This document is a Request for Information (RFI) regarding the potential use of a Project Labor Agreement (PLA) for a federal construction project. The project involves the construction of a maintenance and operations complex for the 10th Marines at Marine Corps Base (MCB) Camp Lejeune in North Carolina, with an anticipated construction cost between $25,000,000 and $100,000,000. The Naval Facilities Engineering Command (NAVFAC) Mid-Atlantic is seeking feedback from the public on the use of a PLA for this project, which is required for large-scale federal construction projects over $35 million. The RFI includes a questionnaire asking for information on the respondent's involvement, the availability of union and non-union labor, interest in participating, and potential impacts of a PLA requirement. Responses to the questionnaire are due by November 12, 2024, and will be used for planning purposes only, without a solicitation or contract award resulting from this RFI.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT LABOR AGREEMENT (PLA) REQUEST FOR INFORMATION (RFI) FOR CONSTRUCTION PROJECT FOR P1556 10TH MARINES MAINTENANCE AND OPERATIONS COMPLEX, MARINE CORPS BASE (MCB) CAMP LEJEUNE IN THE STATE OF NORTH CAROLINA

PLA Questionnaire

Questions
Responses

1) Are you responding as a representative of a government entity, union, contractor (union or non-union) and/or qualified small business?

2) Would the work involve specialized construction that is available from only a limited number of contractors or subcontractors? Explain in detail.

3) What is your understanding of the availability of union labor and non-union labor in this area for this type of project? Are you otherwise aware of national, regional, or local interest in participating in this project by union or non-union contractors. Explain in detail.

4) As a qualified contractor for a project of this type, would you be interested in participating in this project?

Would the requirement of a Project Labor Agreement (PLA) under this project impact your interest in any way? Explain in detail.

5) Are you aware of PLAs having been used on other similar construction projects in the area and/or other nearby areas? Explain in detail.

6) How do union wage rates compare to prevailing wage rates for this type of project and in this area, i.e., prevailing wage rates under the Construction Wage Rates Requirements statute (formerly known as the Davis-Bacon Act). Explain in detail.

7) Are there any ways in which the requirement of a PLA might increase costs on a project of this type in this area? Explain in detail.

Attachment (1) Rev.1 January 26, 2024 1