Attachment 1 Mongolia_SOW_2 MAR.pdf

PDF 540 KB Posted

Attached to
Gravity and GPS Data Collection in Mongolia
Solicitation number
HM157520R0007
Issued by

View the file

Other files

File Type Posted
Q and As.pdf PDF
Attachment 2 Addendum to 52.212-1(b).pdf PDF
Attachment 3 FAR 52.212-2.pdf PDF
HM157520R0007.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

1 | P a g e

GRAVITY AND GPS DATA COLLECTION

IN MONGOLIA

Statement of Work (SOW)

2 March 2020

2 | P a g e

1.0 PURPOSE & BACKGROUND

The purpose of this contract is to perform a terrestrial gravity survey in the country of Mongolia to tie into existing holdings for the National Geospatial-Intelligence Agency (NGA). NGA has a mission-critical need for gravity data over the country of Mongolia. Specifically, terrestrial data is needed as a high-resolution data set for our Earth Gravity Model.

2.0 SCOPE OF WORK

2.1 BASE YEAR

1.) The Contractor shall survey a minimum of 750 new gravity stations inside Mongolia.

2.) The Contractor shall survey at a 5 km spacing along an approximately 1000 km section of the

Mongolian-Chinese border. The Minimum Bounding Rectangle (MBR) is defined by a box whose corners are Latitude 49.86 Longitude 114.968 in the northwest, Latitude 46.481 Longitude 114.968 in the southwest, Latiude 49.86 Longitude 120.098 in the northeast, and Latitude 46.481 Longitude

120.098 in the southeast.

3.) The Contractor shall survey to a distance of 25 km from the Chinese border into Mongolia.

4.) The Contractor shall simultaneously collect precise GPS locations and both orthometric and ellipsoidal heights.

5.) The Contractor shall obtain all necessary permissions from the Mongolian government such as the

General Authority of Border Protection Forces and the Ministry of Defense.

2.2 OPTION YEAR ONE

1.) The Contractor shall survey a minimum of 850 new gravity stations inside Mongolia.

2.) The Contractor shall survey at a 5 km spacing along an approximately 1130 km section of the

Mongolian-Chinese border. The MBR is defined by a box whose corners are Latitude 46.557

Longitude 108.57 in the northwest, Latitude 42.382 Longitude 108.57 in the southwest, Latiude

46.557 Longitude 117.478 in the northeast, and Latitude 42.382 Longitude 117.478 in the southeast.

3.) The Contractor shall survey to a distance of 25 km from the Chinese border into Mongolia.

4.) The Contractor shall simultaneously collect precise GPS locations and both orthometric and ellipsoidal heights.

5.) The Contractor shall survey to an accuracy 1mgal or less.

6.) The Contractor shall obtain all necessary permissions from the Mongolian government such as the

General Authority of Border Protection Forces and the Ministry of Defense.

2.3 OPTION YEAR TWO

1.) The Contractor shall survey a minimum of 850 new gravity stations inside Mongolia

3 | P a g e

2.) The Contractor shall survey at a 5 km spacing along an approximately 1146 km section of the

Mongolian-Chinese border. The MBR is defined by a box whose corners are Latitude 43.19

Longitude 96.13 in the northwest, Latitude 41.385 Longitude 96.13 in the southwest, Latiude 43.19

Longitude 108.102 in the northeast, and Latitude 41.385 Longitude 108.102 in the southeast.

3.) The Contractor shall survey to a distance of 25 km from the Chinese border into Mongolia.

4.) The Contractor shall simultaneously collect precise GPS locations and both orthometric and ellipsoidal heights.

5.) The Contractor shall survey to an accuracy 1mgal or less.

6.) The Contractor shall obtain all necessary permissions from the Mongolian government such as the

General Authority of Border Protection Forces and the Ministry of Defense.

3.0 CONTRACTOR DELIVERABLES

3.1 BASE and OY Contract Deliverables

NGA will receive the processed free-air and Bouguer gravity anomalies and orthometric heights in the

WGS 84 Reference System for all points collected in the base and option years listed above. The gravity anomalies shall be accurate to one (1) mgal and the orthometric heights shall be accurate to at least 50

cm. The gravity anomalies shall also be referenced to absolute gravity stations. The data format shall consist of: Latitude, Longitude, Orthometric Height, ellipsoid height, Free-Air Gravity Anomaly, Bouguer

Anomaly as displayed in the Point Gravity Anomaly Data Format Guide Below, and shall be supplied on appropriate electronic media.

POINT GRAVITY ANOMALY DATA FORMAT GUIDE

NAME FORMAT DESCRIPTION

LAT (-)99.99999 Latitude of gravity station in decimal degrees Sign of Lat.: + 0.00000° to 90.00000° North of Equator - 0.00001° to 90.00000° South of Equator LON (-)999.99999 Longitude of gravity station in decimal degrees Sign of Long.: + 0.00000° to 179.99999° East of Prime Meridian - 0.00001° to 180.00000° West of Prime Meridian SOURCE 99999 Data source number OBS_GRAV 9999.999 Observed gravity less 976,000 mgals, to nearest thousandth BA (-)999.999 Bouguer anomaly to nearest thousandth of mgal FA (-)999.999 Free-air anomaly to nearest thousandth of mgal ELEV_TYPE (9),(X) Type Elevation:

Code Description 0 Gridded data 1 Land Surface 2 Land Subsurface 3 Ocean Surface 4 Ocean Submerged 5 Ocean Bottom 6 Lake Surface (Above Sea Level)

4 | P a g e

7 Lake Bottom (Above Sea Level) 8 Lake Bottom (Below Sea Level) 9 Lake Surface (Above Sea Level - Bottom Below) A Lake Surface (Below Sea Level) B Lake Bottom (Surface Below Sea Level) C Ice Cap (Bottom Below Sea Level) D Ice Cap (Bottom Above Sea Level) E Airborne F Incomplete Data ELEV (-)99999.999 Elevation of gravity station in meters, to nearest thousandth. If elev_type = 3, 4, or 5 then ocean depth (-) SUPP ELEV (-)9999.999 Supplemental elevation in meters, to nearest thousandth If elev_type = 2, 4, 6, 7, 8, 9, or B then instrument reading or bottom depth SEQ XXXXX Station sequence or track number S_FA 999 Free-air anomaly estimated accuracy in mgals S_BA 999 Bouguer anomaly estimated accuracy in mgals RBS 9999X DoD RBS site TC_CODE 9 Isostatic anomaly or terrain correction information Code Description 0 No Information on Either 1 Terrain Correction Given 2 Isostatic Anomaly Given 3 Both Quantities Given CC 99, XX, 9X, or X9 Country code

All raw GPS data as well as the GPS solutions of the first-order GPS network extension as with the associated site descriptions and appropriate metadata shall be supplied on appropriate electronic media. The data format for the GPS solutions shall consist of the Latitude, Longitude, and Ellipsoid

Height at each GPS station. Notwithstanding DFARS 252.227-7015(b)(1)(i), (b)(2) and (b)(3), the

Government will have the unrestricted right to use, modify, reproduce, release, perform, display, or disclose technical data, and to permit others to do so.

All deliveries shall be made to NGA within the last month of the current period of performance unless alternate arrangements are made and agreed to between both the service provider and NGA.

3.2 Delivery Methods

Acceptable delivery methods include:

• FTP Transfers

• External Hard Drives

• DVDs

• New delivery formats not yet known will be reviewed and approved by NGA for approval prior to being used

5 | P a g e

The contractor shall ship delivieries to :

NGA

SLM, Mail Stop: L-41 c/o Mr. Brian Gosling

3838 Vogel Road

Arnold, MO 63010-6238

4.0 REPORTS AND MEETINGS

Communication between NGA and the Contractor is essential to achieving success in meeting our mission, conducting business, and advancing our abilities to provide GEOINT to our customers. To achieve this success, the following requirements are included in this SOW.

4.1 Project History Folder

The Contractor shall deliver a project history folder for each requirement. (Similar requirements may be combined and require only one project history folder.) The project history folder shall include all NGA contractual documents, modifications, addendums, and checklists. The Contractor shall state what sources were used to build or improve the FG data holdings and what processes were used to produce the results. The Contractor shall reference the numerical and percentage increase or improvement made. For finished products, the project history folder shall include a description of what data and processes were used to assemble the product. The project history folder shall also include the dates the work was accomplished, the area of interest of the work, project specific guidance, and any peculiarities of the requirement or processes. The folder shall also include an explanation if the project was completed ahead or behind schedule.

In addition to the project history folder, the Contractor shall provide any Quality Assurance documentation. This should include all internal quality assurance error calls and corrective actions, and all quality assurance checklists, as applicable. Final checklists shall indicate zero defects. Any rework and reasons for it shall be addressed.

The project history folder and all additions shall be delivered to the COR as specified herein within fourteen days of delivery of the data, product, or service. Contractor shall provide email notification of delivery shipment to NGA Program Managers and the COR. Exceptions must be coordinated with the

COR. All materials making up the folder and addendums shall utilize standard office business software

(e.g., Microsoft Office.)

5.0 DATA OWNERSHIP

6 | P a g e

All data acquired with this contract will have no less than Government purpose rights in accordance with the definition in DFARS 252.227-7013. The deliverable data, the databases, all database content, and finished products created by the Contractor shall have government purpose rights for a five-year period that shall commence upon execution of the contract. Upon expiration of the five-year period, the

Government shall have unlimited rights in the technical data.

6.0 DATA SECURITY

All data secured through this contract is to be kept at the Unclassified level.

7.0 RISKS AND LIABILITY

The contractor shall assume all risk in connection with the execution of this contract and waive any claim against NGA arising from the performance of the work specified. The contractor shall agree to protect and hold NGA harmless from any claims that may result from injuries to property or person in connection with its work, as well as arising under or relating to any aspect of this agreement.

The contractor shall be responsible for the conduct of its personnel regarding the laws of the host and any other country affecting operations under this contract. The contractor assumes all responsibility for the safety of its contingent.

The contractor shall be responsible for making all agreements with the host and any other country for the use of airport, airfield, or emergency landing fields, and such agreements by the flying organization shall be made without obligation on the part of NGA.