Decommission Missile Alert Field (MAF) R-01 Radio Tower and Generator AMENDMENT 01
Solicitation number
FA461326Q0002
Issued by

About this file

This is a Performance Work Statement (PWS) for decommissioning a tower and generator set package at Romeo 01 Missile Alert Facility (MAF) located in Platte County, Wyoming, approximately 72 miles from F.E. Warren Air Force Base. Project number GHLN 25-2741 was prepared by the 90 Civil Engineer Squadron/Missile Engineering on January 20, 2026. The contract is a service contract with a period of performance of 35 calendar days. Working hours are 7:30 a.m. to 4:00 p.m., Monday through Friday, excluding federal holidays, with a 90 CES/CEM Inspector present during all work. The contractor must provide all labor, materials, equipment, and transportation necessary for complete decommissioning and comply with strict security requirements including Entry Authority List (EAL) processing, OPSEC protocols, and anti-terrorism notifications.

The primary work objectives include: (1) complete disassembly and removal of a 206-foot self-supporting steel antenna tower with concrete foundation (foundation removal not required) in accordance with manufacturer recommendations and applicable federal/state/local standards; (2) removal of a Cummins Power single-phase diesel generator unit (model DGCB6255847, 85 hp engine); and (3) submission of a final Post-Project Report within 10 working days including before and after photographs. All removed materials become contractor property and must be disposed of in accordance with environmental regulations. Critical submittals include work schedules, equipment lists, and HAZMAT coordination documentation submitted via DoD SAFE within 15 working days of contract award. The contractor is solely responsible for all safety, environmental compliance, and protection of existing Air Force property; any damage must be repaired at contractor expense.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREFORMANCE WORK STATEMENT

DECOMMISSION TOWER and GENSET PACKAGE at ROMEO 01 MAF PROJECT No: GHLN 25-2741

Prepared By:

90 CES/CEM

Missile Engineering F.E. Warren Air Force Base, Wyoming

Carla Mlinar Engineer January 20, 2026

Service Contract

Table of Contents

1. DESCRIPTION OF SERVICE

2. SERVICES OF SUMMARY

3. GOVERNMENT FURNISHED PROPERTY AND/OR SERVICES

4. GENERAL INFORMATION

5. PRINCIPLE FEATURES OF WORK

5.1. General Requirements

5.2. Existing Conditions

ATTACHMENT 1 – MAF Limit of Potential Ground Disturbance ATTACHMENT 2 – Contract Data Requirements List (CDRL)

APPENDIX 1 – REFERENCES

***NOTE: Any Specifications and/or Regulations must be in accordance with the most current)

Performance Work Statement Decommission Tower and Genset Package at Romeo 01 MAF

Project No: GHLN 25-2741 January 20, 2026

1. DESCRIPTION OF SERVICE .

This project includes decommissioning the tower and the genset (generator and engine) package located at Romeo 01 Missile Alert Facilities (MAF). The MAF is a secure site and under the control of F.E. Warren Air Force Base, Wyoming.

1.1. BASIC SERVICE.

The Contractor is to provide all labor, materials, equipment, and transportation necessary to decommission tower and genset package at the MAF as specified in this Performance Work Statement, in strict compliance with the specifications, applicable drawings, attachments, and the Terms and Conditions of the Contract as well as all applicable local, state, and federal standards and practices in the industry

1.1.1. The Contractor is responsible to conduct, perform, and document.

1.1.2. To supply and install a turnkey, fully functional, tested, and operational product meeting the performance requirements outlined by these specifications.

1.1.3. The Contractor at the conclusion of the project shall provide:

1.1.3.1. Post-Project Report (PPR) (CDRL A001)

1.1.3.2. PPR is to be submitted via DoD SAFE to Contracting Officer (CO), from the 90 Contracting Squadron.

Summarize work that was completed per this contract.

o Included in the PPR photos.

Before work begins.

After work has been completed.

1.1.4. Contractor Data Requirements List and Frequencies are identified in Attachment 2.

2. SERVICES OF SUMMARY.

The Contractor service delivery requirements are summarized into performance objectives that relate directly to the standards of performance required to meet mission needs. For the Performance Objective to be met, service delivery must be in substantial compliance with applicable performance standards. The Performance Threshold describes the minimum overall levels of service delivery required for acceptable quality control. Failure to meet these Performance Thresholds means that Contractor Quality Control is unacceptable. The following is a list of the key performance objectives that will be verified as contractually compliant by Government personnel. However, inspection of any contract requirements is authorized.

PERFORANCE

OBJECTIVE

PWS

PARA. PERFORMANCE THRESHOLD METHOD OF

SURVEILLANCE

SS-1:

DISMANTLE-

Tower Antenna disassembly and removal

Sections 2, 4, and 5.0-

5.4

Zero Discrepancies

All parts of the tower antenna with the exception of the foundation must be disassembled and removed from location.

100 % Decommission Customer Feedback

SS-2:

REMOVAL-

Genset Package removal

Sections 2, 4, and 5.0-

5.4

Zero Discrepancies

All parts of the genset package are to be removed from location.

100 % Decommission Customer Feedback

SS-3: RECORDS-

Final Report

Sections 2, 4, and 5.0-

5.4

Post Project Report-10 working days after performance is complete

100% Post Project Customer Feedback

3. GOVERNMENT FURNISHED PROPERTY AND/OR SERVICES

This section is not applicable to this project.

4. GENERAL INFORMATION

4.1. Security Requirements.

The Contractor and its personnel, to include its employees and any subcontractors, shall comply with pertinent Air Force security regulations while working on the project. Special security clearances such as Confidential, Secret, etc., are not required of the Contractor or Contractor representatives for the performance of this project.

4.1.1 Privacy Act: Work on this project requires that personnel have access to Personal Information. Personnel shall adhere to the Privacy Act, Title 5 of the US Code, Section 552a and applicable agency rules and regulations.

4.2. REAL-ID-Compliant Identification.

4.2.1. IAW DoDM 5200.08V3_DAFMAN 31-101V3_DAFGM 2024-01, Installation Perimeter Access Control. Base access and Common Access Cards (CAC) requests will require REAL ID- Compliant identification for Base access and CAC creation. Failure of the vendor to ensure personnel have REAL ID-compliant identification will result in denial of Base access and CAC requests.

4.3. Levels of Security: Individuals performing work under this contract shall comply with applicable program security requirements. Contractors will support the following levels of security: Unclassified and Unclassified But Sensitive.

4.3.1. Missile Field Access: Access to MAFs are controlled by the U.S. Air Force. All contracted personnel entering the sites shall be on an Entry Authority List (EAL), created by the Air Force.

4.3.2.1. The Contractor shall provide complete written, valid, and legible data that shall include legible photocopies or scanned electronic documents to be used to produce the initial EAL prior to their initial commencement of work at the site for this project. The standard processing time for all EAL actions is thirty (30) calendar days (CDRL A004). Any request to create the initial EAL, or any request to, add to, modify, correct, or renew the EAL must be submitted at least thirty-one (31) calendar days before needing entry to the MAF sites. Any delays caused by the submission of incorrect, outdated, or invalid information will be at no cost to the Government.

The 90 CES/CEM shall provide to the Contractor and the CO, the expiration date for each EAL, when the date is made effective.

4.3.2.2. Contractor submitted data shall include the following for each employee (to include prime, subcontractor, and delivery/testing services employees). All documentation is to be submitted via DoD SAFE:

4.3.2.2.1. Project number, contract number, name of project, and the CO

4.3.2.2.2. Employers name and address (city and state).

4.3.2.2.3. One form of ID:

4.3.2.2.3.1. Legible photocopy or electronically scanned valid driver’s license, state photo ID card, or official state/federal photo ID card with the individual’s name.

4.3.2.2.3.2. The same ID shall be shown for entrance onto the site once the EAL is effective.

4.3.2.2.3.3. Identification cards that expire during the service period must be updated and photocopies or scanned copies must be sent to the CO or their authorized representative thirty-one (31) calendar days (CDRL A004) prior to expiration or the person shall be dropped from the

EAL.

4.3.2.2.4. The Contractor is responsible to provide and maintain the information required to obtain a current EAL for all Contractor’s personnel working on the MAF.

4.4. Operational Security (OPSEC).

The Contractor shall adhere to the following minimum requirements in support of this requirement:

4.4.1. All contractors, subcontractors, their employees, associates, and consultants who have access to critical information and indicators must comply with the Air Force-sponsored Operations Security (OPSEC) program.

4.4.2. OPSEC is an information-related capability that preserves friendly essential secrecy by using a process to identify, control, and protect critical information and indicators. If critical information and indicators are disclosed, it could allow adversaries or potential adversaries to identify and exploit friendly vulnerabilities leading to increased risk to mission failure or the loss of life. The desired effect of OPSEC is to influence the adversary’s behavior and actions by reducing the adversary’s ability to collect and exploit critical information and indicators about friendly activities.

4.4.3. Responsibilities.

4.4.3.1. The Contractor must ensure employees receive OPSEC education that includes an overview of the OPSEC process; the definition of OPSEC; its purpose; what is critical information; the individual’s role in protecting critical information; and the general adversary threat to the AF’s critical information. Additionally, OPSEC education must include updated threat information, changes to critical information and indicators, new procedures and/or OPSEC measures implemented, altered, or deleted by the organization.

4.4.3.2. DoD Contractors with OPSEC requirements or those who have access to critical information and indictors shall complete initial and annually-recurring refresher training.

Accomplishment of initial OPSEC training must not exceed ninety (90) calendar days from initial assignment to a contract with OPSEC requirements. Access to mission-critical information will not be allowed until OPSEC education has been completed and documented.

4.4.3.3. OPSEC education is a continuous requirement. The host unit OPSEC coordinator must track OPSEC training statics to include the personnel working on the contract, when each individual has received the required initial OPSEC training, and when refresher training is due and/or completed.

4.4.3.4. The Contractor’s personnel shall not discuss government operations in public or over unprotected or unencrypted communications. Controlled unclassified information (CUI) may only be transmitted as directed in this PWS.

4.4.3.5. Prior to seeking approval through F.E. Warren AFB Public Affairs, any information to be released outside of official U.S. Government channels, via any media to include electronic communication, must be approved through an OPSEC review. All personnel must promptly report OPSEC-related incidents, issues, and concerns to the host-unit OPSEC coordinator.

4.4.3.6. The Contractor shall restrict access to those individuals with a valid need-to-know who are actually providing services under the contract. Further dissemination of other contractors, subcontractors, or any other government agencies and private individuals or organizations is prohibited unless authorized in writing.

4.4.3.7. Because observation of events, operations, physical changes, etc. may reveal National Security Information, specific restrictions are needed to preclude unintentional release of this information to unauthorized parties. Unauthorized disclosure and transfer of National Security Information is punishable under 18 USC§793. Therefore, the Contract Personnel shall not disclose to unauthorized third parties, post to unofficial sites to include Social Networking sites any images, data/information, or observed events that reveal sensitive government operations, personnel, and equipment.

4.5. Anti-Terrorism

4.5.6.1 Notifications: If the Contractor (contract employees/subcontractors) identify any suspicious activity, they shall contact the Base Defense Operations Center (BDOC) at 307-773- 3501 (On-installation)/Missile Security Control (MSC) at 307-773-2701 (Off-installation) and notify the CO and COR (90 CES/CEM) (if appointed) that they contacted the BDOC and/or

MSC.

4.6. Location/Hours of Operation.

4.6.1. Location.

The work shall be performed at the following MAFs located in Colorado, Nebraska, and Wyoming. The distances from F.E. Warren AFB are indicated in Table 1. Accomplish all work in accordance with the Service Contract Specifications.

TABLE 1

SITE COUNTY STATE DISTANCE

R-01 Platte WY 72

4.6.2. Normal Hours of Operation: The Contractor shall perform the services required under this contract during the hours listed for the location identified in Table 1. Working hours will be between the hours of 7:30 a.m. (start processing on site) and 4:00 p.m. (terminated work off site) excluding Saturdays, Sundays, and Federal Holidays. A 90 CES/CEM Inspector will be provided during these hours.

4.6.3. Recognized Federal Holidays include:

New Year's Day (January 1).

Birthday of Martin Luther King, Jr. (Third Monday in January).

Washington's Birthday (Third Monday in February).

Memorial Day (Last Monday in May).

Juneteenth National Independence Day (June 19).

Independence Day (July 4).

Labor Day (First Monday in September).

Columbus Day (Second Monday in October).

Veterans Day (November 11).

Thanksgiving Day (Fourth Thursday in November).

Christmas Day (December 25).

4.6.4. The Period of Performance (PoP) for this project is 35 calendar days.

4.6.5. The Project Coordinator shall be the CO, from the 90 Contracting Squadron, and the Project Manager shall be the 90 Civil Engineer Squadron/Missile Engineering Flight Construction Chief (90 CES/CEM).

4.6.5.1. F.E. Warren AFB Communications: The majority of work will be in areas where commercial phone service is not available. The following phone numbers are provided for assistance in conducting on-base telephone communications.

OFFICE NUMBER

Emergency 911

Base Operator (307) 773-1110 Visitor Control Center (VCC) (307) 773-3694

Contracting Office (307) 773-3411/5751 Fire Department Tech Services (307) 773-5528

90 Civil Engineer Squadron (CES) (307) 773-3600 90 CES Missile Engineering (307) 773-2438 90 CES Customer Service (307) 773-3175

90 CES Environmental (307) 773-2594 90 Missile Wing Safety (307) 773-1842

90 Bioenvironmental Engineering (307) 773-3088

4.7. Contraband.

4.7.1. The following items are considered contraband on MAF sites. It is an individual’s responsibility to make certain contraband items are not brought onto the MAF site.

4.7.1.1. Privately owned firearms; to include rifles, shotguns, handguns, air/pellet guns, and sling shots.

4.7.1.2. Privately owned ammunition or unauthorized ammunition.

4.7.1.3. Knives (unless less than four inches in length).

4.7.1.4. Explosives, except for official use or storage.

4.7.1.5. Illegal drugs or controlled substances.

4.7.2. Contractors, please note, use of any tools related to the project and not annotated on the EAL shall be deemed as contraband.

4.7.2.1. Thus, all tools including use of cameras are required to be annotated on the EAL and must be signed by 90 MW/CC or designated representative to enter the MAF.

4.7.2.2.Vacating the Work Area: During exercises, natural disaster, and national emergencies or for security reasons, the Contractor may be required to vacate a work area.

4.8. Utility Services.

4.8.1. The Contractor shall provide all utilities, water (drinking and project), and sanitary facilities for the Contractor personnel and as applicable, the 90 CES/CEM Inspector when working at the contract. At a minimum, sanitary facilities shall be portable, rigid, enclosed, and lockable enclosures that are replaced or receive weekly maintenance. The Contractor shall provide site facilities for lunch and break areas as needed.

4.8.2. Equipment: Provide all equipment necessary to accomplish the contract work (CDRLs A001, A002, A003, and A004).

4.8.3. Power equipment shall be equipped with safety, noise limiting, and fume control devices.

The equipment shall be in a safe and efficient operating condition.

4.8.4. Only experienced operators shall be permitted to operate the equipment.

4.8.5. Wireless power tools are not permitted in certain secured areas. Plug-in power tools will be required.

4.8.6. The Equipment list also includes cameras. The following information will need to be listed for the camera.

4.8.6.1. Camera make & model to include serial number.

4.9. Environmental Controls.

4.9.1. Compliance with Laws and Regulations: The contractor shall be knowledgeable of and comply with all applicable Interstate, federal, state, and local laws, regulations, and requirements regarding environmental protection to include Section 01 57 19.05 32 Environmental Protection. In the event environmental laws/regulations change during the term of this contract, the Contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost because of the change, the contractor shall inform the CO pursuant to notify requirements and negotiate a modification to the contract.

4.9.2. Notification of Environmental Spill: If the contractor spills or releases any substances constrained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to the F.E. Warren AFB Fire Dept and Environmental. Contact numbers are listed under 4.5.6. The liability for the spill or release of such substance(s) rests solely with the contractor and its agent.

4.9.3. Hazardous Materials: If hazardous materials will be used in the execution of this contract, the contractor shall comply with all federal, state, and local regulations concerning the use, storage, and reporting of the hazardous material in accordance with AFMAN 32-7002, Environmental Compliance and Pollution Prevention. The Contractor shall be required to obtain authorization per the Installation hazardous Materials Management Program before ordering or purchasing any hazardous product and may not bring a hazard material onto F.E. Warren AFB property nor use a hazardous material until the contractor receives all required authorizations.

This authorization process may take up to three weeks. The contractor shall provide the information listed in Attachment 1 of Section 01 57 19.05 32 to request authorization for all hazardous materials proposed for use on FE Warren AFB or the missile field.

4.9.3.1. The Contractor shall coordinate all hazardous materials (HAZMAT), to include each compound or chemical intended to be utilized on the site, with 90 CES Environmental (307-773- 2594) for review and approval prior to delivery and use on the site.

4.9.3.1.1. A hazardous material is defined in Federal Standard, FED/STD-313F (Tables I and II).

The definition of materials presenting a health hazard or physical hazard is found in 29 CFR 1910.

4.9.3.1.2. The HAZMAT approval documentation (CDRLs A001, A002, A003, and A004) shall be maintained on the site and all workers shall familiarize themselves with their contents.

4.9.3.1.3. The Contractor shall be responsible for establishing a system, which tracks the procurement, delivery to site, installation, and disposal of all hazardous materials including proper disposal documents.

4.9.3.1.4. The Contractor shall be held responsible for proper cleanup and disposal of any hazardous or toxic materials spilled while completing the work in this contract. All cleanups shall be accomplished in accordance with applicable Local, State, and Federal regulations.

4.9.3.1.5. No ozone depleting substances shall be used while completing the work in this contract.

4.9.3.1.6. This includes the exterior/interior of adjacent buildings and parking lot/access road.

4.9.3.1.7. The work site shall be returned to a like condition in which it was found prior to the start of work or to the satisfaction of the 90 CES/CEM Construction Chief and the 90 CES/CEM Inspector.

4.9.3.1.8. Damage to Air Force property caused by Contractor vehicles, operations, equipment, or personnel shall be repaired at Contractor's expense with no additional cost to the Government.

Skilled craftsmen in the trade shall repair such damage to the satisfaction of the 90 CES/CEM Construction Chief and the 90 CES/CEM Inspector.

4.9.3.1.9. Any suspected damage to Air Force property shall be documented and submitted to the 90 CES/CEM Construction Chief and the 90 CES/CEM Inspector with a detailed description of the type and location of damage within seventy-two (72) hours of damage.

4.9.4. Green Procurement Program (GPP): In performance of this contract, contractors shall use Environmental Protection Agency (EPA) designated recycled content products, Information Technology (IT) Energy Star products/appliances, Federal Energy Management Program (FEMP) Designated Energy Efficient Low Stand By Power products/appliances, U.S.

Department of Agriculture (USDA) Bio based/Bio preferred products, Environmentally preferable products, Electronic Product Environmental Assessment Tool (EPEAT) registered products, Water Sense or other water efficient products, non- or Low Ozone depleting substances under the Significant New Alternatives Policy (SNAP), non or Low toxic or hazardous constituents (e.g. non-VOC paint) and any other environmentally sustainable product/method, to the greatest extent possible.

4.10. Safety Requirements

The Contractor is solely responsible for all safety on the project including, but not limited to traffic control, trenching, confined space entry, equipment and materials storage, and compliance by all employees with Base Regulations.

4.10.1. In performing work under this contract, the Contractor shall:

4.10.1.1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

4.10.2. Particular care shall be exercised in connection with the operation of vehicles and other equipment on the site.

4.10.3. Project safety shall be coordinated with the Air Force prior to commencing service.

4.10.4. Notify the Air Force of all modifications to the Safety Plan.

4.10.5. Contractor shall comply with the rules, regulations, standards, and requirements of the Department of Defense (http://www.e-publishing.af.mil , the Environmental Protection Agency (EPA 40 CFR Subchapter I, Part 260-268 and FED-STD-313C, Tables I and II) and 20 CFR 1910), the Occupational Safety and Health Administration (OSHA www.osha.gov ), and all applicable Federal, State, and Local requirements regarding disturbing or removing hazardous materials.

4.10.6. The federal government is not exempt from compliance with environmental and labor regulations.

4.10.7. The Contractor shall notify the 90 CES/CEM Construction Chief and 90 CES/CEM Inspector of any emergency situation(s).

http://www.e-publishing.af.mil/ http://www.osha.gov/

4.10.8. The Contractor shall educate each employee to ensure clear understanding of the following:

4.10.8.1. A review of hazards inherent in the work environment and the precautions required to reduce the hazard.

4.10.8.2. The Contractor shall always maintain a complete first aid kit.

4.10.8.3. Location of first aid and other emergency facilities must be identified.

4.10.8.4. Detailed description of what to do in case of injury, fire, or identification of a safety hazard.

4.10.8.5. Review of daily cleanup procedures, including location and review of company safety rules (either posted or handout).

4.10.8.6. The Contractor shall provide all personal protective equipment (PPE) including, but not limited to, ear plugs, goggles, face shields, gloves, safety shoes, and hard-hats. Complete instructions on where and how to use all PPE shall be given by the Contractor.

4.10.8.7. All personnel shall wear PPE when required by the Contractor or Government Inspector.

4.10.8.8. Hospitals near various sites are noted below for emergency purposes.

Cheyenne Regional Medical Center Regional West Medical Center Sterling Regional Medical Center

214 E. 23rd St. 4021 Avenue B 615 Fairhurst St.

Cheyenne, WY 82001 Scottsbluff, NE 69361 Sterling, CO 80751

307-634-2273 308-635-3711 970-522-0122

5. PRINCIPLE FEATURES OF WORK

NOTE: Refer to this Performance Work Statement, drawings, and attachments for complete details of work. This scope is a general overview of intended work.

5.1. General Requirements.

5.1.1. Project Scheduling: The Contractor shall submit project schedule to the 90 CES/CEM Construction Chief within fifteen (15) working days after the award of the Contract (CDRL A002, A003, and A004).

5.1.1.1. Provide a means for contact after normal working hours for notification of emergency changes to the schedule. If work is not coordinated as stated, Air Force personnel may not be available, work may not be permitted, and the Government shall not incur any additional cost as a result.

5.1.2. Submittals: Prior to starting any work and in accordance with AF Form 66 Schedule of Material Submittals (aka “Submittal Register”), submit material and equipment lists to include camera information, shop drawings, certificates, test results, operation instructions, commercial product warranty or guarantee, manufacturer's brochures, catalog cuts, Safety Data Sheets (SDS), parts lists, and samples on AF Form 3000 Material Approval Submittal (CDRLs A002, A003, and A004) to the CO and with guidance from the 90 CES/CEM Construction Chief for review and approval in accordance with the requirement of these specifications.

5.1.2.1. Submittals shall be provided as one (1) searchable electronic copy via DoD SAFE. Each Contractor-supplied item shall be submitted for approval prior to installation. In no case shall materials be incorporated into the work unless prior written approval is obtained from the CO with guidance from the 90 CES/CEM Construction Chief.

5.1.2.2. All submittal information shall be provided by the Contractor, not less than fifteen (15) working days (CDRLs A002, A003, and A004) prior to any site work or by the date determined by the CO with guidance from the 90 CES/CEM Construction Chief at the pre-service meeting.

One signed and dated copy of the submittal shall be returned to the Contractor after approval or disapproval by the CO with guidance from the 90 CES/CEM Construction Chief.

5.1.2.3. Submittals shall not include information on items other than those provided under this contract.

5.1.2.4. Optional or upgraded items and related information shall only be shown in submittals if included or provided to the Air Force as a portion of this contract.

5.1.2.5. The Contractor shall review and forward all submittals (CDRLs A001, A002, A003, and A004), including subcontractors’ submittals, and shall submit all materials as listed via DoD SAFE to the CO and the 90 CES/CEM Construction Chief for review.

5.1.2.5.1. By reviewing and submitting items, the Contractor represents that all measurements, criteria, materials, catalog numbers and similar data have been verified, and each submittal has been coordinated within the requirements of this Performance Work Statement.

5.1.3. Quality Control: The Contractor shall comply with standards and references for this contract. If standards and specifications conflict, request clarification from the 90 CES/CEM Construction Chief, the 90 CES/CEM Inspector, or their technical advisor.

5.1.3.1.1. Obtain copies of standards and references referenced for each for this contract.

5.1.3.1.2. Maintain a copy at the work Site.

5.1.4. Request for Information: Any change in the condition(s) with or clarification(s) to this project must be presented to the CO and the 90 CES/CEM Construction Chief via a Request for Information (RFI) form prior to any work proceeding.

5.1.4.1. The form shall be completed by the Primary Contractor and processed through the CO.

5.1.4.2. The RFI will reflect whether the change or modification will be at no cost modification to the Government. The RFI will also have all agreeing parties’ signatures.

5.1.5. Modifications: Any change in the condition(s) or modification(s) to the project must be presented to the CO and the 90 CES/CEM Construction Chief via a Request for Information (RFI) form prior to any change or modification.

5.1.5.1. The form shall be completed by the Primary Contractor and processed through the CO.

5.1.5.2. The RFI will reflect whether the change or modification will be a complete modification.

The RFI will also have all agreeing parties’ signatures.

5.1.6. Red Lines: Final report must include before and after photos of work completed.

5.2. Existing Conditions

The Contractor shall perform an inspection encompassing the existing condition at Romeo 01.

5.2.1. The Contractor shall verify all quantities, dimensions, and existing site conditions necessary for completion of the project.

5.2.2. In addition to the Federal Acquisition Regulation, “FAR 52.237-2: Protection of Government Buildings, Equipment, and Vegetation.”

5.2.2.1. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain

5.2.3. This facility does not have power turned on at it.

5.2.4. Tower.

5.2.4.1. Foundation.

5.2.4.1.1. The existing self-supporting tower is attached to a concrete foundation.

5.2.4.1.2. Work does not include removal of the foundation.

5.2.4.1.3. The Existing tower is no longer grounded to guy wire.

5.2.4.1.3.1. Remove any existing wire, if any, and dispose of the material in accordance with federal, state, and local requirements.

5.2.4.2. Foundation Tower Unit.

5.2.4.2.1. The existing tower is a two hundred and six foot (206’±) assembled in accordance with E.I.A.-222E, “Structural Standards for Steel, Antenna Towers, and Antenna Supporting Structures,” mounted symmetrically.

5.2.4.2.1.1. The Tower does not have any other associated accessories such as an antenna or dish.

5.2.4.2.1.2. The Tower does have a maintenance ladder.

5.2.4.2.3. Disassemble the tower in accordance with manufacture recommendations following all applicable federal, state, and local standards and regulations to include but not limited to 29 CFR Part 1910 through Part 1926, 29 CFR 1910.28(b)(13)(iii)(A), and 29 CFR 1910.1200(h).

5.2.4.2.3.1. The Tower material is not to be disposed of on Air Force Property.

5.2.4.2.3.2. All material removed from decommissioning become the property of the Contractor and is to be appropriately disposed of.

5.3.5. Generator Unit.

5.3.5.1. Generator Information.

5.3.5.2. Existing generator unit is a Cummins Power, single phase unit; model number DGCB-

6255847 (SN: A080147768).

5.3.5.3. It includes an 85 hp, diesel Cummins engine. The unit was manufactured November 7, 2023; model number 4BTA3.9-G5 (SN: 21816679).

5.3.5.3.1. No air quality permit was issued by the local state entity. Thus, no permit ownership or notifications are required to be completed by the contractor when taking ownership of the unit.

5.3.5.3.2. There is no meter reader available to read as power has been turned off to the unit.

5.3.5.3.3. Maintenance logs are unavailable to provide hours currently accumulated by the unit during operation.

5.3.5.3.4. No source testing was completed on this unit. It is a Tier 1 nonroad unit.

5.3.5.3.4.1. Fuel in the unit was removed.

5.3.6. The generator package or any of the unit’s fluids and parts are not to be disposed on Air Force property.

5.3.6.1. The Contractor is to properly dispose of the generator package in accordance with all applicable state, federal, and local standards and requirements.

5.3.6.2. The generator package becomes the property of the Contractor upon removal.

5.4. Final Report.

5.4.1. A final report is to be provided to the CO in accordance with SS1 and SS2 (CDRLs A001 and A004).

5.4.1.1. Pre/Post-Photos.

5.4.1.1.1. Pre-work photos are to be taken and provided in accordance with SS1 and SS2.

5.4.1.1.2. Post work photos are to be taken and provided in accordance with SS1 and SS2.

END OF PERFORMANE WORK STATEMENT

ATTACHMENT 1 – MAF Limit of Potential Ground Disturbance Drawings are not classified since published in public document. (Approximately 210 ft from Boundary with Easement)

ATTACHMENT 2 – Contract Data Requirements List (CDRL)

Performance Objective PWS Para. Performance Threshold Method of Surveillance

A001: Services. Sections 1, 2, 4, and 5.0-5.4

Removal of Antenna Tower; Removal of Generator package; and Post Removal of units

SS-1 and SS-2

Final Report-10 calendar days after contract award in final report

A002: Work Schedule. Sections 1, 4, and

5.0 Zero discrepancies. SS-1 and SS-2

A003: Coordination Plan. Sections 1, 4, and

5.0 Zero discrepancies. SS-1 and SS-2

A004: EAL Documentation, Storage Plan, Permits (Local, State, Federal, NPDES, ROW, or Other).

Sections 1, 4, and

5.0 Zero discrepancies.

SS-1 and SS-2

Final Report-10 calendar days after contract completion

APPENDIX 1 – REFERENCES

***NOTE: Any Specifications and/or Regulations must be in accordance with the most current)

1) References

a. Title 40 CFR Environmental Protection Agency (EPA), Subchapter I, Part 260-268

b. Title 29 CFR 1910 OSHA,

c. Federal Standard, FED-STD-313C, Tables I and II

d. Federal Acquisition Regulation (FAR) 52.237-2: Protection of Government Buildings, Equipment, and Vegetation

2) WEBSITES:

• Acceptable Document-Submittals

DoD SAFE: www.safe.app.mil

• Anti-Terrorism https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf

• Occupational Safety and health Administration (OSHA) www.osha.gov

• Department of Defense http://www.e-publishing.af.mil

3) USAF Submittal Forms (AF…)

a. Form 103 Base Civil Engineering Work-Clearance Request aka “Dig Permit”

b. Form 592 Hot Work Permit aka “Burn Permit”

c. Form 66 Schedule of Material Submittal Form

d. Form 3000 Material Approval Submittal http://www.safe.app.mil/ https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf http://www.osha.gov/ http://www.e-publishing.af.mil/

1. DESCRIPTION OF SERVICE .
2. SERVICES OF SUMMARY.
3. GOVERNMENT FURNISHED PROPERTY AND/OR SERVICES
4. GENERAL INFORMATION
5. PRINCIPLE FEATURES OF WORK
5.1. General Requirements.
5.2. Existing Conditions
ATTACHMENT 1 – MAF Limit of Potential Ground Disturbance
ATTACHMENT 2 – Contract Data Requirements List (CDRL)
APPENDIX 1 – REFERENCES
***NOTE: Any Specifications and/or Regulations must be in accordance with the most current)