Attachment 1 MTA HVAC Replacement Supplemental Specifications.pdf
PDF 10 MB Posted
- Attached to
- Mt. Adams HVAC Replacement Federal contract opportunity
- Solicitation number
- 1240BH24Q0010
About this file
This document is the Attachment 1 MTA HVAC Replacement Supplemental Specifications for the Mt. Adams HVAC Replacement solicitation, Solicitation Number 1240BH24Q0010.
The solicitation is being issued by the Department of Agriculture Forest Service R6-Pacific Northwest Region for the replacement of the HVAC system at the Mt. Adams facility. The solicitation requires quotes to be submitted by April 26, 2024 at 5:00 PM. The supplemental specifications provide detailed technical requirements for the HVAC system replacement, including performance standards, product specifications, and installation guidelines. Key requirements include energy efficient equipment, proper ventilation, and a comprehensive maintenance plan. No specific award date is provided. This is a standard solicitation for services, and does not appear to have any set-asides or incumbent information.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1240BH24Q0010 Amendment 3.pdf | ||
| Sol_1240BH24Q0010_Amendment_2.pdf | ||
| 1240BH24Q0010 Amendment 1.pdf | ||
| Attachment 4 Wage Determnation WA20240086 01.05.2024.pdf | ||
| Attachment 3 Fire Plan.pdf | ||
| 1240BH24Q0010 Solicitation Package MTA HVAC Replacement.pdf | ||
| Attachment 2 Fire Protection and Suppression.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA Forest Service Project Specifications
February 29, 2024 MTA HVAC Replacement
SPECIFICATIONS
STATEMENT OF WORK
MTA HVAC REPLACEMENT
PART 1 – GENERAL
1.01 Project Summary
1. This contract involves the supply and installation of three (3) HVAC systems at one location; the Mt. Adams Ranger District on the Gifford Pinchot National Forest (NF). The existing HVAC systems in place will need to be removed and disposed of by the contractor.
2. All materials for this project must be energy efficient. Proposed units must have a minimum HSPF (Heating Seasonal Performance Factor) rating of 10.0 or greater.
Work must comply with all applicable Uniform Plumbing Code (UPC), National Sanitation Foundation (NSF), and other applicable regulations. Provide copies of any tests to the Contracting Officer Representative (COR), including a system test prior to use and acceptance of work.
Base Bid Item Building 1018:
Supply and install complete heat pump split system sized in-kind with existing system, to include (not limited to): heat pump, insulated line set, furnace/air handler with aux/emergency heat strips, condensate pump and associated plumbing as necessary, replacement thermostat, removal, and disposal of existing heat pump system. Supply and install an appropriately sized surge protection device to protect all equipment, as necessary.
Contractor to seal all accessible seams (factory and field made) on furnace/air handler and all associated and accessible ductwork with mastic and/or mastic tape.
Contractor to install new filter rack, in accessible location which provides room for filter change outs *existing filter rack blocked, see pictures for detail.
Heat pump and furnace to be installed in existing location.
Optional Bid Item Building 1019:
Supply and install complete heat pump split system, to include (not limited to): heat pump, insulated line set, furnace/air handler with aux/emergency heat strips, condensate pump and associated plumbing as necessary, replacement thermostat.
Supply and install an appropriately sized surge protection device to protect all equipment, as necessary.
Heat pump unit must be installed, centered, on South side of garage (see photo for detail).
Contractor to seal all accessible seams (factory and field made) on furnace/air handler and all associated and accessible ductwork with mastic and/or mastic tape.
Contractor to install new filter rack horizontally, in accessible location which provides room for filter change outs.
Optional Bid Item Building 1014:
Supply and install complete heat pump split system, to include (not limited to): heat pump, insulated line set, furnace/air handler with aux/emergency heat strips, condensate pump and associated plumbing as necessary, replacement thermostat.
Supply and install an appropriately sized surge protection device to protect all equipment, as necessary.
Heat pump unit must be installed, centered, on South side of garage (see photo for detail).
Contractor to seal all accessible seams (factory and field made) on furnace/air handler and all associated and accessible ductwork with mastic and/or mastic tape.
Contractor to install new filter rack, horizontally, in accessible location which provides room for filter change outs.
The Forest Service is interested in replacing the current systems with new systems that have equal or greater capabilities when compared to the current systems. The brand of systems that are to be provided in this contract, must be manufactured by a familiar brand that is easily serviceable by any local company. The contractor must take the following into consideration when determining the best systems to provide for installation:
Manufacturer warranty.
Parts availability.
Serviceability by local service technicians.
Heating Seasonal Performance Factor (HSPF) rating. (10.0 or greater) Air handler/furnace size, to ensure that the new proposed system can fit in the current available space for the air handler/furnace. *An up flow/downflow retrofit kit is acceptable into existing handler/ductwork.
The heating and cooling system must have the following functional modes: Heat, Cool, Emergency Heat, off.
The fan system must have the following functional modes: Auto, on, off; or similar.
The thermostat system must have 7-day (5+2) programmability and the ability to run off of battery power alone.
The new proposed systems must also be able to connect to the current duct systems, as applicable.
System must use readily available disposable filters of a standard size.
PART 2 – EXECUTION
2.01 Heat Pump Installation
A. The Contractor must be responsible for locating and protecting existing structures and utilities during construction operations. In the event of damage to existing structures or utilities, stop all work associated with the damage, and immediately notify the CO. Repair the damage as directed by the CO at the Contractor’s expense.
B. Notify the COR at least 14 days in advance of any construction operations that will cause disruption or to normal business operations at the District Ranger Station Office.
C. BASE BID: Bldg. 1018. Remove existing furnace and associated equipment.
Recycle as necessary. Install a completely new HVAC system and any associated replacement lines and hardware. Work will include a new programable thermostat.
D. OPTION ITEMS: #1: Bldg. 1019. Remove existing furnace and associated equipment. Recycle as necessary. Install a completely new HVAC system and any associated replacement lines and hardware. Work will include a new programable thermostat. #2: Bldg. 1014. Remove existing furnace and associated equipment.
Recycle as necessary. Install a completely new HVAC system and any associated replacement lines and hardware. Work will include a new programable thermostat
E. Any modification of items, designs, materials, products, or equipment (including Government-Furnished property), made necessary because of substitution, will be the responsibility of the Contractor without adjustment in the contract price or time.
The Contracting Officer Representative’s (COR) approval of any substitute will not affect the Contractor's responsibility for such modification. All substitutions will be requested by the Contractor after the award of the contract has been made. No approvals will be made prior to the award.
F. Equipment supplied under this contract must have the manufacturer’s standard warranties. Warranties on equipment must be provided, in writing, directly to the Government.
G. Submit manufacturer’s product information on all materials being used prior to installation. Allow 14 days for approval.
Include the following information in submittals:
1. Contract Name and Number.
2. Date.
3. Name of Contractor.
4. Name of firm or entity that prepared the submittal.
5. Names of subcontractor, manufacturer, and supplier.
6. Submittal purpose and description.
7. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
8. Submittal and transmittal distribution record.
9. Other necessary identification.
10. Remarks.
2.02 Job Site Cleaning
The contractor must clean up the job site and remove all old furnace parts from the site to recycle as necessary.
PART 3 – MEASUREMENT AND PAYMENT
3.01 Method of Measurement
The price and payment must constitute full compensation for furnishing and hauling all necessary materials to the project site, for proper disposal of all waste materials, and for furnishing all labor, tools, equipment, and incidentals necessary to complete the project as specified.
3.02 Measurement and Payment
Method of Measurement
A. Install new fan coil unit, heat pump, thermostat, and wiring as needed.
B. Measurement will be a lump sum. Includes removal of existing furnaces, installation of new fan coil unit, heat pump, pad, programable thermostat, heat strips, breakers, filter media cabinet, and systems testing, as applicable to furnished unit.
Basis of Payment
A. Payment will be at the Contract Pay Unit Price for each item as designated below.
B. Payment will be made under:
Pay item Description Pay Unit
0001 Ducted Heat Pump System - Bldg. #1018 LS
0002 Ducted Heat Pump System - Bldg. #1019 LS
0003 Ducted Heat Pump System - Bldg. #1014 LS
END OF SECTION
PART 4 – RESIDENT PHOTOS OF UNITS
Driveway parking available at and adjacent to each building project site.
Building 1018 Southwest Elevation
Existing heat pump on riser, located on West side of building.
Existing riser/stand and concrete pad.
40 amp Fused disconnect.
Square D Panel
Square D Panel served by 200A main disconnect
6 AWG stranded copper THHN Furnace OCP breakers 18/20 and 22/24.
Basement entrance
Furnace/Air handler. Excess materials to be cleared prior to work commencement. Note sheet metal/joist bay return plenum overhead and lack of mastic/sealant.
14” diameter return air plenums.
Condensate pump, plumbed with clear vinyl hose running parallel w/joists through North side rim joist to exterior.
Note: existing filter rack location and prior photo proximity to floor post. (see next photo) Existing filter rack as noted in section C-4.
Building 1019 Southeast Elevation. *40amp service/disconnect will be installed by USFS, Heat
Pump to be installed, centered, on South Side of building
Bldg. 1019 South Elevation and Heat Pump install location.
1019 Furnace 50A and 60A DP Breakers.
1019 Furnace/Handler in central HVAC closet. Return air above, supply ductwork in crawlspace.
30" Door Opening
1019 Furnace data plate.
Heat Pump Location
BLDG. 1014
Bldg. 1014 South Elevation and Heat Pump install location.
1014 Furnace 50A and 60A DP Breakers.
1014 Furnace/Handler in central HVAC closet. Return air above, supply ductwork in crawlspace
30” Door Width
1014 Furnace data plate.
File details come from the government source that posted it. Updated .