This document is a performance work statement and solicitation for the repair of two irrigation wells at the Roman L. Hurska U.S. Meat Animal Research Center in Clay Center, Nebraska. The contractor shall provide all tools, equipment, parts and labor to repair wells 24D and 13D by April 15, 2024 according to the specifications provided. Well 24D pumps 800 GPM with an 8" column, 170' of column pipe, a 2 1/2" column shaft, a 4 stage 12 EML Flowserve pump, a depth of 195' and a water level of 95' set at 110'. Well 13D also pumps 800 GPM with an 8" column, 170' of column pipe, a 2 1/2" column shaft, a 4 stage 12 EMM Flowserve pump, a depth of 195' and a water level of 80' set at 110'. Quotes are due by February 29, 2024 and the Agricultural Research Service, Plains Area, Department of Agriculture intends to award a firm fixed price purchase order to the responsible offeror providing the most advantageous technical acceptance, past performance and price.

View the file

Other files for this federal contract opportunity

Other files attached to Repairs Wells 24D & 13D, newest first.
File Type Posted
Sol_12805B24Q0117.pdf PDF
Attachment 3 - Bid Schedule.docx DOCX document
Attachment 2 - Wage Determination 2015-5357.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1_- Performance Work Statement

Repair Wells 24D & 13D

1.0 Background and Purpose:

Scientists at the Roman L. Hurska U.S. Meat Animal Research Center (USMARC) are developing scientific information and new technologies to solve high priority problems for the U.S. beef, swine, and sheep industries. As part of the effort, they require the use of irrigation wells to aid in the production of roughage and other feeds to sustain the livestock that live at USMARC. Two of the irrigation wells are in need of repairs to be able to be used in the coming growing season.

CONTRACTOR REQUIREMENTS

2.0 Technical Requirements/Tasks:

· The Contractor shall provide all tools, equipment, parts, and labor to perform the work as herein specified on each of the irrigation wells.

· The Repair of two (2) irrigation wells per the bid schedules are listed on attachment 3.

· Contactor shall be in touch with Government Point of Contact to schedule a time to conduct work.

· Working hours shall be in the time frame of 7:00 am- 5:00 pm on the dates discussed with the Government Point of Contact.

· If components not listed in bid schedule are found to be defective, they shall be brought to the attention of the Government Point of Contact.

· Contractor shall operate well at operating speed to prove correct operation of the well before the work is marked as complete, the intended operation level is provided for each of the wells and is located below.

· Items replaced on the well shall be removed by the contractor at completion of the work.

SEE ATTACHMENT 3 – BID SCHEDULE FOR SPECIFICS

· 24D Irrigation well is intended to pump 800 GPM. It is required for the well to continue to operate at this output. The column is 8”, there is 170’ of column pipe, the column shaft is 2 1/2", the pump is a 4 stage 12 EML Flowserve. Well depth is 195' and the water level is approximately 95', with the pumping depth set at 110’.

SEE ATTACHMENT 3 – BID SCHEDULE FOR SPECIFICS

· 13D Irrigation well is intended to pump 800 GPM. It is required for the well to continue to operate at this output. The column is 8”, there is 170’ of column pipe, the column shaft is 2 1/2", the pump is a 4 stage 12 EMM Flowserve. Well depth is 195' and the water level is approximately 80', with the pumping depth set at 110’.

3.0 Deliverable/Schedule/Address:

· Period of Performance:

Work must be completed by April 15, 2024

· Place of Performance:

USMARC

844 Road 313

Clay Center, NE 68933