Attachment 1 - Product Description Gangway and Pier Attachment.pdf
PDF 692 KB Posted
- Attached to
- 55-Foot Aluminum Marine Gangway
- Solicitation number
- H92240-20-R-0007
- Issued by
-
United States Special Operations Command
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Question Spreadsheet.xlsx | XLSX spreadsheet | |
| H92240-20-R-0007.pdf | ||
| Attachment 3 - Past Performance Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ver: JAN 2020
Product Description and Performance Work Statement
Naval Special Warfare Command
Pier 4E Gangway Fabrication and Installation
1.0 OBJECTIVE
1.1 The purpose of the project is to upgrade an existing pier by purchasing a 55-foot perforated aluminum gangway that will connect the existing floating landing area and floating dock (in the form of finger piers) system to the shore in order to safely expedite unloading of personnel and equipment from the floating dock system. The purchased gangway system will be fabricated and installed by the contractor on the east side of Pier 4.
2.0 BACKGROUND
2.1 Currently the only method to load and/or unload from the existing floating dock system located on the east side of Pier 4 is through the use of ladders that are connected to the Pier. A new egress system is required to allow the safe and timely loading and/or unloading of personnel and equipment onto the floating dock system.
3.0 DESCRIPTION OF REQUIREMENT
3.1 The contractor shall provide labor, material, equipment, transportation, and supervision including possible design requirements to procure and install marine grade, perforated aluminum gangway for NAB Pier 4 in place and ready for use.
3.2 A pre-proposal site visit will be scheduled during solicitation to allow prospective vendors the opportunity to inspect the site and obtain the information necessary to prepare a quote. Access will be limited to two persons per vendor.
3.3 All proposals submitted for consideration shall include a set of drawings of the proposed gangway. Drawings shall include a material list describing the type/grade/thickness of material being used. All costs associated with producing drawings are not reimbursable and shall be the sole responsibility of the
Contractor.
3.4 Specifications and Quantities
3.4.1 Contractor provided final drawings shall be approved by the NSW Staff
Civil Engineer prior to commencement of work.
3.4.2 Procure and install one 55 foot long marine grade aluminum gangway similar in design and fabrication to the example illustrated in the attached photos. Gangway shall be 5 foot wide with handrails that are 4 foot in height. Weight bearing capacity of the gangway should be no less than 50 pounds per square foot.
3.4.3 Gangway shall be constructed to allow light to pass through
3.4.4 Specific location for installation will be provided at the pre-proposal site visit.
3.4.5 Structural member for the gangway that is connected to the pier shall be heavy galvanized metal.
3.4.6 All solid sheets parts (i.e. steps, thread, etc.), shall be diamond plate.
Ver: May 2013
3.4.7 Provide and install required roller plate to be attached to existing plastic floating pier.
3.4.8 Provide and install all required structural members.
3.4.9 No alteration of the existing pier or any part of the government facility is allowed
3.5 Installation
3.5.1 Contractor shall be responsible to coordinate with Requiring Activity personnel to identify a lay-down area, if required.
3.5.2 Contractor shall be responsible for removal of all debris and objects not remaining as part of the finished installation.
3.5.3 Contractor shall not damage existing structure of Pier 4 or surrounding landscapes. Contractor shall be responsible for all necessary repairs at their expense for any damage that occurs.
3.5.4 The NSW Staff Civil Engineer will inspect the finished gangway and installation to determine acceptability prior to contract closure.
3.6 Post Award Conference
3.6.1 A post award conference will be scheduled prior to commencement of work to coordinate the requirements and schedule.
3.6.2 The Contractor shall provide a written summary of the Post-Award
Conference.
4.0 DELIVERY INFORMATION.
4.1 Required delivery date: 30SEP2020
4.2 Delivery POC Name: LT Chaka Hazelwood
4.3 Delivery POC Phone Number: 619-437-0955
4.4 Delivery POC Email: chaka.a.hazelwood.mil@socom.mil
4.5 Delivery address: 3632 Guadalcanal Rd San Diego CA 92155
4.6 Special instructions: None
5.0 SECURITY
5.1 Base access will be required.
5.2 Contractor may be required to enroll in RAPIDGate in order to access the base.
6.0 QUALITY ASSURANCE
6.1 The Government reserves the right to perform inspections and surveillance to evaluate the Contractor’s compliance to the contract terms to include proper delivery of quantity and type of goods. The Government will make every effort to ensure that the surveillance methods used are conducted in an objective, fair, and consistent manner.
Attachment A: NAB Pier Photos
Attachment A
NAB Pier Photos
Pier 4: Looking north
Pier 4: Looking south
Pier 4: Looking southwest
Pier 6: Sample Pier attachment (looking from the north)
Pier 6: Sample Pier attachment (looking from the south)