This Statement of Work (SOW) details a construction project for the re-habitation of Building 720 at Fort Bragg, North Carolina. The project requires comprehensive renovation of the administrative area, including demolition and replacement of ceiling tiles, removal of wallpaper, wall patching and painting, deep cleaning for mold, and updating electrical and plumbing systems. Specific architectural work involves removing and returning furniture, replacing acoustic tiles, applying plaster finishes, installing new baseboards, and steam cleaning carpets and tiles.
The project has several key requirements: all contractor personnel must be U.S. citizens, work will be performed between 7:30 AM - 4:00 PM Monday through Friday, and the contractor must provide a minimum one-year warranty on materials and workmanship. The project scope mandates compliance with multiple federal, state, and military regulations, including UFC standards, OSHA guidelines, and Fort Bragg Installation Design Guide. The total project timeline is not to exceed 60 days from demolition to completion, with a kick-off meeting required within one week of purchase order award. The contract is being managed by the 43d AMOG Business Office, with a project number of P2-00010-25 and a document status date of 22MAR2025.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Project Location: Ft. Bragg, North Carolina
Contract Type: Construction
Project Description: Re-Habitation of Building 720
Project Number: P2-00010-25
Document Status: 22MAR2025
Prepared By: 43d AMOG, Business Office
Re-habitation of Building, 720 P2-00010-25
STATEMENT OF WORK
22 March 2025
NOTE: ONLY CHECKED BOXES APPLY
1. Request for Construction Services: P2-00010-25, Rehabitation of Building 720,
2. Description of Work: Furnish all labor, material, equipment, incidentals, supervision, and transportation for work necessary for restoration of building 720. All work shall be performed in accordance with the purchase order specifications, manufacturer’s recommendations, and UFC 1-200-01 and UFC 1-200-02. Work performed under this purchase order shall comply with the latest edition of all required publications, Federal, Department of the Army, State of North Carolina, and Fort Bragg construction safety and environmental protection laws, regulations, rules, and codes (i.e. American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE), ASTM International (ASTM), U.S. Department of Defense (DOD), U.S. Environmental Protection Agency (EPA), etc.) and the Fort Bragg Installation Design Guide (IDG), dated at the time of the purchase order award. When a required publication is not specifically referenced in the purchase order, the contractor shall utilize one that has national applications. Where conflicts arise between publications, the most stringent requirements shall apply.
3. AT/OPSEC Requirements: See Appendix M
Access, General Protection, and Security Policy and Procedures.
Contractor and all associated subcontractor employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this purchase order, should the Force Protection Condition (FPCON) at any installation or individual facility change, the Government may require changes in contractor security matters or processes.
iWATCH Training.
The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 5 calendar days of purchase order award and within 10 calendar days of new employees commencing performance with the results reported to the COR NLT 15 calendar days after purchase order award. This information is available at the following website: https://www.youtube.com/watch?v=vlzYhQp7fPw
4. Monthly Anticipated Adverse Weather Delay: Workdays Based on 5-Day Work Week.
https://www.youtube.com/watch?v=vlzYhQp7fPw
These days are included in the POP.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
10 9 6 4 4 6 8 7 4 4 5 9
5. Interface with Government Personnel: Access to and from the site shall be coordinated through 43d AMOG. Contractor will coordinate work schedule with designated 43d AMOG COR/inspector.
6. Contractor Requirements:
A. Project Involves Handling of Asbestos or Lead Base Paint.
Record of Survey is provided.
Record of Survey has not been completed.
REC provided: See Appendix L
B. Occupancy During Construction
C. CQC System Requirements
CQC Manager
D. Quality Control System (QCS) Required
E. Submittals are required on the following materials.
All Materials (FIO Approval)
F. After purchase order award:
APP – Accident Prevention Plan (GA Approval)
Contractors shall submit all required submittals, including the APP within 10 calendar days of issuance of the purchase order AWARD.
7. Government Furnished Items/Work: None.
8. Scope of Work: This job includes all labor, materials and equipment required for full performance of the work. The scope of work under this purchase order includes, but is not limited to the following specific items of work:
A. Architectural:
1. Remove existing furniture to the warehouse area of facility prior to demolition, cleaning, and painting. Clean, sanitize, and return furniture to its original position after completion of other actions.
2. Demolish and replace existing ceiling tile in ALL rooms throughout the administrative area. Reference Appendix A highlighted portion of picture; approximately 7400 sq ft in highlighted portion in picture 1 will be referred to as administrative area. Actual dimensions and measurements are to be verified by contractor.
3. Demolish and remove ALL wallpaper in entire administrative areas.
Remove any loose coating or paper attached to walls. The contractor shall not remove or damage any moldings.
4. Patch and paint all existing walls and door frames to match existing in accordance with IDG.
5. Tighten all door locks to usable conditions
6. Deep clean entire admin area for mold. After removing all ceiling tile and all wallpaper, open all doors interior to the admin area, seal all door leading out of the administrative areas, and fumigate entire admin area with bleach agent for not less than 24 continuous hours to kill all mold bacteria and spores. Ventilate for 24 hours before re-occupation.
7. Replace all acoustic tiles with like tile currently in place.
8. Apply plaster skip trowel level 5 finish to drywall, and paint all surfaces ICW whole building design guide, and comply with all UFC requirements. Refence Fort Bragg DPW for approved paint colors. Must follow paint manufacturers specification for lighting while applying coating to ensure no defects, holidays, or uneven tones.
9. Apply new 4.5 in base to match existing in accordance with IDG to entire administrative area after painting is completed.
10. Steam clean of all carpet in the administrative area once interior work is completed.
11. Clean Ventilation system and coil units on all Air handling systems, cooling and heating coils, serving the administrative area.
12. Steam clean tile in bathrooms after completion of plumbing specified in paragraph 8, B.
B. Plumbing:
1. Demolish and replace existing faucets in Men’s and Women’s bathroom to match existing in accordance with IDG (4 in total).
2. Demolish and replace shower heads and control valves to match existing in accordance with IDG in the Men’s and Women’s showers (2 in total). Replace with water efficient valves and shower heads.
3. All plumbing fixtures shall be WaterSense labeled. A minimum of
20% water reduction shall be obtained.
4. Roto clean the drain line from the building to the curb to ensure proper water flow.
5. Replace service sink faucet in closet to match existing in accordance with IDG.
C. Electrical:
1. Demolish and replace existing lighting in all admin areas. Install new surface mounted 2’x 4’ LED fixtures.
2. Install new duplex receptacles and face plates to match existing in accordance with IDG in entire administrative area.
D. Contractor is responsible to verify all measurements and conditions pre-bid. The Government intends to only hold one official site visit. Requests for additional site access must go through the 763 ESS/OL-Pope Contracting Squadron (763 ESS) point of contact (POC) listed in the Request for Proposal. Any additional site access will be made available to all Contractors solicited for this project.
Acceptance of the purchase order shall constitute acceptance of the existing conditions. The contractor shall: protect existing, in-place, and new work, always provide adequate protection for persons and property, and execute the work in such a manner to avoid any hazard to persons and property as necessary.
E. The government referenced details indicate the general extent of the work. The references are not intended to indicate or describe all work required for the full performance and completion of the requirements of the job.
F. Kick-off Meeting: Contractor shall schedule a kick-off meeting to occur within one week of purchase order award. Representatives in attendance shall at a minimum include contractor project manager, contractor engineer or technical representative, contracting officer representative and customer facility manager.
G. Contractor shall provide timeline to completion during the RFQ phase; and shall adhere to schedule given, not to exceed 60 days from demolition to completion.
H. All materials shall be on hand before any work commences.
9. ADDITIONAL ENCLOSURES: It is the responsibility of the contractor to ensure they are in receipt of and have reviewed all appendices prior to award.
A. Appendix A
10. DISPOSAL OF WASTE: Loose debris on trucks leaving the site shall be loaded in a manner that shall prevent losing or dropping of materials on streets and conform to local ordinances/ laws. Fasten suitable cover, such as a tarpaulin, over the load before entering surrounding streets. The Contractor shall be responsible for cleaning up any materials that fall from trucks and held liable for any resulting damages. The Contractor is solely responsible for spillage from its vehicles, and such spillage shall be cleaned up immediately. The Contractor shall report all spills to the Fort Bragg Fire Department 910.432.0911 or 911. For the duration of this purchase order and on a daily basis, the Contractor shall remove from all roads and / or streets asphalt, mud, soil, rocks, trash, and debris that result from its operations. All roads and / or streets affected shall be cleaned before close of business on the day affected.
Contractor is also responsible for restoring the site/grounds back to its original condition.
Grass/soil must be restored to its original condition.
• Contractor shall submit all trip tickets from the off-post landfill facility to the
COR/ACOR within three working days to show all debris is being land-filled in accordance with all Federal requirements and in an approved location.
• The Contracting Officer (CO) will determine if materials removed from and not reused in the project are salvageable or unsalvageable. Salvageable materials shall be disposed of as directed by the CO. When material is designated as unsalvageable, the material from that point shall become the property of the Contractor.
• The Fort Bragg Lamont Construction and Demolition (C&D) Landfill is closed and is not accepting any C&D Waste or Asbestos Waste. The Municipal Solid Waste (MSW) Transfer Station at the Lamont Landfill Facility is closed and is not accepting MSW at the facility.
• All contractors shall use a State Certified C&D Landfill or Subtitle “D” Landfill outside
Department of Defense land for the disposal of C&D waste, asbestos waste, and MSW.
The contractor shall maintain data of all waste disposed (C&D and MSW) and all materials recycled in execution of a purchase order. The Department of the Army (DA) and the North Carolina Department of Environmental Quality (NCDEQ) requires monthly and annual reporting of all materials (waste and recyclables) managed by Fort Bragg. The Fort Bragg Environmental Compliance Branch, Solid Waste/Recycling Office is responsible for compiling data into monthly Directorate Reports to be consolidated into reports for DA and NCDEQ. A form from the Solid Waste/Recycling Office or a Contractor form shall be completed by the Contractor with the type of waste or recycled material, the weight of the waste/material (tons or pounds), and the certified facility accepting the waste/material. This information shall be submitted to Fort Bragg Solid Waste/Recycling Office no later than the second Friday of each month. Information can be submitted in person or by fax (910.396.4188). Phone number is 910-396-3372.
• All recyclable materials generated during execution is Government property unless the purchase order specifies that the Contractor can obtain the materials. State Law and Fort Bragg regulations requires covering of loads of waste or recyclables to prevent litter. All waste and recyclable material loads are subject to be inspected of their contents while on Department of Defense land. The Lamont Landfill Facility Recycling Area will accept specific recyclable items as indicated below.
• Concrete, Brick, Block and Asphalt: tested and free of asbestos and lead based paint to be recycled; no larger than 2 feet by 2 feet pieces or equivalent; minimal amount of dirt in load; no rebar protruding out of the concrete.
• Trees, Limbs, and Stumps: 6 feet or less in length for diameter < 3 feet; 3 feet or less in length for diameter => 3 feet; minimal amount of dirt in load and in stump roots; ground wood chips accepted; no trash in load.
• Pallets: serviceable and non-serviceable.
• Steel and Aluminum: no items requiring demilitarization; no items containing or coated with liquid.
• Cardboard: clean of trash, plastic, styrofoam, wood, metal, etc.; 40 cubic yard dumpster available for material; alternate acceptance location at Fort Bragg Recycling Center (Building 3-1240, DPW Compound at Butner Road / Reilly Road intersection).
11. AVAILABILITY AND USE OF UTILITY SERVICES: Utility services are available on site (power and water) for accomplishment of the work required. Any additional utility services will be furnished at an additional cost to the Contractor.
The Government will make no connections or alterations to the existing utility systems for the Contractor. Utilities for offices and/or storage buildings or areas will be billed to the Contractor monthly and will not be furnished free of charge. The Contractor shall be responsible for installing meters or other connections at no cost to the Government. At the conclusion of the purchase order, the Contractor shall remove all temporary connections, distribution lines, meters and associated paraphernalia unless otherwise notified by the COR.
Prior to installing any utility connections at an office/storage site, the plan will be approved by the COR. When utility meters are installed, the Contractor shall notify the COR for the initial meter reading. Failure to obtain this initial reading will result in the Contractor being charged for the entire amount shown on the meter.
12. CONTRACTOR STORAGE AND TRAILERS: The Contractor shall place or paint a sign on all storage trailer(s) and building(s) used on this purchase order. At a minimum, the sign shall contain the name of the Contractor and a telephone number at which the contractor can be reached. The trailer(s) and building(s) shall be completed with gates and/or doors which can be locked. Only material for this project shall be stored in the trailer(s) or building(s). The Contractor shall remove the storage trailer(s) or building(s) within 30 days after completion of the purchase order and prior to submitting his final invoice. The area around the storage trailer(s) and building(s) shall be kept clean.
13. SAFETY: Safety will follow the Corps of Engineers Safety Manual EM 385-1-1. Use of appropriate safety equipment is mandatory and not limited to hard hats and steel-toed shoes.
Contractor is responsible for daily clean up and complete restoration of the area once the purchase order is complete. Additional safety references to be followed include:
a. 29 CFR 1910, OSHA General Industry Standard
b. 29 CFR 1926, OSHA Interim Construction Standard
c. DA Pamphlet 385-10, The Army Safety Program
d. Fort Bragg Regulation 385-10, Fort Bragg Safety Program
14. CONTRACTOR’S PERSONNEL
• Contractor personnel performing work under this purchase order shall be U.S. citizens unless the provisions of Army Regulation 25-2, Information Assurance have been fully completed and approval has been granted by the Government for the non-U.S. citizen to perform the required support.
• Contractor personnel performing work under this purchase order shall be able to read, write, speak, and understand the English language to effectively carry out all purchase order requirements. They shall have a command of both the written and spoken English language to communicate in person properly, clearly, and effectively or via electronic devices (telephone or Email) with co-workers, customers, and the general public.
• Contractor personnel must act as guests on the installation, which they are. Employees are expected to be always on the job site. In the event a contractor employee’s conduct is unsatisfactory, the foreman/supervisor is expected to handle the situation accordingly and in a timely manner.
15. HOURS OF WORK: Work shall be accomplished between the hours of 7:30 AM - 4:00 PM, Monday through Friday. No work will be done on weekends or federal holidays without prior approval from the Contracting Officer. Legal holidays falling on Saturday are observed on the proceeding Friday and those falling on Sunday are observed on the following Monday. Work schedule and facility security to be coordinated with the Contracting Officer Representative (COR) or Quality Assurance (QA) personnel for facility access and security maintenance during duration of work. Contractor shall not work outside of the stated hours of work, without first obtaining approval from the COR or QA personnel.
16. WARRANTY: The contractor shall provide a minimum of one (1) year warranty on all materials and workmanship from the date of the Government’s acceptance of the work.
17. PHOTOGRAPHY: Photography on Fort Bragg is regulated/restricted. All contractors needing to photograph as part of their work must gain approval from Shane Woodmancy at shane.r.woodmancy.civ@army.mil (910) 908-1086 or Don Mollett at donald.l.mollett.civ@army.mil (910) 907-5293 for Ft. Bragg, Simmons Army Airfield and Pope Army Field, prior to taking photographs. Tag geolocation data and other metadata must be turned off.
END OF STATEMENT OF WORK
22 March 2025