About this file

This document is an attachment to a federal solicitation providing site-specific requirements for a contract to service an oily water treatment system at Puget Sound Naval Shipyard & IMF in Bremerton, Washington. The attachment outlines environmental, safety, security and logistical requirements contractors must follow, such as obtaining training and certifications for personnel, complying with waste handling procedures, and restricting activities during certain hours. Contractors would be responsible for storage and disposal of all waste generated. The solicitation requests servicing of an existing oily water treatment system and responses are due by April 30, 2021, with work expected to commence in July 2021.

The attachment specifies documentation that must be submitted regarding hazardous materials, lift points on equipment, plans for excavation and drilling, and vehicle permits. It also defines restricted areas and activities at the facility along with required personal protective equipment and training. Compliance with enumerated laws and regulations is mandatory.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1, Site Specific Requirements

Puget Sound Naval Shipyard & IMF, Bremerton Site and Naval Base Kitsap

1. SCOPE

1.1. Scope. This attachment covers the site specific requirements of Naval Base Kitsap (NBK) and Puget Sound Naval Shipyard & Intermediate Maintenance Facility (PSNS & IMF) for contract work.

2. APPLICABLE DOCUMENTS

2.1. General. The following documents form a part of the site specific requirements to the extent specified herein.

2.2. Washington Administrative Code (WAC)

WAC-173-303 Washington Dangerous Waste Regulations

WAC-173-60 Maximum Environmental Noise Levels

WAC-173-304 Minimum Functional Standards for Solid Waste Handling

(Copies are available online at: http://apps.leg.wa.gov/wac/)

2.3. Code Of Federal Regulations (CFR)

29 CFR 1910.141 Sanitation

29 CFR 1910.1200 Hazard Communication

40 CFR Part 82 Protection of Stratospheric Ozone

40 CFR Part 89 Control of Emissions from New and In-Use Non-Road

Compression-Ignition Engines

(Information is available at: http://www.ecfr.gov/cgi-bin/ECFR?page=browse)

2.4. American Society of Mechanical Engineers (ASME)

ASME B30.26 - 2015 Rigging Hardware

ASME BTH-1 - 2017 Design of Below-the-Hook Lifting Devices(Information is available at:

https://www.asme.org/)

2.5. American Society for Testing and Materials (ASTM)

ASTM E709 – 17 Standard Specification for Structural Steel

(Information is available at: https://www.astm.org/)

2.6. American Welding Society (AWS)

D1.1/D1.1M:2006 Structural Welding Code – Steel

(Information is available at: http://www.aws.org/technical/d1/D1scope.pdf)

2.7. Military Standards

MIL-STD-2035 Nondestructive Testing Acceptance Criteria

(Information is available at: https://assist.dla.mil/online/start/)

2.8. Unified Facilities Criteria (UFC)

http://apps.leg.wa.gov/wac/ http://www.ecfr.gov/cgi-bin/ECFR?page=browse http://www.aws.org/technical/d1/D1scope.pdf https://assist.dla.mil/online/start/

UFC 3-430-07 Operations and Maintenance: Inspection and Certification of

Boilers and Unfired Pressure Vessels

2.9. PSNS & IMF

Contractor Guide to Environmental and Safety Compliance

(Contact the Receiving Activity’s Point of Contact to obtain a copy of the guide)

2.10. NAVAL FACILITIES ENGINEERING COMMAND (NAVFAC)

NAVFAC P-307 Management of Weight Handling Equipment (June 2016)

(Copies available online at http://www.navfac.navy.mil/navfac_worldwide/specialty_centers/ncc/about_us/resources/p307.h tml)

3. REQUIREMENTS

3.1. Prior to commencing work. The Contractor representative(s) shall meet in conference with the Receiving Activity’s Point of Contact, shop supervision, and other necessary

Shipyard personnel to discuss and develop mutual understandings relative to environmental, safety, methods and schedules, security, waste management, and any other subject necessary for a smooth and successful execution of this contract. This meeting shall be held at the

Receiving Activity within 30 business days of contract award.

3.2. Methods and schedules. The work shall be executed in a manner and at such times as to cause the least practicable disturbance to the occupants of the buildings and normal activities of the Shipyard.

3.3. Plan of Action and Milestones. Within 30 business days of contract award the Contractor shall provide a Plan of Action and Milestones (POAM) detailing key events with dates of the following:

a. Design

b. Manufacturing

c. Equipment Delivery

d. Equipment Set-up/Installation

e. Equipment Testing

f. Training

g. Final Completion Date

3.4. Field Supervisor. The Contractor shall provide a full-time (start of installation to final acceptance) Field Supervisor to direct installation and testing of the equipment. The Field

Supervisor shall be capable of reading, writing, and conversing fluently in the English language and have full authority to implement field decisions expeditiously. No work shall be accomplished when the Field Supervisor is not in the immediate work area. The Field

Supervisor shall be identified to the Receiving Activity’s Point of Contact prior to the start of the installation and be responsible for coordinating security clearances of all Contractor http://www.navfac.navy.mil/navfac_worldwide/specialty_centers/ncc/about_us/resources/p307.html http://www.navfac.navy.mil/navfac_worldwide/specialty_centers/ncc/about_us/resources/p307.html personnel expected to perform on-site work. The Receiving Activity’s Point of Contact shall be notified of any change in personnel performing this duty.

3.5. Calibration. The Contractor shall provide calibration control instructions for each calibrated item.

3.6. Outages and permits. The Government’s process of review/approval for Utility, Area, and Track Outages may take up to 20 business days from the date the Contractor provides acceptable drawings, forms, and any other required information to the Receiving Activity’s

Point of Contact.

3.7. Excavation or drilling. An Excavation Permit request form will be provided to the contractor by the Receiving Activity’s Point of Contact. Prior to any excavation or drilling, the contractor shall:

3.7.1. Perform a Locate Service Survey of the installation site to locate and identify any subsurface interference(s). A copy of the Subsurface Interference Survey Report and a completed Excavation Permit form shall be provided, in electronic format, to the Receiving

Activity’s Point of Contact for review, and approval by NAVFAC, no later than 20 business days prior to the start of excavation or drilling.

3.7.2. Post the approved Excavation Permit onsite from the beginning of excavation or drilling through completion.

3.7.3. Construct adequate containments around the excavation or drilling site to minimize dust, and to prevent foreign material from becoming airborne, and intrusion on or into existing equipment in the vicinity.

3.7.4. Two Waste Information Sheets (WIS, Section 8.2) shall be submitted for concrete cut water. One for pH less than 11, and one for pH 11 or greater. The Environmental Safety and

Health Office (Code 106.33) will classify each type of concrete cut water. The Contractor shall supply the pH test strips for determining pH level of concrete cut water

3.7.5. Upon completion of excavation or drilling, the Contractor shall provide the information on the Excavation Permit indicating completion and submit the permit to the Receiving

Activity’s Point of Contact for closing.

3.8. Building columns. Welding, drilling, cutting, or clamping to original building columns and column bracing is restricted. Prior to performing any of these evolutions, the Contractor shall submit a request to the Receiving Activity’s Point of Contact for approval. The request shall include locations, components, materials, static loads, dynamic loads, moment forces, and structural calculations demonstrating that the load will not adversely affect the structural integrity of the column or its bracing.

3.9. Internal combustion engine operation inside buildings. The Contractor shall utilize the following ventilation controls when operating internal combustion engines inside buildings:

a. Open doors, windows, roof vents, and/or use blowers or other mechanical systems to move fresh air through work areas. In the event internal combustion engines will be operated for more than 30 continuous minutes, the receiving activity’s

Environmental, Safety, and Health Department shall be notified in advance to survey the area to ensure there is adequate ventilation.

b. When operating internal combustion engines longer than 30 continuous minutes with less than 3 minutes between operations, attach an approved ventilation exhaust hose and exhaust the fumes to the exterior of the building where they cannot re-enter the workplace. Regularly inspect the hose for defects and damage, and repair or replace as required. The Contractor shall provide an engineering solution for the use of long exhaust hoses to prevent engine back pressures.

c. Ensure internal combustion equipment is properly maintained and routinely inspected to minimize exhaust emissions.

d. Use of internal combustion equipment shall be coordinated with the Building

Manager. This pre-planning will help ensure that indoor air quality issues are minimized.

3.10. Non-Road Engines. All non-road engines rated 50 horsepower and above shall be identified to the Receiving Activity’s Point of Contact prior to being brought on to PSNS &

IMF or NBK to prevent violation of Title V, Air Operating Permit. C/106.31 will determine the need for additional air pollution controls when using non-road engines (i.e. skid or trailer mounted generators and pumps).

3.11. Boilers and Unfired Pressure Vessels. Boilers and unfired pressure vessels which meet the below criteria shall be identified to the Receiving Activity’s Point of Contact prior to being brought onto PSNS & IMF or NBK. The boilers and unfired pressure vessels that meet the below criteria shall be certified in accordance with UFC 3-430-07 Inspection and Certification of Boilers and Unfired Pressure Vessels.

a. Greater than 5 cu ft in volume and 250 psi design pressure

b. Greater than 3 cu ft in volume and 350 psi design pressure

c. Greater than 1-1/2 cu ft in volume and 600 psi design pressure

3.12. Utilities. Reasonable amounts of shop air (80-90 psi) and electricity (120 Volt) will be made available adjacent to the installation site at no cost to the Contractor. The Contractor shall be responsible for any costs incurred in connecting, converting and transferring the utilities to the work.

3.13. Storage. Lay-down area(s) will be provided within the vicinity of the installation site for storage of Contractor’s materials and tools. The Contractor shall submit an Area Outage

Request to the Receiving Activity’s Point of Contact no later than 20 business days prior to the outage date. The Government does not accept responsibility for security of Contractor’s materials or tools. The area must be kept clean and orderly, free of rags, paper, and other debris. Failure to maintain the area in a clean condition may result in the loss of the area. The

Contractor shall be responsible to restore the storage area to original condition after use.

3.14. Contractor Training. The following training is available for Contractors whose work requires it. The training classes are held on Naval Base Kitsap (NBK) and are provided at no cost to the Contractors. For access to NBK see section “Access to NBK”.

3.14.1. Contractors that anticipate generating or encountering hazardous waste during the performance of this contract shall attend Site Specific Hazardous Waste Accumulation Area

Operator Training for Contractors, Course HW49 prior to generation of waste. This training is typically held on the third Thursday of each month and is approximately three (3) hours in length. 5-business days prior to training the Contractor shall provide a list of names to the

Receiving Activity’s Point of Contact of those who will be attending the training. The

Receiving Activity’s Point of Contact will coordinate this training with the Shipyard

Environmental, Safety, and Health Office (Code 106.33).

3.14.2. Any welding, burning, flame cutting or grinding occurring at PSNS & IMF or NBK requires a Hot Work Permit and Fire Watch Training. This training is typically held on the third Thursday of each month, is approximately one (1) hour in length, and is provided without charge. 5-business days prior to training the Contractor shall provide a list of names to the Receiving Activity’s Point of Contact of those who will be attending the training. The

Receiving Activity’s Point of Contact will coordinate this training with the Shipyard Fire

Inspector.

3.15. Lifting and rigger services. The use of privately owned cranes, multi-purpose machines, material handling equipment, or other construction equipment that may be used in a crane-like application to lift suspended loads on NBK and PSNS & IMF property by

Contractor personnel is restricted (see NAVFAC P-307 Management of Weight Handling

Equipment for information and forms). Contractors requiring this type of equipment in the performance of this contract shall provide the Receiving Activity’s Point of Contact with sufficient information (crane manufacturer documentation of maximum axle loads in a traveling configuration, crane manufacturer documentation of maximum outrigger loads

(loaded and unloaded), compliance certification, crane certification, operator qualifications, crane wire certification, lifting sketches and designs, loads, locations, time, etc.) at least five

(5) business days prior to equipment arrival for arranging Government inspection services and approvals. The Contractor shall furnish labor and provide all material handling and lifting equipment, rigging support services, and other support equipment (such as cranes, forklifts, Bobcats, man-lifts, etc.) necessary for continuous support of the installation and shall provide qualified personnel to operate it.

3.16. Crane clearance envelope. To allow for the safe travel of overhead traveling cranes, jib cranes, and hoists the Contractor shall not modify existing buildings or place equipment or temporary structures in any way, which would affect the working envelope of overhead traveling cranes, jib cranes, and hoists. Minimum clearances for working envelopes are:

3.16.1. Top clearance. A minimum of three (3) inches between the highest point of the crane and the lowest overhead obstruction must be maintained. In areas where truss sag may become a significant factor, the Government will evaluate the need to increase the minimum clearance.

3.16.2. Side clearance. A minimum of two (2) inches between the end of the crane and side obstructions (building columns, knee braces, walls, etc.), assuming the crane is skewed in the worst case situation on the runway rails or when jib cranes are rotated, shall be maintained.

Piping, electrical conduits, etc. must not reduce this clearance.

3.17. Lift points. The equipment shall be readily liftable via lift points meeting the requirements of this section to allow lifting by crane during equipment off-loading, installation, operation, and removal. Lift points shall be located, designed, and marked per the following to ensure the equipment is readily liftable when it arrives.

3.17.1. Integral (i.e., not bolt-on), lifting point items such as lugs, thru-holes, pad-eyes, trunnions, and ISO container corner fittings are suitable for use at PSNS & IMF.

3.17.2. Removable lift points such as swivel hoist rings, eye bolts, etc., are not preferred for use at PSNS & IMF due to the corrosive environment. To be permitted, the contractor must receive approval from the Receiving Activity POC prior to contract award.

3.17.3. Lift points shall accommodate ASME B30.26 common rigging gear (e.g., shackles, wire rope pendants/grommets, etc.).

3.17.4. Lift point allowable strength shall be based on ASME BTH-1 (latest revision), Category B, Service Class 0.

3.17.5. Welding involved shall comply with applicable AWS Standards.

3.17.6. When possible, to maximize stability, locate lift point(s) symmetrically around, and above, the Center of Gravity (CG), on the same horizontal plane. This helps ensure equal length slings converging to a common point will lift the equipment visually level.

3.17.7. Locate the lift points such that the routing of rigging gear is clear of obstructions.

This is to avoid damaging equipment, chaffing, etc.

3.17.8. The minimum lift point Working Load Limit (WLL) shall be based on the entire weight of the equipment plus 10%. Account for additional loads induced by 45° sling angles with respect to horizontal.

3.17.8.1. Lift points for three- or four-point lifts shall be sized such that any two points carry the entire load based on worse case load distribution with respect to center of gravity.

3.17.8.2. For padeyes, align their primary planes toward the CG so that the slings do not pull out of plane by more than 5°. Exceptions may be acceptable if they are designed to account for the resultant out-of-plane loading.

3.17.8.3. The use of spreaders or strongbacks is not preferred. If spreaders or strongbacks are required, a lift sketch detailing the required spread, capacity and orientation of that gear shall be submitted.

3.17.9. Lift point supporting structures shall be designed to sustain the various loads imparted by the lifting arrangement.

3.17.10. Provide all arrangement drawings, lift sketches, calculations required for the design and usage, and manufacture’s documentation of the lift points. All calculations required for the design of the lift points shall be stamped by a Professional Engineer. A minimum of ten business days is required for Government reviews and approvals of design(s). The

Government will determine if lift sketch labels are required.

3.17.11. When required, lift sketch labels shall be permanently and conspicuously located on the equipment and must be suitable to withstand outdoor, potentially corrosive, environments. Lift sketch labels shall include, at a minimum, the following:

3.17.11.1. The maximum weight of the equipment expressed in pounds.

3.17.11.2. The CG location(s).

3.17.11.3. The lift point locations and their capacity.

3.17.11.4. Recommended minimum sling lengths and capacities.

3.17.12. Permanently label all lift points, or immediately adjacent to them, with the WLL, and test date.

3.17.13. Load test lifting points to 125% (+5%, -0%) of the WLL and hold for at least two (2) minutes. Acceptance criteria shall be: no bending, cracking, or permanent deformation of the lift points or associated structure. The contractor shall perform load tests plus a pre- and post-load visual inspection (VT) in accordance with applicable standards prior to painting.

Documentation of satisfactory results shall be submitted prior to Government acceptance.

3.17.13.1. Alternative to a load test, a magnetic particle testing (MT) of the lift point welds per ASTM E709 is permitted. The acceptance criteria is Section 6.2 of MIL-STD-2035A, or equivalent standard(s) as approved by the government, provided the testing is performed by a certified third party. Documentation of satisfactory results shall be submitted prior to

Government acceptance.

3.18. Arrival of personnel. The Receiving Activity’s Point of Contact shall be notified no less than 48 hours prior to the arrival of Contractor personnel associated with the contract.

3.19. Shipment of materials. Shipment of materials shall be coordinated with site preparation and installation. Material transportation from the manufacturer’s facility to the work site shall be the responsibility of the Contractor. Limited secured storage areas at the receiving activity will not permit the Government to store material for extended periods of time. Early shipment of materials, without the permission of the Receiving Activity’s Point of Contact will be refused.

3.20. Packing material. The use of shredded paper, whether newspaper, office scrap, computer sheets, or wax paper, in packing material for shipment to Navy activities, is prohibited.

3.21. General security requirements. The Contractor shall comply with security regulations imposed by the installation Commander and/or agency occupying the space where the work is to be performed. Access badges/passes and vehicle permits are obtained at Pass & ID (Bldg.

981) from 7:00 am -3:20 pm, Monday through Friday except federal holidays.

3.22. Access to NBK. A Defense Biometric Identification System (DBIDS) card will be issued at the Pass & ID office once the Department of the Navy Local Population I.D. Card/Base

Access Pass Registration form (SECNAV 5512/1) has been processed and a satisfactory background check has been performed. The DBIDS card will allow access to NBK.

3.22.1. A Department of the Navy Local Population I.D. Card/Base Access Pass Registration form (SECNAV 5512/1), provided by the Government, shall be completed by the contractor.

The Contractor shall hand-carry the completed form along with a valid government issued photo identification and proof of United States citizenship to Pass & ID when picking up a badge/pass. Valid proofs of United States citizenship are:

a. Birth Certificate (with a raised state seal)

b. Valid United States Passport

c. Certificate of Citizenship (Form N-560 or Form N-561 issued by the Immigration and Naturalization Service)

d. Certificate of Naturalization (Form N-550 original only)

e. Report of Birth Abroad (Form FS-240)

f. Certificate of Birth (Form FS-545 or Form DS-1350)

g. A document provided that does not contain a photograph, a current state issued photo identification (Driver’s License or Identification Card) shall also be presented

3.22.2. Foreign Nationals shall submit a copy of their valid passport and the Department of the Navy Local Population ID Card/Base Access Pass Registration (SECNAV 5512/1), when submitting the Visitor Badge Request to the Receiving Activity’s Point of Contact. This will allow Immigration and Customs Enforcement (ICE) to complete a background check prior to arrival at NBK.

3.23. Access to the Controlled Industrial Area (CIA). The Contractor shall require access to the Controlled Industrial Area (CIA) of PSNS & IMF and shall be admitted to the work site only after they have been issued a NAVSEA badge from Pass & ID. The NAVSEA badge is separate from the DBIDS card.

3.23.1. Persons who are currently on probation or parole from a felony conviction cannot qualify for a NAVSEA badge and will be denied access to the CIA.

3.23.2. Contractor personnel requiring unescorted entry into the CIA will be required to provide personal background information to the extent necessary to obtain a NAVSEA badge.

3.23.3. A Visitor Badge Request form and Foreign Interest Determination questionnaire shall be completed by the Contractor and submitted to the Receiving Activity’s Point of Contact not less than twenty (20) business days before the badges are needed. Visitor Badge Request forms and Foreign Interest Determination questionnaires submitted less than twenty (20) business days will cause a delay in processing and/or approval.

3.23.4. The Government will issue badges without charge.

3.23.5. Contractors requesting access to the CIA will be required to view an orientation videotape lasting approximately 30 minutes prior to receiving a badge.

3.23.6. Contractor shall allow approximately two (2) hours for each employee to acquire a badge.

3.23.7. Each employee shall visibly display/wear the NAVSEA badge chest high, over the front of their outermost clothing.

3.23.8. It shall be the Contractor’s responsibility to collect and account for all NAVSEA

Badges issued to their personnel upon termination of any employee, expiration of the badge, completion of the contract, or when access is no longer required. When badges, passes, and permits are no longer needed they shall be returned to the Pass and I.D. Office immediately.

3.24. Vehicle permits. Contractors may be allowed to bring contract company registered and insured vehicles into the CIA, based upon the nature of their work, as determined by the

Commanding Officer in conjunction with the Industrial Security Officer. Rental vehicles may also be allowed. Vehicle rental agreements shall be in the name of the contract company and authorized driver. Personally owned vehicles (POVs) are not allowed.

3.24.1. The Contractor shall provide the following, in electronic format, to the Receiving

Activity’s Point of Contact, a minimum of twenty (20) business days business days in advance of when the vehicle pass is needed:

a. Current vehicle registration. The registration shall be in the name of the contract company

b. Current vehicle insurance information. The insurance shall be in the name of the contract company.

3.24.2. Contractors shall clearly display a company sign or logo on each vehicle.

3.24.3. Contractor vehicles are not allowed to enter the CIA with more than three (3) people onboard.

3.24.4. Contractor vehicles shall not travel within the CIA between 4:02 pm and 4:09 pm.

3.24.5. Each Contractor shall provide the state registration, or a photocopy, and proof of insurance documents of each approved vehicle to the Pass and I.D. Office where one of the following Vehicle Permits may be issued:

3.24.5.1. A “lay-down” permit authorizes the vehicle to be brought in to transport tools, parts, or materials to/from the site or function as a work platform. Vehicles with “lay-down” permits are kept at the negotiated job site when not traveling to/from the gate.

3.24.5.2. A “load/unload” permit authorizes the vehicle to be brought in to drop off tools, equipment and machinery (which cannot be hand carried) then is taken out of the CIA.

Vehicles with “load/unload” permits shall not be left unattended at the job site for more than 30 minutes.

3.24.5.3. A “service permit” authorizes the vehicle to be brought in and used as a mobile work platform because it contains tools, parts, materials, supplies and/or fabrication equipment. Vehicles with “service permits” allow the vehicle to be used at job sites throughout the CIA where no negotiated “lay-down” area exists.

4. RESTRICTIONS.

4.1. Regular working hours. All work is to be performed during PSNS & IMF regular work hours from 7:30 a.m. to 4:00 p.m., Monday through Friday, except for Federal Holidays.

Work performed outside of regular working hours requires notification two business days in advance for consideration and approval. Work that disrupts the normal operations of PSNS &

IMF will be required to take place outside of regular working hours/days mentioned above.

Disruptive work may include excavation and movement of equipment through buildings.

4.2. Restricted colors. This Shipyard uses the colors magenta, yellow, red, and blue to identify specially controlled materials. The Contractor is specifically prohibited from using magenta, yellow, red, or blue colored plastic wrapping, packaging materials, bags, tape, or other covering materials.

4.3. Radio restrictions. Operation of privately owned citizens band or amateur radio equipment (receive and transmit) within the geographic limits of PSNS & IMF is prohibited.

All radio equipment installed in privately owned motor vehicles must be turned off upon entering NBK or PSNS & IMF.

4.4. Privately owned personal computers. The use of privately owned personal computers by contractor personnel at PSNS & IMF is restricted. Contractors requiring use of privately owned personal computers in the performance of this contract shall complete an AIS Security

Survey for Computer Equipment. The completed survey shall be returned to the Receiving

Activity’s Point of Contact for processing a minimum of five (5) business days prior to the arrival date. Bluetooth devices, USB thumb drives and double ended USB cables are prohibited.

4.5. Sanitation. PSNS & IMF only allows its employees to consume food in designated eating areas. Hardhats, gloves and any other regulated work clothing shall not be worn, or placed, in designated eating areas. Contract employees shall comply with OSHA 29 CFR 1910

(Sanitation).

4.6. Smoking. Smoking is permitted in a Designated Tobacco Use Area (DTUA) only.

4.7. Sheltering in place. For drills or actual events, Contractors shall shelter in place as required by emergency announcements and personnel. If inside a building, stay inside the building and follow directions from the emergency response team. If outside, enter the nearest building at the designated entrance and remain at the entrance until given direction by the emergency response team. If inside a vehicle, pull off of the road, shut off the engine, exit the vehicle, and enter the nearest building or stay inside the vehicle, secure the heat and air conditioning, and close vents and windows. If shipboard, remain shipboard until notified by emergency personnel.

4.8. Required Speed Limits. The following speed limits shall be adhered to in the CIA:

a. Farragut Ave: 20 MPH

b. All piers, wharves, and dry dock routes: 5 MPH

c. All other streets: 10 MPH

5. PROHIBITED ITEMS AND ACTIVITIES.

5.1. Prohibited Items. Weapons or other dangerous materials, alcoholic beverages, and any other item, the possession of which is prohibited by Federal or Municipal law, Department of

Defense or Department of Navy Instruction, directive and policies, shall not be brought on

NBK or PSNS & IMF property.

5.2. Prohibited photography/recording. Contractor personnel are prohibited from having devices with cameras or activated WI-FI/Bluetooth, tape recorders, zip drives, or other recording devices in their possession while inside PSNS & IMF’s Controlled Industrial Area

(CIA).

5.3. Cellular phones with cameras. Cellular phones with cameras are prohibited at PSNS &

IMF. The use of cellular phones while driving at PSNS & IMF is prohibited.

6. ENVIRONMENTAL SAFETY AND HEALTH

6.1. Environmental, safety and health requirements for PSNS & IMF and NBK.

Contractors shall comply with the Environmental, Safety, and Health requirements for PSNS

& IMF and NBK. The Contractor Guide to Environmental and Safety Compliance is intended to provide Contractor personnel with information regarding environmental, safety, and health issues they may incur during their work at PSNS & IMF and NBK.

6.2. Environmental Compliance. Contractors working at PSNS & IMF are required to perform their work in compliance with all Federal, State, and local regulations pertaining to the environment. Contractors shall ensure all their personnel and their supervisors are familiar with the contents of the Contractor Guide to Environmental and Safety Compliance.

6.3. Environmental Protection. The equipment shall be designed and constructed so that during the operation, service, transportation, and storage conditions described herein the equipment will comply with all applicable Environmental Protection Agency (EPA), Occupational Safety and Health Agency (OSHA) and State of Washington Department Of

Ecology (WDOE) restrictions for materials classified as hazardous to the environment in effect on the date of the contract. The equipment described herein shall not contain or emit material hazardous to the ecological system as prescribed by federal, state and local statutes in effect at

PSNS & IMF.

6.4. Spill Events. A Spill Event is a release involving any unauthorized spilling, leaking, pumping, emitting, emptying, discharging, injecting, escaping, leaching, disposing, or dumping of oil or hazardous substance. There are two types of spill events in the BNC: a non-emergency and an emergency spill event. The following information is provided to ensure all contractor personnel performing work at PSNS & IMF are aware of, and understand, spill events and the proper response for each type of spill event.

6.4.1. Non-Emergency Spill Event. A non-emergency spill event is a discharge of a known material or hazardous substance of ten gallons or less that can be cleaned up by the personnel who discovered the spill and does not pose an immediate threat to human health or the environment. In a non-emergency spill event, the spill material is not released into any waterway inlet (e.g., storm drain) or outside the BNC fence line. The following actions are required in a non-emergency spill event:

a. Stop the source of the spill.

b. Contain the spilled material by keeping the spill away from drains or waterways by blocking off drains located near the spill if there is a chance that the spill will reach them.

c. Clean up the spilled material wearing the proper personal protective equipment.

d. Dispose of the spill debris per designation by Code 106.33. See Waste Management section.

6.4.2. Emergency Spill Event. An emergency spill event is any release of a known or unknown material or hazardous substance which poses an immediate threat to human health or the environment and is not classified as a non-emergency spill event. In these situations, the individual which discovers the spilled material may require assistance from the government. All unpermitted or uncontrolled releases, greater than ten gallons if on land, or any amount to any waterways, or outside BNC properties, are classified as emergency spill events. The following actions are required in an emergency spill event:

a. If you don’t know the properties of the material or it is a threat to human health, evacuate the area and go upwind.

b. Warn others in the area and direct them upwind.

c. Ask someone to watch the area and to warn others away.

d. Call the Regional Dispatch Center (RDC) by dialing “911” from a BNC telephone

(for cellular telephones, call 360-476-3333), and provide the requested information.

e. Return to the spill site and stand by for emergency response personnel.

f. Maintaining a safe distance, try to stop the source of the spill or contain it to prevent it from going into drains or waterways.

g. If you have Safety Data Sheets (SDSs) for the spilled material, provide them to the emergency response personnel.

6.5. Water Pollution Prevention and Best Management Practices (BMPs). In no event shall waste or any other material be disposed of in the storm sewer system.

6.5.1. This system is normally identified with a metal fish tag stating “DO NOT

DISCHARGE - DRAINS TO BAY”.

6.5.2. Discharging to a sanitary sewer drain (e.g., sinks & toilets) is prohibited unless prior authorization has been obtained from the Receiving Activity’s Environmental, Safety, and

Health Department.

6.5.3. The Contractor Guide to Environmental and Safety Compliance pamphlet is available from the Receiving Activity’s Point of Contact upon request. The pamphlet will help explain what types of practices need to be identified and utilized for Contractor activities.

6.5.4. BMP Pollution prevention practices include, but are not limited to: good housekeeping, proper materials storage and handling, drip pans, control of dust and overspray, over water protection, protection of storm drains, and preventative maintenance. For a complete listing of the BMPs see the Contractor Guide to Environmental and Safety Compliance pamphlet.

6.6. Air Pollution Control and Reporting. Containers of paint, epoxy, solvents, or other volatile organic compounds (VOCs) are not to be left open to the atmosphere unless they are being used. All containers are to be secured at the end of each shift. Evaporation of solvents shall not be used as a means of minimizing or disposing of dangerous waste.

6.6.1. Any equipment that emits pollutants to the air (blast equipment, dust collectors, etc.)

must be identified to PSNS & IMF Code 106.3 prior to use on base. Maintenance records demonstrating equipment is in good working order must be kept and copies provided to

PSNS & IMF Code 106.3.

7. HAZARDOUS MATERIALS

7.1. Globally Harmonized System (GHS) Safety Data Sheets (SDS). Offerors and

Contractors shall submit Globally Harmonized System Safety Data Sheets (SDS), whenever the supplies being acquired or supplies used during performance are identified as hazardous materials. Hazardous Materials include any material which, by virtue of its potentially dangerous nature (e.g., toxic, flammable, corrosive, oxidizing, irritating, sensitizing, reactive), requires controls in its use, packaging, handling, storage, or stowage, to assure adequate safety to life and property. This definition is intended to apply to proprietary industrial, commercial, or locally prepared blends, mixtures, formulations, or compounds of gases, liquids, and solids intended for use at the job site. Any other material designated by a Government technical representative as potentially hazardous and requiring safety controls shall also be supplied with a SDS. SDSs shall be available at work sites where materials are being used.

7.2. Contractor Hazardous Material Inventory Request (CHMI). Hazardous materials to be used in the performance of this contract require advance approval by the Government and monthly usage reporting by the Contractor. Prior to arrival and use at NBK or PSNS & IMF, the Contractor shall provide an inventory of all hazardous materials anticipated to be used during the performance of the contract. Hazardous materials shall be listed on a Contractor

Hazardous Material Inventory (CHMI) form. The CHMI form can be obtained from the

Receiving Activity’s Point of Contact.

7.2.1. The Contractor shall provide, in electronic format, the completed CHMI form and the

Globally Harmonized System Safety Data Sheet (SDS) for each item listed on the CHMI.

The SDS shall be not older than five (5) years.

7.2.2. CHMI submittal shall be no less than 10 working days prior to hazardous material being brought on PSNS & IMF to allow review and approval by the Environmental, Safety and Health office. A Receipt and Monthly Usage Form will be issued for all approved hazardous materials.

7.2.3. Each calendar month the contractor shall complete the Receipt and Monthly Usage

Form and return it to the Receiving Activity’s Point of Contact within the first ten (10) business days of the following month. If the Receipt and Monthly Usage Form is not the final submission, the following month’s Receipt and Monthly Usage Form will be sent to the

Contractor.

7.3. Containers. Containers shall have a labeling system to identify the contents of all containers on site, per 29 CFR 1910.1200, Hazard Communications Standard. This shall include as minimum the following:

a. Chemical Name

b. Manufacturer’s Name and Address

c. Explanation of the Chemical Hazard

7.4. Hazardous material exclusions. Supplies being used in the performance of this contract, or materials being provided as part of the equipment shall be free of known hazardous materials. Hazardous materials shall not be brought on site without prior approval from the

Government, Code 106.33. Hazardous materials not needed for this project are prohibited.

Definitions of hazardous materials are specified in the latest version, including revisions adopted during the term of the contract, of Federal Standard No. 313.

7.4.1. Notwithstanding any other hazardous material usage permitted in your contract, materials that contain Asbestos, Acrylonitrile, Arsenic, Beryllium, Mercury, Lead, Methylene Chloride, Cadmium (in a powder or liquid), Isocyanates, Coal Tar, Vinyl

Chloride, and Polychlorinated Biphenyls (PCB) and Chrome VI are prohibited. Also prohibited are radioactive materials and instruments capable of producing ionizing radiation.

7.4.2. Class I or II Ozone Depleting Substances, as defined in 40 CFR Part 82, shall not be used in the performance of this contract, or be provided as part of the equipment.

7.4.3. Exceptions to the prohibition of these materials must be referred to the Contracting

Officer in writing, for consideration within 30 days after contract award and prior to any work being performed.

7.5. Unforeseen hazardous material. If material that may be dangerous to human health upon disturbance is encountered during contract operations the Contractor shall stop that portion of work and immediately notify the Receiving Activity’s Point of Contact. If the situation is an immediate threat to human health or the environment, call 911 on a Shipyard phone or (360)

476-3333 on an outside line or cellular phone.

8. WASTE

8.1. Handling and Disposal of Waste. PSNS & IMF is the owner of all waste (hazardous or otherwise) generated within its facilities. This includes waste generated by contractor personnel while working at PSNS & IMF. All waste that originates or is generated on PSNS

& IMF must be designated and tracked, even if the waste has been designated as non-hazardous. Additional information may be found in the Contractor Guide to Environmental and Safety Compliance.

8.2. Waste identification and designation. Any item or material not incorporated into the project and not reusable will be considered a waste. The Contractor is responsible to identify all waste to be generated or produced by their performance of this contract. They shall complete Section 1 of a Waste Information Sheet (WIS) for each identified waste and submit the WIS to the Receiving Activity’s Point of Contact at least ten (10) business days prior to the generation of that waste. The Government (Code 106.33) will then designate the waste listed on the Waste Information Sheet (WIS). The Government (Code106.33) shall perform any analysis required for designation of waste.

8.3. Waste Management. The Contractor shall be responsible for the following:

8.3.1. Discharge to the storm sewer or sanitary sewer is prohibited without written authorization from Code 106.33 Environmental, Safety, and Health Department via the

Waste Information Sheet (WIS) process.

8.3.2. Solid waste shall be containerized to prevent spills or discharges to the environment.

8.3.3. Cover and contain all solid waste to prevent it from blowing away, to control the spread of waste by rats, birds, raccoons, etc., and to prevent water run-on or run-off. The area around the solid waste collection areas shall be kept clean and free of debris.

8.3.4. Disposal of solid waste shall be in containers specified by Code 106.33

8.4. Hazardous waste (HW).

8.4.1. All waste designated by the Government as Hazardous or Dangerous shall be accumulated in a Contractor operated Satellite Accumulation Area (SAA) or a <90 day

Accumulation Area (AA) that has been certified by C/106.33, or turned over to a

Government operated <90 day AA (for accumulation and disposal) prior to the end of the work shift. All Hazardous or Dangerous Waste shall be accompanied by a processed WIS.

8.4.2. Under no circumstances shall the Contractor remove HW from the Government’s premises. The Government will retain ownership of all HW.

8.4.3. Containers, labels and blank WISs necessary for proper hazardous waste management will be provided by the Government (Shop 99HM). Containers and labels are available for pick-up in Bldg. 367, located in the Controlled Industrial Area (CIA), Monday through

Friday between the hours of 0745-1530. Requests for bulk containers require seven (7) days advance notice.

8.4.4. Hazardous waste containers shall have an ID label (PSNS 5090/82) to identify the type of waste, HW/WSW (PSNS 5090/81 or PSNS 5090/183) label, and DOT label(s) as specified by the WIS.

8.4.5. Designated hazardous and dangerous waste shall be turned over to PSNS & IMF Shop

99 HM with a processed WIS.

8.4.6. The contractor shall provide additional waste data to Shop 99HM as required.

8.5. Non-hazardous waste.

8.5.1. All waste designated by the Government as non-hazardous (e.g. Landfill Controlled or

Solid Waste or Recyclable) shall be properly handled, managed, and disposed of by the

Contractor and tracked with Solid Waste Tracking Sheets (SWTS) and Contractor Monthly

Project Waste Summary Report (CMPWSR). WAC-173-304 Minimum Functional

Standards for Solid Waste Handling.

8.6. Waste Awaiting Designation (WAD).

8.6.1. Waste Awaiting Designation (WAD) (i.e. waste for which designation as hazardous, problem, or non-hazardous waste has not been completed) shall be controlled as hazardous waste per Section 8.4 until proper waste designation and direction has occurred.

8.6.2. All samples and testing for designation will be taken and performed by the

Government.

8.6.3. The Contractor shall apply a completed ID label for each container of WAD. Include the letters “WAD” in the space below the “ID” indicator located on the left side of the ID label. A completed WIS shall be immediately submitted to Code 106.33 via the Receiving

Activity’s Point of Contact to start the waste designation process. A copy of the submitted

WIS shall be kept with the container(s) of waste to be designated.

9. SAFETY OF PERSONNEL AND EQUIPMENT

9.1. Personal safety and health. The proposed work described herein will be performed in an industrial manufacturing area under the guidelines of OSHA and the Receiving Activity’s

Environmental, Safety, and Health Office.

9.1.1. The Contractor shall conduct all work in a safe manner and shall provide all necessary safety equipment during the execution of this contract.

9.1.2. The Contractor shall make the maximum use of low-noise emission equipment as certified by the Environmental Protection Agency. Applicable regulatory requirements for maximum environmental noise levels are per WAC 173-60. The Contractor shall provide hazardous noise signs and label equipment, wherever work procedures and equipment produce sound-pressure levels greater than 84 dB(A) steady state and/or 140 dB peak sound pressure level for impact or impulse noise, regardless of the duration of the exposure.

9.1.3. Contracting personnel shall perform all work in accordance with the latest OSHA rules and regulations issued by the Department of Labor, 29 CFR Parts 1910, 1915, and 1926 as applicable.

9.1.3.1. A Permit is required when entering confined spaces. Permitting shall be accomplished in accordance with 29 CFR 1910.146, Permit-Required Confined Spaces.

Contractors shall be responsible for permitting prior to entering confined spaces.

9.1.4. All contractor personnel shall have in their possession and shall properly wear OSHA approved personnel protective safety equipment (i.e. hard-hats, steel-toe safety shoes, safety glasses and hearing protection).

9.1.5. The Contractor shall provide all appropriate safety barricades, signs, and signal lights required to properly isolate the area of work.

9.1.6. The Contractor’s work space may be inspected periodically for OSHA violations.

9.1.6.1. Abatement of violations will be the responsibility of the Contractor and/or the

Government as determined by the Contracting Officer.

9.1.6.2. The Contractor shall provide assistance to the Environmental, Safety, and Health escort and the federal OSHA inspector if a complaint is filed. Fines levied on the

Contractor by federal OSHA offices due to safety/health violations shall be paid promptly.

9.1.6.3. Failure to comply with, or repeated violations of, OSHA safety requirements can result in the violator(s) losing their access to the Government facility or the operation being suspended until the Contractor can provide properly trained personnel. Certification of training shall be presented upon request by the Environmental, Safety, and Health office.

9.1.6.4. The Contractor shall ensure that any additional measures that the Contracting

Officer or the Receiving Activity’s Point of Contact determines to be necessary for safety are taken.

9.1.7. Additional safety and health requirements shall be as specified in other paragraphs of this contract.

9.2. Fire Hazard Awareness. The Contractor and his/her employees shall know where the fire alarms are located and how to activate them. The Contractor shall handle and store all combustible supplies, materials, waste, and trash in a manner that prevents fires or hazards to persons, facilities, and materials. Contractor employees shall respond to a fire or evacuation alarm.

9.3. Accident Reporting. The Contractor shall submit to the Contracting Officer and/or the

Receiving Activity’s Point of Contact a full written accident report pertaining to all accidents resulting in death, trauma, or occupational disease. Accident reports shall be submitted within

24 hours of the accident occurrence.

9.4. Damage to Government Property. The Contractor shall submit to the Contracting

Officer and/or the Receiving Activity’s Point of Contact a full written report of damage to

Government property or equipment by contractor employees. Damage reports shall be submitted within 24 hours of the occurrence.

9.5. Emergency Medical Care. Report medical emergencies immediately. For prompt medical treatment and ambulance, transport to local area hospitals; dial 911 from a Bremerton

Naval Complex (BNC) phone or from a dial phone 360-476-3333.

File details come from the government source that posted it. Updated .