Attachment 1 - PWS 1305M321QNRMA0051.pdf

PDF 517 KB Posted

Attached to
NOAA Pacific Marine Environmental Lab R/V SP Hayes Repair
Solicitation number
1305M321QNRMA0051
Issued by

About this file

This performance work statement outlines repair and modification requirements for the NOAA research vessel R/V SP Hayes. The vessel will undergo a comprehensive refurbishment including rebuilding main engines; replacing engine components, steering systems, bilge pumps, and navigation equipment; inspecting and repairing hull plating; and modifying structures to enhance deployment capabilities. The contractor will transport the vessel, complete all repairs at their facility by fall 2021, and conduct sea trials prior to returning the vessel to NOAA. The statement establishes repair requirements and contractor responsibilities to ensure the vessel remains reliable and safe for NOAA research missions through 2031.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1 - PWS

Performance Work Statement

NOAA Pacific Marine Environmental Lab R/V SP Hayes Repair

FY 2021

Table of Contents

GENERAL 3

BACKGROUND 3

OBJECTIVE 3

SCOPE 4

REFERENCES 5

DEFINITIONS 6

REQUIREMENTS 8

WORK ITEMS 18

PICTURES 24

1. GENERAL

1.1. BACKGROUND

NOAA’s Pacific Marine Environmental Laboratory (PMEL) is a federal laboratory that makes critical observations and conducts groundbreaking research to advance our knowledge of the global ocean and its interactions with the earth, atmosphere, ecosystems, and climate. Its main office is located at NOAA’s Western Regional Center in Seattle, WA.

PMEL owns and operates the R/V SP Hayes; a 38’ aluminum work vessel used exclusively in the Puget Sound region and Lake Washington. The vessel is primarily used to deploy and test data collection platforms including: buoys, subsurface instrumentation, and autonomous vehicles. PMEL acquired the vessel from the Army Corps of Engineers over 20 years ago. Since acquiring the vessel it has undergone several modifications to increase its functionality for PMEL missions.

Vessel specifications and other details are as follows:

● Year built: 1976

● Manufacturer: Dura Craft, Monticello, AR

● Length overall: 38’ 10”

● Beam: 12’ 10”

● Hull Material: Aluminum

● Superstructure Material: Aluminum

● Engines: Twin 671 Detroit Diesels

● Single station control in main cabin of vessel

● Stern mounted A-Frame

○ 96” of clearance between deck to center padeye

○ 48” of overboard clearance

○ Base width 126”

○ Safe working load 3,000 lbs

1.2. OBJECTIVE

1.2.1. Repair the R/V SP Hayes to a condition that ensures its continued reliability, safety and utility to the lab and its partners until 2031.

1.2.2. Modify existing structures and add features that enhance the vessel's primary mission capabilities including deployment of buoys and instrumentation.

1.3. SCOPE

1.3.1. This Performance Work Statement (PWS) contains the general requirements for work performed by the Small Vessel Repair Contractor (Contractor) for the Pacific Marine Environmental Lab’s R/V SP Hayes. These general requirements apply to all work items contained in this contract including care of the vessel, sea trials, and services provided to the vessel during the contract.

1.3.2. Work under this contract will be performed at the Contractor’s facility. The Contractor is responsible for transport between the NOAA Facility and the Contractor’s facility. Upon completion, NOAA will conduct acceptance testing at the Contractor’s facility.

2. REFERENCES

2.1. US Code of Federal Regulations, 46 CFR, Subchapter T, Small Passenger Vessel (under 100 Gross Tons)

2.2. American Boat and Yacht Council (ABYC) Standards and Technical Information Reports for Small Craft

2.3. American Bureau of Shipping (ABS), Guidance for Building and Classing High Speed Craft,

2.4. ABS Rules for Materials and Welding - Aluminum and FRP

2.5. US Coast Guard (USCG), Marine Safety Center, MTN 01-08

2.6. NOAA Small vessel Standards and Procedures Manual, 4.1 Edition

2.7. NOAA Standard Specification S0100, Implementation and Conduct of Checkpoints

2.8. NOAA Standard Specification AMC-000-3C General Requirements for Small Contract Ship Repairs

2.9. IEEE Std 1580-2010, IEEE Recommended Practice for Marine Cable for Use on Shipboard and Fixed or Floating Facilities

2.10. International Organization for Standardization (ISO) 6954:2000- Mechanical Vibration- Guidelines for the measurement, reporting, and evaluation of vibration with regard to habitability on passenger and merchant ships.

2.11. American Welding Society (AWS) D1.2 Structural Welding Code- Aluminum

3. DEFINITIONS

Wherever used in this specification and in all other work items in this contract, the following definitions of terms apply:

3.1. COR | Contracting Officer’s Representative. An individual, including a Contracting Officer’s Representative (COR), designated and authorized in writing by the contracting officer to perform specific technical or administrative functions.

3.2. Inspect | Visually evaluate the specified surface, item, part, or component for evidence of contamination, damage, excessive wear, scoring, and any other condition which could interfere with the proper operation or functioning of the surface, item, part or component.

3.3. Install | Place the specified item in position for service and make all connections needed to ensure proper use, service, appearance, and operation. Except as may otherwise be specified, this shall include the following:

3.3.1. Provide new or modify existing foundations. Securely mount equipment and components using new fasteners. Align connected equipment and components to meet manufacturer’s specifications.

3.3.2. Make all electrical connections. Provide new electrical cable runs between controllers and motors of new equipment. Existing cables may be reused in other applications, except where the existing cables are too short to make connections. Continuous cable shall be used unless an exception is approved by COR.

3.4. KO | Contracting Officer. A person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the contracting officer acting within the limits of their authority as delegated by the contracting officer.

3.5. Piping | A system of pipe, tube, elbows, tees, valves, couplings, and other pipe fittings.

Unless otherwise specified in the detailed item description, all piping systems and components shall comply with material and installation requirements of reference 2.1.

3.6. Rebuild | Disassemble, clean, inspect, submit condition found report, repair (including renewal of all parts needed such as o-rings, gaskets, and other consumable parts), reassemble, test, and calibrate the specified part, component, system, or machine to restore it to a condition of reliability equivalent to a new part, component, system, or machine.

Components and parts shall meet the manufacturer's applicable rebuild specifications.

3.7. Reinstall | Return the same item which was previously removed to its previous configuration and location.

3.8. Renew | Provide and install a new item for an existing item previously removed or to be removed. The new item must be the identical part number or component ID as the removed item, or manufacturer specified part superseding the item if the removed item is obsolete.

3.9. Replace | Provide and install a new different item for an existing item previously removed or to be removed. The new item must be comparable in material, performance and configuration to the item removed.

3.10. Checkpoint | Instances that have the verbiage “***CHECKPOINT***” in the PWS require the Contractor to verify the work to be performed before commencing the work or upon completion of the work item with the COR if this verbiage is at the end of a work item list.

Any section that does not include “***CHECKPOINT***” does not preclude the Contractor from obtaining COR approval, or verification, before proceeding with work.

4. REQUIREMENTS

4.1. Condition Found Report

4.1.1. A Condition Found Report (CFR) shall be prepared and submitted by the Contractor to the COR on all of the following occasions:

4.1.1.1. Whenever specifically required by this or other documents.

4.1.1.2. Whenever the Contractor determines or notes that additional work or material or other deviation is necessary in order to produce a reliable or complete repair.

4.1.1.3. Whenever defects or deficiencies are noted in Government-furnished Property, or on government equipment or components.

4.1.1.4. Whenever measurements, tests or inspections are required by these specifications, manufacturer standard procedures, or procurement documents, the results and findings shall be documented on a CFR.

4.1.2. Condition Found Reports shall contain, as a minimum, the following:

4.1.2.1. Name of the vessel and Hull Number.

4.1.2.2. Contract number and related work item number.

4.1.2.3. Detailed description of conditions observed, including a record of all measurements taken and other supporting data.

4.1.2.4. Recommendations of additional work and materials deemed to be needed, if any, including the Contractors proposed cost for time and material incidental to the recommendation.

4.1.2.5. Estimate of the impact on the completion of the contract, if any.

4.1.3. Submit Condition Found Reports to the COR within twenty-four hours after completing the measurements, inspections, or tests, or after the need for additional work or material is noted.

4.1.4. For work involving disassembling and inspection of equipment, machinery or systems, the work must be completed and a Condition Found Report submitted during the first 25-percent of the work performance period.

4.2. Responsibility

4.2.1. Coordination of the work schedules will be the responsibility of the Contractor to avoid any delays or disruptions in order to meet the performance period. The Contractor will provide all facilities, labor, materials, tools, and services required to complete the work UNLESS exceptions are noted in the specified tasks below.

4.2.2. Upon receipt of the vessel the Contractor will accept full responsibility for the safety of the vessel, including but not limited to fire protection, security patrols, water-tight integrity, and protection from adverse environmental conditions, etc. This responsibility will terminate only after all work defined herein (or added during the work period) is complete, accepted by NOAA, and NOAA personnel receive the vessel. Contractor is advised that the vessel’s integrated fire protection system may be disabled for all or part of the contract period for service, this does not relieve the Contractor from responsibility for the safety of the vessels.

4.2.3. NOAA employees and Contractors may be working on board the vessel during the contract performance period on a not to interfere basis. During this period it will be required that these personnel have access to the vessel during normal working hours.

4.2.4. If the vessel is hauled from the water, the Contractor will ensure that all machinery and equipment used for that purpose is fully functional, suitable for the task, rated for loads at least 20% greater than the maximum weight of the vessel, and operated by trained, competent personnel. COR (or a representative) shall be present for haul-out and launch of vessel and shall approve the planned placement of lifting straps. The keel shall be blocked in accordance with industry best practices, a minimum of three keel blocks no less than 8 inches in length and at least 4 jack stands shall be used to support and stabilize the vessel.

4.2.5. The government reserves the right to award some or all tasks defined herein, and to add tasks during the work period so long as period of performance revisions, if any, are mutually agreed.

4.2.6. The Contractor is required to maintain any and all applicable regulatory certificates and comply with any and all required inspections for and during the performance of the contract.

4.3. Progress Meetings

4.3.1. Weekly progress meetings shall be held at a time and place mutually agreeable to the COR and the Contractor. As a minimum, the meetings shall be attended by the COR and a Contractor's management official having authority to make binding commitments.

Other interested parties may attend the meetings as appropriate.

4.3.2. Prior to the end of the work day preceding the progress meeting, the Contractor shall submit to the COR a preliminary progress report containing the following information:

4.3.2.1. Percentage of completion of each contract item, including all additional work items authorized by the Contracting Officer.

4.3.2.2. Notation of any problems which could impact timely completion, including material delivery delays

4.3.3. Meeting minutes will be recorded by Contractor and provided to the COR in a CFR.

4.4. Personnel Information

4.4.1. Provide to the COR a list of the Contractor's supervisors and a list of telephone numbers where the supervisors can be reached.

4.4.2. Provide to the COR a list of all Contractor’s and Subcontractor’s workers that will be performing work on Government equipment. Include in the list relevant certifications and certification expiry dates.

4.5. Protective Coverings

4.5.1. Prior to starting work, protect the decks, working surfaces and hull in areas in which contract work is to be performed and spaces through which workers will traverse with a temporarily fitted heavy vinyl, plywood or particle board. Securely tape all edges and joints of the protective covering. Maintain the protective covering in place during the entire contract period, renewing sections which are damaged during the contract period.

4.5.2. Protect all compartments, machinery, equipment, deck coverings, furnishings, insulation, glass, cables, piping systems, coatings, structures, and other vessel components from damage and from entry of dust, dirt, grit, sand, and other foreign particles.

4.5.3. All damage and contamination resulting from failure to provide adequate protection shall be repaired and cleaned by the Contractor at the Contractor’s expense to re-establish the condition which existed at the start of the work.

4.5.4. After completion of all other work, remove and dispose of all protective coverings along with any adhesive residue used to hold coverings in place.

4.6. Local Policies and Directives

4.6.1. While Contractor personnel, including those of subcontractors, are working on the vessel or on other government facilities, they shall comply with all policies and directives issued by the COR or vessel captain.

4.7. Safety Requirements

4.7.1. Fire Watch Standers:

4.7.1.1. Hot work is permitted only when fire watch standers are provided by the Contractor and the work site has been approved by a certified Marine Chemist or Competent Person as required. A fire watch stander is required whenever welding, flame cutting or other hot work is performed where combustible materials are present within 35 feet; or where wall or deck openings within a 35-feet radius expose combustible materials in adjacent areas; or when combustible materials are adjacent to the opposite side of metal partitions exposed to hot work, and could be ignited by conduction or radiation. In the latter case, a fire watch stander is required on both sides of the partition.

4.7.1.2. Each fire watch stander shall be outfitted by the Contractor with a fire extinguisher of a suitable size and type, and appropriate personal protective equipment.

4.7.1.3. Prior to leaving the work site, the fire watch stander shall verify with the worker performing the hot work that no further hot work will be performed. Fire watch standers shall remain at the hot work location for a minimum of 30 minutes after cessation of hot work and ensure the work site is cool to the touch prior to leaving.

4.7.1.4. Insulation, sheathing, or other materials which limit access to either side of a partition or structure on which hot work is being performed shall be considered to be an interference, and shall be removed and restored by the Contractor.

4.8. Interferences and Restorations

4.8.1. Remove all interferences and obstructions necessary to complete the required work. This shall include the disassembly and removal of machinery, piping, ducts, cable, wiring, insulation, structures, and anything else which interferes with the proper accomplishment of work. Except as otherwise specified, this does not include relocations made necessary by new installations which physically prevent an interference from being returned to its existing location.

4.8.2. Whenever an interference to be removed involves a structural strength member, temporary supports shall be provided to compensate for the strength loss. If the vessel is waterborne, whenever watertight integrity is violated by a removed interference, provide a temporary means of maintaining watertight integrity, except when work is actually being performed or the space is otherwise manned.

4.8.3. Restore all interferences to their existing configuration and condition. Install new gaskets and fasteners. In place of material which is rendered unsuitable for reinstallation during removal or storage, provide and install new materials which are equal in composition, strength, design, type, and size as existed prior to removal. All insulation removed or damaged shall be renewed with new insulation.

4.8.4. Align and conduct strength, tightness, and operational tests to ensure that the reinstalled interferences safely perform their normal functions.

4.8.5. The Contractor shall be responsible for identifying all interferences involved in accomplishing required work. Interferences are not normally identified in the detail specifications of the work item.

4.9. Watertight Integrity

4.9.1. The Contractor shall maintain or restore the watertight integrity of the vessel's watertight bulkheads, decks, and hull by installing stuffing tubes, welded bulkhead and deck penetrations, multi-cable transits, couplings, and kickpipes as appropriate. All materials and installation details shall be the same as the nearest similar existing penetrations.

4.10. Removals

4.10.1. Whenever removal of equipment or machinery is specified, but reinstallation is not specified, the Contractor shall remove all related electrical cables, brackets, foundations, and piping. Removal of cables shall be to the nearest circuit breaker or terminal not needed for operation of other equipment or machinery. Removal of piping shall include all related piping not used by other systems or equipment. Install pipe caps as needed to maintain the seal of remaining piping. Foundations or supports shall be cut close to the deck, bulkhead, or other support and ground smooth.

4.11. Brackets and Supports

4.11.1. All pipe, cables, ducts, furniture, equipment, and machinery installed by the Contractor shall be bracketed, supported, and secured so as to carry the weight of the material, prevent excessive vibration, and withstand inertia forces resulting from rolling and pitching of the vessel. For general structural elements and supports excessive vibration is considered in excess of 30 mm/s for single frequency peak component and in excess of 12 mm/s for overall frequency weighted root mean square value when measured in accordance with reference 2.10.

4.12. Gaskets, Packing and Seals

4.12.1. Whenever the Contractor performs work which disturbs existing gaskets, packing, or seals, new gaskets, packing, and seals of same material as existing shall be installed unless otherwise specified.

4.13. Welding and Allied Processes

4.13.1. All welding, brazing, and allied processes shall be in accordance with the requirements and recommendations of references 2.3, 2.4, and 2.11.

4.13.2. Prior to any welding or allied process being performed on the vessel, the Contractor shall provide documentation of welder qualification in accordance with reference 2.4 and 2.11, or alternative qualification as approved by the COR.

4.13.3. All welding on the vessel shall follow a written Weld Procedure Specification, as developed in accordance with reference 2.4 and 2.11. The Contractor shall supply the COR copies of all relevant Weld Procedure Specifications.

4.13.4. All welding, brazing and allied processes on the hull shall be conducted while the vessel is out of the water.

4.13.5. When welding on equipment, machinery, pressure vessels, or piping, the return ground cable to the welding equipment shall be connected in the immediate vicinity (as close as practical) of the work to ensure that current does not flow through bearings, pipe hangers or other areas where arcing or high resistance paths exist.

4.14. Painting

4.14.1. Prior to applying any paint or coatings, the Contractor shall verify that all surfaces have been properly prepared and that weather conditions are suitable for painting. Painting shall not commence until the COR, or representative, has observed the Contractor verify temperature and humidity conditions are within the paint manufacturer's requirements.

Contractor shall submit a CFR documenting the conditions at the time of paint application.

4.14.2. Paint shall be applied only when the following conditions exist and can be maintained until the paint has cured:

4.14.2.1. Apply paint only to dry surfaces and when there is no chance of precipitation until after the paint has cured. The temperature of the surface to be painted shall be at least 5 degrees Fahrenheit above the dew point. The dew point shall be measured prior to painting by taking the dry-bulb temperature of the surface and the wet-bulb temperature at the jobsite.

4.14.2.2. The air temperature and surface temperature must both be a minimum of 45 degrees Fahrenheit at all times, unless a lower temperature is specifically authorized by the paint manufacturer’s printed instructions.

4.14.2.3. Painting is permitted only when the humidity is less than 80 percent unless otherwise specified in the paint manufacturer’s written instructions. In the event the Contractor desires or must proceed with painting when the existing weather conditions do not meet the above specified conditions, the Contractor shall erect a cover over the surfaces to be painted and shall heat the surfaces and the surrounding air to establish the required conditions. The conditions shall be maintained until the paint has fully cured in accordance with the paint manufacturers’ application instructions.

4.14.3. Restore all existing coating systems which are damaged during performance of work. The new coating system shall be the same as existing.

4.14.4. Surface preparation and paint application shall be in accordance with applicable NOAA specifications and comply with the paint manufacturers' printed recommendations and instructions for all aspects of surface preparation, and handling, mixing, and application of paint materials.

4.14.5. Paint schedule: Paint systems used on the vessel shall consist of a primer coat followed by a minimum of two top coats unless otherwise specified either in the detailed specification or by the manufacturer of the paint. It is the responsibility of the Contractor to ensure that paint used is compatible with existing paint on the vessel

4.15. Electrical

4.15.1. All requirements and recommendations of references 2.2, 2.3, and 2.5 shall be followed in the selection and installation of electrical cables, equipment, and machinery in accordance with 46 CFR Part 111. New electrical cable shall meet the standards of reference 2.9. Cables shall be installed neatly and shall be aligned with one another.

Cable paths shall avoid sharp bends and chafe points, and cables shall be secured at approximately 18 inch intervals. Where cables penetrate watertight boundaries, the penetrations shall be sealed with mechanical stuffing tubes or compression block fittings.

New cables shall be labeled with the name of the circuit number or system, and labels shall be of robust material and robustly attached to the cable. Cable connections shall be made with mechanical crimp ring terminal fittings utilizing heat shrink tubing, or with compression terminal strip blocks. AC power cabling shall be routed with at least six inches of separation from signal or communication cables.

4.16. Weight and Stability

4.16.1. Contractor shall provide certified weight of vessel in a CFR before commencing work and after all work is complete.

4.17. Departure Trials and Testing

4.17.1. Upon completion of work all systems that were worked on shall be tested per manufacturer’s recommendation and to demonstrate satisfactory system performance in normal operating conditions.

4.17.2. The Contractor will, prior to departure, provide a thorough clean-up of all work areas to be approved by the COR. The clean-up shall restore all work areas and associated passageways and access pathways to the same condition of cleanliness and serviceability as they were originally upon the vessel's arrival. Clean up shall include, but not be limited to activities such as sweeping, vacuuming, wiping, washing, degreasing, waxing, painting and repairing/replacing as necessary to return the vessel to the arrival condition of cleanliness and serviceability.

4.17.3. The Contractor shall submit to the COR a schedule for testing all equipment the Contractor has worked on one week before departure. The Contractor must submit a list of the personnel who will ride on the vessel during departure for testing work.

4.17.4. The Contractor shall provide at least one supervisor for departure testing to coordinate testing, adjustment and repair of discrepancies.

4.17.5. All equipment will be operated by government personnel.

4.17.6. All testing will be conducted during normal working hours.

4.17.7. No Contractor work will be allowed during trials except as approved by the COR.

4.17.8. Departure trial discrepancies must be corrected before the completion of the contract.

4.17.9. At the COR’s discretion, departure trials may be replaced with dock trials.

4.18. Test and Inspections

4.18.1. Prior to the Contractor accepting the vessel, a walkthrough shall be conducted jointly with the Contractor and NOAA representative demonstrating proper operation of all systems or current condition. Satisfactory performance (or discrepancies) shall be documented in a CFR. Upon completion of all Contractor work the vessel shall be cleaned in all work areas and returned to the condition which it arrived as documented jointly by the COR and Contractor.

4.18.2. At least twenty-four hours (and during normal working hours), in advance of conducting each required test and inspection, notify the COR in order to allow the COR the opportunity to witness, or to arrange for another NOAA representative to witness the tests and inspections. The COR must be present unless the COR has authorized testing/inspection to proceed without their presence.

4.18.3. All tests and inspections shall be witnessed by the Contractor's supervisor responsible for the work. A Condition Found Report (See 4.1) shall be prepared to document the results of all tests and inspections.

4.18.4. To the extent possible, all tests and inspections shall be scheduled during the normal weekday work shift. Tests and inspections may be scheduled for other times only when necessary to avoid a delay in contract completion. When necessary to schedule a test or inspection after the normal workday shift or on a weekend, the COR shall be notified of the test or inspection at least four hours before the end of the last preceding regular work shift.

4.18.5. The Contractor shall perform an operational test of all newly installed, overhauled, and repaired equipment to demonstrate proper operation. Vessel equipment will be operated by the NOAA Personnel.

4.19. Disposal of Fluids

4.19.1. Whenever work requires that equipment, machinery, piping, or tanks be drained of fluids, the Contractor shall be responsible for draining and proper disposal of the fluid in accordance with local, state, and federal regulations. If the Contractor drains the fluid into the vessel's bilges, the Contractor shall pump all fluid from the applicable bilges into tanks and properly dispose of the fluid, including the fluid that existed prior to and the fluid that accumulates between the time the equipment, machinery, piping or tanks were drained and the time the bilges have been pumped dry by the Contractor. The cost of this should be included in the specific work items. A written record shall be provided to the COR at the completion of the contract, documenting quantity and type of fluids disposed of and receiving authority (ie company that took possession of the fluids).

4.20. Disassembly and Inspections

4.20.1. Whenever equipment, machinery, systems, or other system components are required to be disassembled, opened or overhauled, the Contractor shall complete all disassembling and inspections during the first 25-percent of the work performance period. No time extension of the work performance period will be granted for delays caused by the Contractor's failure to comply with this 25-percent time requirement.

The 25-percent time requirement is calculated by multiplying the total number of work days proposed in the Contractors schedule by 0.25 and rounding up to the next whole number then adding that number of days to the scheduled start date not counting weekends or holidays not worked.

4.21. Notes

4.21.1. The requirements and provisions of this specification are additions to or amplification of the requirements and provisions set forth in other specifications, solicitation, or procurement documents. In the event a conflict should occur, the requirements of the other documents take precedence over those contained here.

5. WORK ITEMS

1. Main Cabin | Control Station

1.1. Remove and replace throttle and steering controls with electro/mechanical controls at the main cabin control station. Provide COR options for replacement systems and cost breakdown for final installation determination.

1.2. Provide COR options for integrating a remote steering/throttle control unit worn/held by the captain to control the vessel from the aft deck.

1.3. Remove and replace all gauges at the main cabin control station including port and starboard engine monitoring gauges. Install new audio/visual engine alarms and remote shutdown controls including oil pressure and engine temperature. Mount gauges so they sit at a 45° to 65° angle to the horizontal plane to increase readability.

1.4. Remove and replace all existing breakers/switches at the cabin control station. Replace all wiring and hardware with marine grade components according to ABYC standards.

1.5. Remove and replace captains chair with new chair ergonomically installed to enable easy access to controls, and switches, while providing clear visibility of gauges.

2. Main Cabin Bilge | Bilge Pump

2.1. Renew bilge pump in main cabin bilge compartment with like and kind. Bilge pumps capacity in “Gallons per Hour” shall be no less than the existing bilge pump.

3. Main Cabin Bilge | Thru-hull Inspection

3.1. Inspect thru-hulls and transducer for watertight integrity. Submit a CFR with findings and recommendations.

4. Main Cabin Bilge | Starboard Side Cracked Weld Seam

4.1. Inspect damaged weld seam and hull plating. Submit CFR with findings and recommendations for repair.

4.2. ***Checkpoint***Crop out and renew damaged plating in this area.

5. Main Cabin Bilge | Remove Pitting and Clean Bilge

5.1. Clean main cabin bilge for inspection of pitting near keel on port and starboard side.

5.2. Gauge pitting on port and starboard side of keel. Clad weld all pits that are greater than 20% wastage of the original hull thickness. Alternatively crop out and renew plating if this is more cost effective.

5.3. Clean, prepare, and coat the main cabin bilge with appropriate protective paint upon completion of all other work in space.

6. Optional | Engine Compartment | Engine Hatch Lift

6.1. Install spring assist gas shocks on engine hatches appropriate for the weight of the hatches.

Mechanical safety locks shall be installed to secure the hatch in the “up” position.

7. Engine Compartment | Bilge Pump

7.1. Renew bilge pump in engine compartment with like and kind. Bilge pumps capacity in “Gallons per Hour” shall be no less than the existing bilge pump.

7.2. Install bilge pump alarm float switch at a location lower than the actual bilge pump. Speak with COR on exact placement.

8. Engine Compartment | Sea Water Strainers

8.1. Renew port and starboard engine seawater intake strainers. Replace seawater hoses if beyond serviceable condition.

9. Engine Compartment | Engines

9.1. ***CHECKPOINT*** Perform comprehensive out-of-frame engine rebuilds to the port and starboard main engines. The below child bullet shall be included in the engine rebuilds.

9.1.1. Inspect, clean and pressure check exhaust manifolds for leaks and integrity.

9.2. Remove and replace all fuel lines. Install chafing gear around fuel lines. New fuel lines shall be routed through a bracket mounted fuel shut-off manifold and all fuel lines shall be secured with retaining clips. Fuel lines shall be rated for use with biodiesel.

9.3. Remove and replace all hose lines associated with the port and starboard main engines.

9.4. Prepare and paint engines prior to reinstallation.

10. Engine Exhaust Systems

10.1. Inspect exhaust runs and all system components including exhaust risers and mufflers.

Confirm integrity of all piping. Submit CFR with findings and recommendations.

10.2. Replace all worn, corroded or leaking components as necessary. Re-insulate system.

10.3. Install flexible hoses on outlet sides of the port and starboard exhaust mufflers. Remove part of the existing exhaust piping to accommodate the new flexible hose at transom in the lazarette.

11. Engine Compartment | Transmissions

11.1. Check transmission oil pressures prior to the vessel being hauled out.

11.2. Check transmission input and output shaft seals for leaks.

11.3. Remove and inspect transmissions. After separating engines from reverse gears, check couplings between engine and transmission for wear.

11.4. Submit a CFR documenting findings and recommendations including transmission oil pressure prior to haul out.

11.5. Replace all transmission hoses.

11.6. Prepare and paint transmissions prior to reinstallation. Mask off transmission output flange prior to painting.

12. Propeller shaft

12.1. Remove and inspect port and starboard propeller shafts. Submit CFR with findings and recommendations.

12.2. Remove and replace cutlass bearings.

12.3. Test and prove alignment of shaft log, strut bearings, and transmission output flange prior to reinstalling shafts. Confirm propeller shafts align to engines. Submit CFR with final coupling flange alignment measurements.

13. Engine Compartment | Shaft seal

13.1. Remove and replace existing port and starboard packing glands with dripless seal systems.

13.2. Inspect aluminum shaft log tubes for corrosion.

14. Engine Compartment | Seawater Intake Valves

14.1. Inspect main engine seawater hull penetrations for corrosion and pitting. Submit CFR.

14.2. ***Checkpoint*** Crop out and replace seawater hull penetrations as necessary.

14.3. Remove and replace seawater valves for the port and starboard main engines. New seawater valves must be compatible sizes with seawater strainers and of sufficient size to supply engines with appropriate cooling water.

15. Engine Compartment | Clean Bilge

15.1. Clean engine compartment bilge. Renew bilge protective coatings in accordance with industry best practices for aluminum plating.

16. Lazarette | Bilge Pump

16.1. Renew bilge pump in lazarette with like and kind. Bilge pumps capacity in “Gallons per Hour” shall be no less than the existing bilge pump.

17. Lazarette | Steering System

17.1. Remove and replace all components of the existing steering system and helm with new hydraulic steering system. Provide COR options for replacement hydraulic system with capability to integrate electronic steering controls. Provide quote for final installation determination.

17.2. Rudder shall be capable of being locked in the centered position with a by-pass lockout valve in the hydraulic lines in the event of a steering failure.

18. Lazarette | Portside FWD Bulkhead Hull Plating

18.1. Inspect damaged hull plating located on the forward portside of the compartment. Submit CFR with findings and recommendations.

18.2. ***Checkpoint***Crop out and renew damaged hull plating.

19. Lazarette | Sea Water Pump Hose Hull Penetration

19.1. Crop out and renew sea water pump hull penetration at the forward/outboard port bulk head of the lazarette. Install new metallic penetration fitting with metallic cutout valve. No non-metallic hoses or fittings shall be used prior to the cutout valve.

20. Lazarette | Hull Plating in the Vicinity of the Propellers

20.1. Survey entire hull plating for wastage, specifically in the vicinity of the propellers. Submit CFR with findings and recommendations.

20.2. ***CHECKPOINT*** Crop out and renew wasted hull plating.

21. Lazarette | Clean Bilge

21.1. Clean lazarette bilge. Renew bilge protective coating.

22. Lazarette | Battery Charger Connection Wires

22.1. Rewire connection to battery charger on starboard side bulkhead of lazarette to ABYC standards.

23. Lazarette | Rudders

23.1. Remove rudders. Inspect rudders, rudder gland tubes, seals and bearings. Submit CFR with findings and recommendations to bring up to date.

24. Optional | Aft deck Control Station

24.1. Submit a CFR providing recommendations for the fabrication of an aft steering control station. The steering/propulsion control station should be located on the exterior aft portion of the starboard cabin superstructure. The steering/throttle controls should be combined into a single unit if possible.

24.2. This option would be considered if work item 1.2 was not able to be accomplished.

25. Optional | A-frame

25.1. Increase maximum height of A-frame by 12 inches. The new A-frame must meet or exceed the safe working load of the existing A-frame. A licensed professional engineer shall approve all designs before modifications are made.

25.2. A stability analysis shall be conducted for this modification and provided to the COR.

26. Propellers

26.1. Inspect propellers. Submit CFR documenting findings and recommendations.

26.2. Re-condition propellers. Check pitch and rebalance as needed. Check fit to propeller shaft.

Provide COR with a before and after prop-scan report.

27. Optional | Bulkhead Penetrations

27.1. Inspect bulkhead penetrations. Submit a CFR documenting findings and recommendations.

27.2. ***Check Point*** Correct deficiencies in bulkhead penetrations, including sealing penetrations with mechanical stuffing tubes or compression block fittings to ensure watertight integrity where required. All methods for ensuring bulkhead watertight integrity shall be in compliance with industry standards and best practices.

28. Optional | Main Cabin Bilge | Configure existing unused tank in bilge to supply fresh water to back deck

29. Lazarette | Generator

29.1. Inspect generator for proper functioning and signs of wear. Submit CFR with findings and recommendations.

30. Optional | Navigation Lights

30.1. Replace all navigation lights and their respective housings. New lights should be LED.

Navigation lights include side lights, masthead light, and stern light. New lights shall comply with all U.S. Coast Guard rules and regulations.

31. Optional | Main Cabin Bilge | Install permanent edge tech transducer thru hull

6. PICTURES

6.1. Pictures of task items can be accessed via the following google drive link below:

https://drive.google.com/drive/folders/1t19GIjybip9orgJXH1cXSD0rnxjMZzoj?usp=shar ing

6.2. If necessary request access to the pictures after clicking the link.

File details come from the government source that posted it. Updated .