJMIC. (Commander, Joint Munitions Command)

1.5 Period of Performance: 7 days from Notice to Proceed.

1.6 General Information:

1.6.1 Quality Control Plan (QCP): Reserved.

1.6.2 Operations Security (OPSEC) SOP/Plan Requirements: Reserved

1.6.2 Quality Assurance (QA): The government shall evaluate the contractor’s performance under this contract in accordance with (IAW) the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed IAW the performance standards and contract quality requirements are met. Contract quality requirements” means the technical requirements in the contract relating to the quality of the product or service and those contract clauses prescribing inspection, and other quality controls incumbent on the contractor, to ensure the product or service conforms to the contractual requirements. It defines how the performance standards will be applied, the frequency of surveillance, the performance threshold, and deductions, if applicable.

1.6.3 Recognized Holidays: The contractor is not required to perform services on holidays. Tailor for the specific location(s) of performance.

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day

Memorial Day Thanksgiving Day Independence Day Christmas Day Juneteenth Day

1.6.4 Hours of Operation: The contractor is responsible for conducting business between the hours of 0800-1700 Monday through Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.

For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must, at all times, maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons.

1.6.5 Place of Performance: The work to be performed under this contract will be performed at 801 Chaffee Road, Fort Bliss, TX 79916.

1.6.6 Type of Contract: The Government anticipates the award of a firm fixed price type contract.

1.6.7 Access and General Protection Policy and Procedures:

1.6.7.1 FPCON: In addition to the changes otherwise authorized by the changes of clause of contract, should the US Government Force Protection Condition (FPCON) at any individual installation change, the Government may require changes in contractor security matters or process in accordance with DoDI 2000.16.

During FPCONs Charlie and Delta, only contract services that have been deemed “mission essential” by the Government will continue. Contract services will resume when the FPCON is reduced to Bravo or lower.

1.6.7.2 Physical Security: The contractor shall be responsible for safeguarding all government equipment, information, and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured IAW Army Regulation (AR) 190-13, “The Army Physical Security Program.”

1.6.7.3 Escorts: The Contractor and all associated sub-contractor employees performing services under this contract shall be escorted at all times by host nation security personnel or by an individual designated by the Contracting Officer Representative (COR) while accessing U.S. facilities or activities.

1.6.7.4 Personnel Security Clearance Requirements: Reserved

1.6.7.5 Background Checks: Reserved

1.6.7.5.1 Background Check Notification Requirements: If a background check on any employee or subcontractor employee performing services under this contract, whether the check was conducted as a condition of employment or as part of the contract with the Government, reveals any information from any source (including host country law enforcement) of criminal activity by Contractor employees, subcontractors, or subcontractor employees, the Contractor shall notify the KO and COR of that information within 24 hours. The Contractor shall make notification of:

(1) Traffic violations, other than parking, will be reported to the KO or COR only if the contract is for drivers for the Government;

(2) Any suspicious activity by Contractor employees, subcontractors, or subcontractor employees the Contractor believes may pose a risk to U.S. or host nation national security or imminent risk of deadly bodily harm to any person; and

(3) Any actions taken against Contractor employees, subcontractors, or subcontractor employees pursuant to this requirement.

1.6.7.5.2 Remedies. In addition to other remedies available to the Government, the Contractor’s failure to comply with the requirements of this paragraph my result in requiring the Contractor to remove a Contractor employee or employees from the performance of the contract.

1.6.7.5.3 Subcontracts. The Contractor shall include the substance of this paragraph and the preceding paragraph in all subcontracts.

1.6.7.6 Uncleared Contractor Common Access Card (CAC) Credentialing and Access Procedures

1.6.7.6.1 Contractor Common Access Card (CAC) Eligible Requirements: Reserved

1.6.7.6.1.1 Federal Installation/Facility Access: Contractor and all associated sub-contractor employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The employee performing services under this contract shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, Security Office or the host nation equivalent.

1.6.7.6.2. Contractor Non CAC Eligible Requirements for DOD Facility and Installation Access:

Contractor and all associated subcontractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations. The employee performing services under this contract shall provide all information required for background checks to meet installation access requirements to the installation Provost Marshal Office, Director of Emergency Services, or Security Office.

1.6.7.7 Employment Eligibility: The Contractor shall ensure that all Contractor employees and sub-contractor employees performing services under this contract in the U.S. or its territories have been pre-screened for employment eligibility using the E-verify Program on the Department of Homeland Security website http://www.uscis.gov/e-verify. Personnel that have not met the employment eligibility requirement on this website are not authorized to perform services under this contract. Verification of the eligibility check will be made available to the KO or COR within 5 days of request. This requirement is not in lieu of and does not relieve the Contractor from the I-9 Employment Eligibility Verification Forms for employment of personnel.

1.6.7.8 Access to Government Information Systems Reserved

1.6.7.9 Key Control: Reserved

1.6.7.10 Lock Combinations: Reserved

1.6.8 Post Award Conference/Contract Periodic Progress Meetings: The Contractor shall attend the post award conference convened by the contracting activity or contract administration office IAW Federal Acquisition Regulation (FAR) Subpart 42.5. The KO, COR, with other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the KO will apprise the contractor of how the government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.6.9 Contracting Officer Representative (COR): The COR will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: ensure the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral http://www.uscis.gov/e-verify communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor Contractor's performance and notifies both the KO and Contractor of any deficiencies; coordinate availability of government furnished property; and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.6.10 Key Personnel: The following contractor personnel are considered key personnel by the government: Contract manager/alternate contract manage. The Contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate, who shall act for the Contractor when the manager is absent, shall be designated in writing to the Contracting Officer within 1 day. Contract Manager and alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract.

Qualifications for all key personnel are listed below: Contract Manager and Alternate Contract Manager

Contract Manager and Alternate Contract Manager: Contract Manager and Alternate Contract Manager: The CV provided by the Contract Manager and Alternate Contract Manager must have 5 or more years of construction experience; Knows and understand the safety and State laws pertaining to construction in the El paso region. 3 hour three response time with KO or COR for the contract reaches out to get updated status of project. Contract manager or alternate manager shall be onsite at all times.

1.6.11 Special Qualifications or Certifications: Reserved

1.6.11.1 IA/IT Training Certification: Reserved

1.6.12 Identification of Contractor Employees: Contractor employees shall identify themselves as Contractor personnel and shall avoid representing themselves as Government employees. This identification includes meeting attendance, answering Government telephones, email communications, and working in other situations where Contractor status is not obvious. Contractor personnel identification shall be easily identifiable through the display of badges, name tags, lanyards, etc.

1.6.12.1 Badging of Contractor Employees: Reserved

1.6.12.2 Uniform: The Contractor shall provide a standard uniform for all Contractor and subcontractor employees performing services under this contract and ensure they wear the uniform during appointed duty hours. The uniform may consist of the same type and color shirt and slacks for all workers. Company logo is optional.

1.6.13 Contractor Travel: Reserved.

1.6.14 Other Direct Costs (ODC): No other outside cost for the contractor in regards to worksite.

1.6.15 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.6.16. Non-Disclosure Requirements: Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of the Government or others. Neither the Contractor, nor Contractor personnel, shall divulge, nor release data or information developed, or obtained under performance of this work statement, except to authorize Government personnel or upon written approval of the KO. The Contractor shall not use, disclose, or reproduce proprietary data, which bears a restrictive legend, other than as specified in this PWS. All documentation showing individual names or other personal information shall apply, and shall be controlled and protected under the provisions of the Privacy Act of 1974, Public Law 93-579, 5 United States Code (U.S.C.) Section 552a.

1.6.16.1 Non-Disclosure Statements: The Contractor shall provide signed non-disclosure agreements to the Government prior to commencement of work under the contract. Disclosure of information by Contractor personnel may result in Contractor personnel removal from performance of duties under this contract.

1.6.16.2 Advertisement and Social Media: The Contractor shall NOT post information to public website or social media locations, personal or professional, that in any way disclose names, locations, hotel data, participants, discussions, pictures, etc. before, during or after the contract period of performance without the express consent of the Government. The use of propaganda violates DOD Commercial Use of Imagery Guidelines stated at (www.dimoc.mil/resourcess/limitations/). The Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any marketing tools to include its company website, tv/radio broadcasts, online forums and social media including content posted to accounts of family, friends or associates

1.6.16.3 INFORMATION ASSURANCE: At no time will the Contractor or associated sub-contractor employees transmit government documents or information over using methods that do not meet the security requirements specified in the National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171, "Protecting Controlled Unclassified Information in Nonfederal Information Systems and Organizations" such as personal electronic mail accounts, public digital data storage sites (cloud storage), social media platforms or instant messaging. Approved government sites such as U.S. Army Aviation and Missile Research Development and Engineering Center (ARMDEC) Safe Exchange at https://safe.amrdec.army.mil/SAFE/About.aspx, or All Partners Access Network (APAN) at https://community.apan.org/, or other transmission means determined by the government must be used.

1.6.17 Organizational Conflict of Interest (OCI) Contractor and subcontractor personnel performing work under this contract may receive, have access to, or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.6.18 Phase-in/Phase-Out (PIPO) Period: Reserved.

1.6.19 General Training Requirements: Reserved

1.6.19.1 Anti-Terrorism (AT) Level I Training Reserved

1.6.19.2 OPSEC Awareness Reserved

1.6.19.3 Information Assurance (IA) Training Reserved

1.6.19.4 Information Assurance (IA)/Information Technology (IT) Training Reserved http://www.dimoc.mil/resourcess/limitations/

1.6.19.5 Threat Awareness Reporting Program (TARP Training) Reserved

1.6.19.6 iWATCH Training Reserved

1.6.19.7 OPSEC Training Reserved.

1.6.20 Overseas Training Requirements: Reserved.

1.6.20.1 Antiterrorism (AT) Awareness Training for Contractor Personnel Traveling: Reserved

1.6.20.2 SERE Training: Reserved

1.6.21 Foreign (OCONUS) Requirements: Reserved

1.6.21.1 Theater and Country Clearance Requirements: Reserved

1.6.21.2 Vetting: Reserved

1.6.21.2.1 Reserved.

1.6.21.3 Installation Access to DOD Facility or Host Nation Installation: Reserved

1.6.21.4 Host Nation Installation Access with No DOD Facility: Reserved

1.6.21.5 Deoxyribonucleic Acid (DNA) Samples: Reserved

1.6.21.6 Medical Travel Requirement: Reserved.

1.6.22 Synchronized Pre-deployment and Operational Tracker (SPOT) Reserved.

1.6.22.1 Reserved

1.6.23 Safety: The following provides information pertaining to Safety and Accident Prevention:

RA shall consult with the responsible Safety Officer and Activity manager assigned to performance location(s) – Sample narrative provided below may be used and edited as applicable.

1.6.23.1 (OCONUS - Host Nation) Safety Laws and Regulations: Reserved.

1.6.23.1.1 Reserved.

1.6.23.1.2 Reserved.

1.6.24 Environmental Compliance: The following provides information on Environmental Compliance.

1.6.24.1 Environmental Compliance Plan and Program: Environmental. The Contractor shall perform all work in such a manner as to minimize the polluting of air, water, or land and shall, within reasonable limits, control noise and the disposal of solid waste material, as well as other pollutants. The Contractor shall comply with AR-420-47 Solid & Hazardous Waste Management, Title 40 CFR Part 260 through 273 and with all Federal, State, and local laws and regulations concerning environmental pollution control.

Compliance by Subcontractors shall be the responsibility of the Contractor.

PART 2

DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. Definitions:

2.1.1 Area of Responsibility. The U.S. Southern Command (USSOUTHCOM) area of responsibility (AOR) includes the geographic areas of Antigua and Barbuda, Argentina, Aruba, Barbados, Belize, Bolivia, Brazil, British Virgin Islands, Cayman Islands, Chile, Colombia, Costa Rica, Cuba, Curacao, Dominica, Dominican Republic, Ecuador, El Salvador, Falkland Islands, French Guiana, Grenada, Guadeloupe, Guatemala, Guyana, Haiti, Honduras, Jamaica, Martinique, Mayotte, Montserrat, Nicaragua, Panama, Paraguay, Peru, Saint Barthélemy, Saint Martin, Saint Kitts and Nevis, Saint Lucia, Saint Vincent and the Grenadines, Saint Maarten, Suriname, Trinidad and Tobago, Turks and Caicos Islands, Uruguay, and Venezuela.

2.1.2. Contractor. The total contractor organization or a separate entity of it; such as an affiliate, division, or plant that performs its own purchasing.

2.1.3. Contracting officer (KO). A person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.

2.1.4. Contracting Officer’s Representative (COR). An individual designated and authorized in writing by the contracting officer to perform specific technical or administrative functions.

2.1.5. Defective Service. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.6. Deliverable. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.7. Foreign National. A foreign national is not a U.S. citizen. Green card holders are also identified as foreign nationals. A foreign national is further categorized as either a third country national or a local national based on the person’s citizenship and location of performance of duty.

2.1.8. Key Personnel. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.9. Local National. Local nationals are foreign nationals who are citizens of the country where the performance of duty will occur.

2.1.10. Performance Work Statement (PWS). A statement of work for performance-based acquisitions that describes the required results in clear, specific, and objective terms with measurable outcomes.

2.1.11. Physical Security. Protection of the perimeter area, government property, and assets that prevent the loss or damage of Government property.

2.1.12. Quality Assurance. The various functions, including inspection, performed by the government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.

2.1.13. Quality Assurance Surveillance Plan (QASP). A plan describing how the agency will survey, observe, test, sample, evaluate and document the Contractor’s performance in meeting critical performance standards identified in the contract.

2.1.14. Quality Control (QC). Tasks performed by the Contractor to improve the quality of the organization’s output.

2.1.15. Shall. An imperative command; has a duty to or is required to. Denotes that a regulation must be followed unless the contracting officer has obtained a deviation.

2.1.16. Subcontractor. Any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime contractor or another subcontractor.

2.1.17. Third Country National. Third country nationals are foreign nationals who are not citizens of the country where the performance of duty will occur.

2.1.18. Work Day. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.19. Work Week. Monday through Friday, unless specified otherwise.

2.2 Acronyms:

AFFSSIR Armed Forces Repository of Specimen Samples ALMS Army Learning Management System ANSI American National Standards Institute AOR Area of Responsibility AR Army Regulation ATCTS Army Training Certification Tracking System AT Anti-Terrorism CAC Common Access Card CFR Code of Federal Regulations CI Counter Intelligence CLIN Contract Line Item Number CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative DD Form 254 Department of Defense Contract Security Requirement List DNA Deoxyribonucleic Acid (DNA) DOD Department of Defense DODD Department of Defense Directive DODI Department of Defense Instruction FAR Federal Acquisition Regulation FHP Force Health Protection FCG Foreign Clearance Guide FN Foreign National FY Fiscal Year GFE Government Furnished Equipment GFP Government Furnished Property GFS Government Furnished Services IA Information Assurance IAW In Accordance With IT Information Technology JPAS Joint Personnel Adjudication System JTR Joint Travel Regulation KO Contracting Officer LN Local National LOA Letter of Authorization NCIC-III National Crime Information Center Interstate Identification Index

NIST National Institute of Standards and Technology ODC Other Direct Costs OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs OSHA Occupational Safety and Health Administration OPSEC Operation Security PIPO Phase In/Phase Out PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QCP Quality Control Program RA Requiring Activity SCR Service Contract Reporting SOP Standard Operating Procedures SPOT Synchronized Predeployment and Operational Tracker TCN Third Country National TE Technical Exhibit TSDB Terrorist Screening Data Base U.S.C. United States Code USNB United States Naval Base USSOUTHCOM United States Southern Command

THIS SECTION INTENTIONALLY LEFT BLANK

PART 3

Government Furnished Equipment (GFE), Government Furnished Property (GFP), and Government

Furnished Services (GFS)

3. GOVERNMENT FURNISHED ITEMS AND SERVICES:

3.1. Services Reserved.

3.2 Facilities: Reserved.

3.3 Utilities: Reserved.

3.4 Equipment: Reserved.

3.4.1 Reserved.

3.5 Materials: Reserved.

3.6 Common Access Cards (CAC): Reserved.

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Part 3 of this PWS.

4.2 Facility Security Clearance: Reserved.

4.3. Materials The Contractor materials. Contractor will be provided; furnish materials, supplies, and equipment necessary to meet the requirements under this PWS.

4.4. Equipment: The Contractor equipment. Contractor will be provided equipment necessary to meet the requirements under this PWS.

PART 5

SPECIFIC TASKS

5. Specific Tasks: Contractor shall provide non-personal services of demolition, debris removal, and ground clearing to include the temporary T4 Building at BLG 807 at Fort Bliss, Texas. The contractor shall accomplish a complete demolition, debris removal, and ground clearing of the T4 Building site at Bldg 807 to safely accommodate the weight, dimensions, and operational standoff required for the heavy-duty vehicle/trailer-mounted CJMIC. (Commander, Joint Munitions Command)

5.1. Basic Services: The contractor shall execute the complete demolition and removal of Building T4. This includes worksite preparation, verification of utility disconnections, structural teardown, removal of all associated debris (including tie-downs, skirting, and stairs), off-post disposal at an approved facility in accordance with local and environmental regulations, and final site cleanup.

5.2 Building T4 Demolition and Removal Workflow

5.2.1 Pre-inspection of Worksite: The Contract Manager shall coordinate and conduct a joint pre-inspection of the worksite with the Contracting Officer's Representative (COR) prior to mobilization.

(a) Standard (STD): The pre-inspection shall document existing site conditions, verify that all utilities have been properly disconnected and capped, identify any potential safety hazards or environmental concerns, and define the exact limit of demolition work. Must be completed deliverable prior to the commencement of any physical demolition/removal activities.

AQL: 100% compliance.

Deliverable A001 : Demolition Schedule/checklist

5.2.2 Conduct Demolition and Removal of T4 Building: The Contractor shall execute the physical demolition and removal.

(a) STD: The Contractor shall safely demolish the structure, load, transport, and properly dispose of all generated debris off-post at a licensed and approved disposal facility. All work shall be performed in accordance with Occupational Safety and Health Administration (OSHA) standards, Fort Bliss Directorate of Public Works (DPW) requirements, and applicable environmental regulations. The site must be leveled and completely cleared of all structural components, metal frames, and surface debris. Removal of the structure and associated debris with zero unresolved safety violations or unauthorized dumping incidents.

Deliverable A002 shall be submit to COR at the end of work day to show worksite progress update and status.

AQL: 100% compliance.

Deliverable A002: Daily Progress Report

5.2.3 Pre-Final Inspection: The Contractor shall coordinate a pre-final site evaluation to ensure all demolition requirements are substantially complete.

(a) STD: Upon completion of demolition and site clearing, the Contractor shall notify the COR to conduct a joint pre-final inspection. The Contractor shall document any deficiencies or remaining debris identified by the COR during this inspection on a formal punch list and correct all noted items within three

(3) business days.

AQL: 100% Compliance Deliverable A001: Demolition Schedule/checklist Deliverable A002: Daily Progress Report

5.2.4 Final Inspection and COR Approval: The Contractor shall secure final Government acceptance of the completed worksite.

(a) STD: After correcting all punch list items from the pre-final inspection, the Contractor shall schedule a final inspection with the COR. The COR will evaluate the site for final cleanliness, safety, and adherence to all PWS requirements. Final approval will be granted by the COR upon verification that the site is fully restored to the agreed-upon state. Site meets all contract requirements and receives formal COR sign-off. Pass or Fail.

AQL: 100% compliant.

PART 6

APPLICABLE PUBLICATIONS

6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)

6.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

6.1.1 DOD Commercial Use of Imagery Guidelines

6.1.2 AR 190-13, The Army Physical Security Program

6.1.3 Army Directive 2014-05, Policy and Implementation Procedures for CAC Credentialing Access for Uncleared Contractors

6.1.4 DOD 5220.22-M, National Industrial Security Program Operating Manual

6.1.5 Defense Federal Acquisition Regulation Supplement (DFARS)

6.1.6 Joint Travel Regulation (JTR)

6.1.7 AR 735-5, Policies and Procedures for Property Accountability

6.1.8 DODD 8570.01, Information Assurance Training Certification and Workforce Management

6.1.9 DOD 8570.01-M, Information Assurance Workforce Improvement Program

6.1.10 AR 25-2, Information Assurance

6.1.11 DODI 3020.41, Contractor Personnel Authorized to Accompany the U.S. Armed Forces

6.1.12 USSOUTHCOM SC Regulation 40-501, Medical Suitability Screening Regulation

6.1.13 DODI 2000.16 DoD Antiterrorism (AT) Program

PART 7

ATTACHMENT/TECHNICAL EXHIBIT LISTING

7. Attachment/Technical Exhibit List:

7.1 Attachments:

7.1.1 Attachment 1 – Performance Requirements Summary

7.1.2 Attachment 2 – Deliverables Schedule

7.1.3 Attachment 3 – Site photos

ATTACHMENT 1

Performance Requirements Summary The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The standard should relate to timeliness, quality, or quantity (metrics) of service required by the Contractor is stated in the PWS verbiage. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective

Standard Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”) Acceptable Quality Levels (AQL’s)

PRS#1-PWS para(5.1).

The contractor shall execute the complete demolition and removal of Building T4.

The contractor shall execute the complete demolition and removal of Building T4.

This includes worksite preparation, verification of utility disconnections, structural teardown, removal of all associated debris (including tie-downs, skirting, and stairs), off-post disposal at an approved facility in accordance with local and environmental regulations, and final site cleanup.

100% compliance

PRS#2-PWS para(5.2.1) The Contract Manager shall coordinate and conduct a joint pre-inspection of the worksite with the Contracting Officer's Representative (COR) prior to mobilization

The pre-inspection shall document existing site conditions, verify that all utilities have been properly disconnected and capped, identify any potential safety hazards or environmental concerns, and define the exact limit of demolition work.

100% compliance.

PRS #2 - PWS para (5.2.2) The Contractor shall execute the physical demolition and removal.

The Contractor shall safely demolish the structure, load, transport, and properly dispose of all generated debris off-post at a licensed and approved disposal facility. All work shall be performed in accordance with Occupational Safety and Health Administration (OSHA) standards, Fort Bliss Directorate of Public Works (DPW) requirements, and applicable environmental regulations. The site must be leveled and completely cleared of all structural components, metal frames, and surface debris.

PRS #3 - PWS para (5.2.3)

The Contractor shall coordinate a pre-final site evaluation to ensure all demolition requirements are substantially complete.

The Contractor shall coordinate a pre-final site evaluation to ensure all demolition requirements are substantially complete

STD: Upon completion of demolition and site clearing, the Contractor shall notify the COR to conduct a joint pre-final inspection.

The Contractor shall document any deficiencies or remaining debris identified by the COR during this inspection on a formal punch list and correct all noted items within three (3) business days.

PRS #4 - PWS para (5.2.4) The Contractor shall secure final Government acceptance of the completed worksite.

After correcting all punch list items from the pre-final inspection, the Contractor shall schedule a final inspection with the COR.

The COR will evaluate the site for final cleanliness, safety, and adherence to all PWS requirements. Final approval will be granted by the COR upon verification that the site is fully restored to the agreed-upon state.

ATTACHMENT 2

Deliverables Schedule

Deliverable Frequency # of Copies Medium/Format Submit To A:001 Demolition Schedule/checklist (PWS para.5.2.1)

Start of demolition/removal

1 Copy Electronic document (PDF or Excel)

COR

A:002 Daily Progress Report [PWS para. 5.2.2]

Daily, NLT 1700 local time

1 Copy Electronic document (PDF) COR

Attachment 3 Site Photos