Attachment 1-MAHG231025 Repair Holbrook Manor HVAC B7320 Div I Specs 21MAR26.pdf

PDF 23 MB Posted

Attached to
MAHG231025 Repair Holbrook Manor HVAC, B7320
Solicitation number
FA301026R00032
Issued by

About this file

Summary of MAHG231025 Repair Holbrook Manor HVAC, B7320 Specifications

This document comprises the Division 1 General Requirements and Division 23 Mechanical specifications for the repair of the HVAC system at Holbrook Manor (Building B7320) at Keesler Air Force Base in Biloxi, Mississippi. The project scope includes furnishing all equipment, labor, supervision, and materials to provide and replace Air Handling Units (AHUs) and Variable Air Volume (VAV) boxes for the student dormitory, with a fully operational cooling and heating system integrated into a new Direct Digital Control (DDC) package. The contract period of performance begins 10 calendar days after award and concludes 270 calendar days later, with work phased to allow facility occupancy during construction. The project is estimated between $5,000,000 and $10,000,000.

The specifications require comprehensive submittals including pre-construction quality control plans, shop drawings, product data, and schedules of values prior to work commencement. The contractor must establish a Quality Control (QC) program with a full-time QC Manager meeting minimum qualifications of 10 years combined construction experience and 4 years as a QC Manager, along with a project superintendent with at least 10 years experience and 5 years as superintendent. A Site Safety and Health Officer (SSHO) is required to oversee compliance with EM 385-1-1 safety standards. Critical requirements include coordination with the Facility Manager on phasing, management of occupied spaces, comprehensive testing and balancing (TAB) procedures per AABC and NEBB standards, and final commissioning with performance verification testing. All DDC hardware must be BACnet-compliant, BTL-listed, and capable of interoperable communication using standard ASHRAE 135 protocols. The contractor must also provide operation and maintenance manuals, training for four operating staff members (32 hours minimum), warranty management, and one year of maintenance and service following project acceptance.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAHG231025

PROJECT:

Repair Holbrook Manor, HVAC, B7320

PROJECT NUMBER:

MAHG231025

KEESLER AIR FORCE BASE

BILOXI, MISSISSIPPI

508 L Street

Keesler AFB, MS 39534

Attachment 1

FA301026R000

MAH G231025

INDEX

SECTION DESCRIPTION

01 11 00 Summary of Work

01 14 00 Work Restrictions

01 30 00 Administrative Requirements

01 32 01.00 10 Project Schedule

01 33 00 Submittal Procedures

01 35 26 Governmental Safety Requirements

01 42 00 Sources for Reference Publications

01 45 00 Quality Control

01 58 00 Project Identification

01 78 00 Closeout Submittals

01 78 23 Operation and Maintenance Data

07 92 00 Joint Sealants

09 25 50 Gypsum Board Assemblies

09 51 10 Acoustical Panel Ceilings

09 91 00 Paint

22 00 00 General Plumbing

23 03 00.00 20 Basic Mechanical Materials and Methods

23 05 93 Testing Adjusting and Balancing for HVAC

23 07 00 Thermal Insulation for Mechanical Systems

23 09 00 Instrumentation and Control for HVAC

23 09 13 Instrumentation and Control Devices for HVAC

23 09 23.02 BACNET Direct Digital Control for HVAC and other Building Control Systems

23 30 00 HVAC Air Distribution

23 31 13.00 40 Metal Ducts

23 73 13.00 40 Modular Indoor Central Station Air Handling Units

Attachment 2

FA301026R0003

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

02/24, CHG 1: 05/25

PART 1 GENERAL

1.1 ACRONYMS/DEFINITIONS

ACM Asbestos Containing Material AF Air Force

AFB Air Force Base

AFI Air Force Instruction

AHU Air Handling Unit

APR Air Purifying Respirator

BMP Best Management Practice

BOS Base Operating Service

C&D Construction and Demolition

CE Civil Engineering

CES Civil Engineer Squadron

CEV Civil Engineering Environmental

CFR Code of Federal Regulations

CM Contract Monitor/Construction Manager

CO Contracting Officer

CUI Controlled Unclassified Information

DOD Department of Defense

DDC Direct Digital Control

EISA Energy Independence and Security Act

EPA Environmental Protection Agency

FPCON Force Protection Condition

FOIA Freedom of Information Act

FT Foot

GFCI Ground Fault Circuit Interrupter

HEPA High Efficiency Particulate Air (filter)

IAW In Accordance With

IBC International Building Code

IN Inch

LBP Lead Based Paint

LF Linear Feet

MAU Makeup Air Unit

MDEQ MS Department of Environmental Quality

MDOT Mississippi Department of Transportation

MSS Material Submittal Schedule

NEC National Electric Code

NFPA National Fire Protection Association

OSHA Occupational Safety and Health Act

PM Project Manager

SECTION 01 11 00 Page 2

POC Point of Contact

PPE Personal Protection Equipment

RAMS Random Antiterrorism Measures

RCRA Resource Conservation and Recovery Act

RFI Request for Information

SDS Safety Data Sheets

SF Square Foot

SOW Statement of Work

SWPPP Storm Water Pollution Prevention Plan

SY Square Yard

TAB Test, Adjust and Balance

UFC United Facilities Criteria

VAV Variable Air Volume

VFD Variable Frequency Drive

WT Work Task

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G

1.3 WORK COVERED BY CONTRACT DOCUMENTS

1.3.1. Project Description

The contractor shall furnish all equipment, labor, supervision and materials necessary to provide and replace AHU’s and VAV’s for the Student Dormitory Holbrook Manor, B7320, on Keesler AFB. The required end state is a fully operational cooling and heating system integrated into a new DDC package. All work is to be performed in accordance with all contract documents and is subject to the terms and conditions of the contract.

It is not anticipated that hazardous material will be encountered during the course of work. However, should such material be encountered, the Contractor is to immediately stop work and contact the CO. All hazardous material will be handled IAW paragraphs 1.8, 1.9, and 1.10 of this Section.

1.3.2. General Scope Notes

Contractor shall provide and maintain filters, etc. to prevent construction dust and debris from spreading throughout the HVAC system, Fire System Devices, and IT equipment.

Contractor shall provide constant daily cleaning of the building after area of work is completed for that day. Contractor shall be responsible for disposing of all material and cleaning the area of work at the completion of the project.

Contractor shall provide 5% additional stock of ceiling tile and all new finish material as applies to this project.

SECTION 01 11 00 Page 3

All work shall be phased to allow the facility to remain occupied and operational during construction. Dorm Rooms will be released one (1) wing (A, B, or C) including (floors 1st, 2nd, and 3rd) at a time. Contractor will coordinate with Facility Manager on the number of MTL offices released in each phase. Work within the Commons area to be coordinated and worked as required by each wing.

Contractor to ensure occupied rooms are not to be disturbed during construction in adjacent spaces.

All Furniture and building equipment to be moved away from work area and covered with tarp or plastic for dust control. Personal items are to be removed by the customer unless directed otherwise. Relocate furniture and building equipment following construction work. Clean all areas during and after work of gypsum dust, debris and gypsum mud.

1.3.3. Period of Performance

Performance will begin 10 calendar days after Award and will conclude 270 calendar days later.

No Work shall begin until all Submittals related to that work have been received and approved. The government will provide a response to submittals within 10 calendar days of receipt of submittal required by the MSS and 14 calendar days for any submittal that requests or requires deviation from the contract drawings or specifications.

Punch list items noted during inspections shall be corrected and accepted prior to the end of the Period of Performance or the contract will be considered past due.

1.3.4. Location

The work is located at the Holbrook Manor, B7320, Keesler AFB, Biloxi MS, approximately as indicated.

1.4 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.

The project will be phased providing one wing at a time, including all three floors. Work within the Commons Area will be phased separately and as required for each wing phase.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.5 EXISTING WORK

Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

SECTION 01 11 00 Page 4

1.6 LOCATION OF UNDERGROUND UTILITIES

PERMITS:

Contractors will be required to obtain permits as required by Keesler in the performance of their work. Contractors shall post or have readily available all permits before work is commenced.

The following permits must be obtained anytime referenced work is required:

DIG PERMIT – BOS/CE Customer Service

BURN PERMIT – Keesler AFB Fire Department (certified personnel only)

CONFINED ENTRY PERMIT – BOS/CE CM; Notification to Fire Department of actual day and time work is accomplished.

CRANE PERMIT - Coordinate crane usage with the Subcontract Technical Monitor (STM). Submit notice with the Federal Aviation Administration (FAA) at least 45 days before the start of the proposed construction or the date an application for a construction permit is filed, whichever is earliest.

1.6.1 INTERRUPTION OF SERVICES:

If interruption of any building utility services such as but not limited to the following: chilled water, electrical power, domestic water, fire protection water supply, or communications etc. are required, the Contractor shall perform the work on normal work week hours after receiving approval, during the weekend or on non-training Fridays. The Contractor shall coordinate the interruption of the utilities 14 days in advance with the CM and user regardless of the option chosen. The Contractor shall include any additional cost of performing the work in their original bid.

The Contractor shall submit Utility Service Outage Request to the Contracting Officer. The Contracting Officer may require the Contractor to attend a coordination meeting to assess the purpose, intent, and impact of the outage request with the facility and any or all operations departments. Contractors shall not shutdown or start-up any mechanical, electrical and/or plumbing system without the coordination and/or permission of the CO.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with dual frequency Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.6.2 Notification Prior to Excavation

Notify the Contracting Officer at least 48 hours prior to starting excavation work.

SECTION 01 11 00 Page 5

1.7 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 2 miles of the construction site.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

1.8 REQUIRED ASBESTOS ABATEMENT AND MANAGEMENT PROCEDURES:

These steps are in accordance with Air Force Instruction (AFI), EPA, and MDEQ. OSHA regulations govern all worker safety requirements and must be complied with at all times by the Contractors and sub-Contractors. These requirements are summarized in the Keesler Air Force Base Asbestos Operations and Management Plan.

The following steps are required by all personnel or Contractors doing work on Keesler AFB:

1.7.1 If the personnel or Contractor encounters what they think may be asbestos, they are required to stop and call the KAFB Asbestos Point of Contact (APOC) for the Keesler Environmental Section (BOS/CEV) at 228- 377-1262 or EMCS (228- 377-4179) after hours.

1.7.2 Once it is determined by the APOC that asbestos is present, the following actions described below are required (Only the APOC and Bioenvironmental are certified to make that determination).

1.9 NO ABATEMENT WORK IS TO BEGIN WITHOUT WRITTEN APPROVAL FROM THE APOC:

A Mississippi State certified asbestos abatement Contractor must be used to conduct the abatement. Please note that non-friable asbestos can easily be made friable and become regulated.

1.9.1 Before: The following documents must be submitted to the CO and approved in writing before abatement can begin:

1.9.1.1 10 Day MDEQ notification and return acknowledgment letter.

1.9.1.2 Asbestos Hazard Abatement Plan (to be certified by a

Mississippi Certified Management Planner and/or Certified Industrial Hygienist).

1.8.1.3 Asbestos Work Plan (scope of work, removal

procedures, worker protection, air monitoring, disposal location, containment procedures).

1.9.1.4 MDEQ Asbestos Abatement Certification for the

Company.

SECTION 01 11 00 Page 6

1.9.1.5 Supervisor’s qualifications and state certification.

1.9.1.6 CURRENT State Certifications (applications will not

be accepted) for all individuals working on site.

1.9.1.7 Respirator fit tests for all individuals.

1.9.1.8 Physicals for all individuals.

1.9.2 During: Once the submittals are approved in writing, the following actions are required:

1.9.2.1 The Contractor is required to set up their

containment areas, negative air machine, and critical barriers and obtain approval from the Asbestos POC to begin work.

1.9.2.2 The Asbestos POC routinely checks the abatement work

to ensure the containment area and critical barriers are secure, the workers are wearing the appropriate personal protective equipment, the asbestos-containing material is being bagged appropriately, and air monitoring is being conducted on the workers and outside the abatement area. This also includes reviewing the daily log maintained on site to assure no uncertified individuals are performing abatement work.

1.9.2.3 Upon completion of the abatement work, the Contractor contacts the Asbestos POC to conduct a walk-through of the area and approve all abatement has been completed and the area has been cleaned of asbestos fibers. This action will require at least a 24-hour period. Please reference cleaning procedures in the Asbestos Management and Operations Plan.

1.9.2.4 Air sampling results are required to be collected and submitted for approval by the Asbestos POC before the containment area, negative air machine, and critical barriers can be removed.

1.9.2.5 All asbestos waste must be handled and disposed of in accordance with State law. The Asbestos POC must review the waste prior to leaving the base and the manifest will be signed by a designated Keesler government representative. Contractors will not sign manifests for asbestos containing material (ACM).

1.9.3 After: After the abatement has been complete and approved by the Asbestos POC, the Contractor shall submit the following items in a post-job submittal to be maintained in the Asbestos Abatement Files:

1.9.3.1 Air sampling results.

1.9.3.2 Daily report logs.

1.9.3.3 Daily workers sign in/out sheets.

1.9.3.4 Waste manifest (Generator Copy)

1.9.4 The Asbestos POC and Environmental Section (BOS/CEV) are available at any time to provide asbestos awareness training and consultation to CM’s, PM’s, Contractors and Sub-Contractors prior to beginning the project.

SECTION 01 11 00 Page 7

1.10 REQUIRED LEAD-BASED PAINT MANAGEMENT PROCEDURES:

Appropriate OSHA worker protection is the responsibility of the employer. All projects will be monitored and inspected by BOS/CEV. The purpose of these instructions is to provide guidance to safely remove or encapsulate lead-based paint without causing a hazard. All work must be performed in accordance with OSHA, MDEQ and any local regulations for all work and disposal. The regulations are divided into two parts; a) lead-based paint on non-child occupied/non-target housing buildings and

b) child occupied/target housing buildings.

1.10.1 Non-child occupied/ commercial buildings:

1.10.1.1 For non-child-occupied/commercial buildings, the

minimum requirement for Contractors is to protect workers IAW OSHA requirements, use poly lay-down to collect paint chips, and turn into BOS/CEV for disposal. At minimum the supervisor of the project should be LBP trained and supply proof of certification before work begins. The Contractor shall notify BOS/CEV before start of any project. Contractor must place plastic on the ground sufficient to capture all loosened paint chips and control water run-off. Removal methods preferred at Keesler AFB are the use of an approved chemical stripper or wet sanding methods for better collection of LBP chips and waste. These processes minimize lead dust and allow for maximum collection of LBP chips.

1.10.1.2 The Contractor shall meet with BOS/CEV prior to

beginning the project to discuss protective measures, best management practices (BMP’s), any landfill disposal, and maintenance of chips and their collection (until they are turned over to BOS/CEV).

1.10.1.3 Any buildings with lead-based paint, if bead blasted to remove old paint, shall be supervised by a Contractor with proper training. Bead blasting upon prior approval only (see preferred method above).

1.10.1.4 The Contractor, under OSHA rules, must comply with

the lead-based paint rules (including notification to BOS/CEV, if the job is abatement), certify appropriate training, and maintain personal monitors on workers until it is demonstrated there is no airborne lead risk.

1.10.1.5 BOS/CEV will inspect all projects involving Lead

Based Paint removal and any required documentation must be provided to BOS/CEV prior to beginning work.

1.10.2 Child-occupied/target housing buildings:

1.10.2.1 Any child-occupied/target housing building older than 1978 must be painted using Lead Paint Protocol, including poly-lay-down, collection of paint chips, and the Contractor must always have a minimum of lead hazard training for all workers.

The Contractor shall notify BOS/CEV before start of any project.

1.10.2.2 A paint Contractor must collect paint chips in their own clean buckets and have BOS/CEV dispose (if contract requires BOS/CEV dispose). Contractor must place plastic on the ground sufficient to capture all loosened paint chips and control water run-off.

SECTION 01 11 00 Page 8

1.10.2.3 For work on child-occupied/target housing buildings

falling under the Lead Paint Protocol, the Contractor must use water or amended water when scraping or chipping. All members of the Contractor’s work force must wear protective clothing and comply with all OSHA rules and regulations. OSHA regulation compliance is the employer’s responsibility and is subject to inspection by OSHA and the Base. Suggested PPE include foot protection (ex. Rubber Boots) worn while on the poly. All PPE shall be stored on the protective plastic when not in use and shall be decontaminated or disposed of in an approved manner.

Minimum respiratory protection for any OSHA “trigger task” such as scraping, manual sanding, demolition, heat gun and power tool cleaning is a half-mask air purifying respirator (APR) with HEPA filter that is at least 99.97 percent efficient (i.e., P100). APR fit tests evidence must be provided for inspection. Other circumstances may warrant higher protection. PPE determination is the responsibility of the Contractor.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20, CHG 5: 02/25

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

15 CFR 772 Definition of Terms

15 CFR 773 Special Licensing Procedures

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map; G

Progress and Completion Pictures; G

SD-02 Schedule of Values (SOV); G

1.3 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.

1.4 SUPERVISION

1.4.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project.

SECTION 01 30 00 Page 2

The superintendent is not permitted to also serve as the Quality Control (QC) Manager, as established in Section 01 45 00 QUALITY CONTROL, However, the Site Safety and Health Officer (SSHO) may serve dual roles as the SSHO and QC Manager. The QC Manager must have qualifications in accordance with Section 01 45 00.

1.4.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.4.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.4.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time or excess costs or damages by the Contractor.

1.5 PRECONSTRUCTION

Immediately after award, Contractor may coordinate with the Contracting Officer a time and place to meet for the Preconstruction meeting. The purpose of this is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to:

daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out.

Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

Contractor must provide preliminary Schedule of Values (SOV) for Contracting Officer review and approval (See Section 01 33 00 for additional information).

1.5.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

SECTION 01 30 00 Page 3

1.6 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process prior to start of construction and convene at regularly scheduled Red Zone Meetings beginning at approximately 75 percent of project completion. Include the following in the facility Turnover effort:

1.6.1 Red Zone Checklist

1.6.1.1. Contracting Officer's Technical Representative (COTR) or CM will provide the Contractor a copy of the Red Zone Checklist template.

1.6.1.2. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

1.6.2 Meetings

1.6.2.1. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

1.6.2.2. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer. At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.

1.6.2.3. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

1.6.2.4. During the Red Zone Meetings discuss with the COTR or CM any upcoming activities that require Government involvement.

1.6.2.5. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

1.7 MOBILIZATION

Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.

1.8 JOBSITE MAINTENANCE AND STORAGE AREAS:

The Contractor shall maintain the jobsite and staging areas in conformance with the standards below and as directed by the CO.

1.8.1 Lay down/staging areas shall be kept neat and free of loose debris at all times. Grass shall be cut and maintained regularly. Height and maintenance shall be consistent with Base standards and consistent with the immediate area.

1.8.2 Parking on the grass is not permitted.

SECTION 01 30 00 Page 4

1.8.3 Jobsites and lay down/staging areas shall be enclosed with a 6’ chain link fence with brown fabric screening unless otherwise noted.

Materials and equipment may be stored inside storage units. Items stored in the lay down area shall be arranged neatly.

1.8.4 All temporary storage trailers and storage containers shall present a neat and clean appearance and shall be in a state of good repair and shall be located within the fenced area described in paragraph above.

1.8.5 If allowed by the contract and if approved by the CO, an office mobile unit may be located outside of a fenced area. At a minimum, this unit shall be in a paved area and shall present a neat, professional appearance. Unit shall be of Keesler standard colors, shall have presentable skirting and access stairs. Ancillary items, such as porches and canopies, shall be neat and painted Keesler brown. Contractor shall submit a picture of the proposed unit for approval and before unit is moved to Base.

1.8.6 Execution of work may require excavation or other type of work both at and away from primary work area. These areas shall be secured, and work times shall be kept to a minimum. Open excavations shall be directly in progress or shall be covered directly after work complete.

Open excavations requiring extended period of inactivity shall be temporarily backfilled. In no case shall an excavation be open for more than 72 hours. Barricades, fences and other warning devices shall be maintained neatly at all times.

1.8.7 The Contractor shall maintain the premises, including any staging area or storage areas, free from accumulations of waste, debris, and rubbish caused by the Contractor’s work and shall minimize the spread of dust and flying particles. As work is completed, or at the end of each day, the site shall be cleaned, and all waste material shall be properly disposed of properly.

1.8.8 Should warnings of winds of gale force or stronger be issued, the Contractor shall take every practical precaution to minimize danger to persons and damage to property. These precautions shall be coordinated through the CO and shall include closing all openings; removing all loose materials, tools, and equipment from exposed locations; securing all material, tools, equipment and construction work; as well as removing or securing scaffolding and other temporary work. The Contractor shall also coordinate all efforts with the CO and follow the Base Commander’s direction in the event of an upcoming storm or hurricane which may range from securing sites to complete demobilization of all equipment and material from the base.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 32 01.00 10 Page 1

SECTION 01 32 01.00 10

PROJECT SCHEDULE

08/23, CHG 1: 08/24

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASSOCIATION FOR THE ADVANCEMENT OF COST ENGINEERING,

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

AACE 84R-13 (2015) Planning and Accounting for Adverse Weather

AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)

ASCE 67-17 (2017) Schedule Delay Analysis

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (2017) Administration -- Project Schedules

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Preliminary Project Schedule; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules for projects of similar size and complexity to this contract, using Primavera P6, Microsoft Project, or equivalent project management software.

Representative must have a comprehensive knowledge of CPM scheduling principles and application.

SECTION 01 32 01.00 10 Page 2

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

2.1.1 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM) in a Gantt Chart format.

3.1.1 Scheduling Expectations Kickoff Meeting (SEKO)

In conjunction with the post award conference or preconstruction conference the Government and the Contractor may hold a separate and distinct Scheduling Expectations Kickoff Meeting (SEKO). The intent of this meeting is for the Government to review with the contractor the requirements of the scheduling specification, communicate the Government’s expectations regarding schedule development and management, and answer any questions the Contractor may have regarding the schedule requirements.

This meeting can be held the same day as the post award conference or preconstruction conference.

3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.2.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will have final project schedule approval.

3.2.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Non-procurement activities Original Durations (OD) are not to exceed 20 workdays or 30 calendar days.

SECTION 01 32 01.00 10 Page 3

3.2.3 Procurement Activities

Include in the schedule activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.2.4 Mandatory Activities

Include the following activities in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Submission of mechanical/electrical/information systems layout drawings.

c. Submission and approval of O & M manuals.

d. Submission and approval of as-built drawings.

e. Submission and approval of testing and air balance (TAB).

f. Submission of TAB specialist design review report.

g. Submission and approval of fire protection specialist.

h. Contractor's pre-final inspection.

i. Correction of punch list from Contractor's pre-final inspection.

j. Government's pre-final inspection.

k. Correction of punch list from Government's pre-final inspection.

l. Final inspection.

3.2.5 Government Activities

Show in schedule, Government and other agency activities that could impact progress. These activities include, but are not limited to approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.2.6 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

3.2.6.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to

SECTION 01 32 01.00 10 Page 4 the date that the NTP is acknowledged.

3.2.6.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.

3.2.6.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.2.6.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.2.6.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.2.7 Adverse Weather

Ensure anticipated adverse weather is accounted for in the Project Schedule. AACE 84R-13 provides methodologies for techniques in planning for adverse weather. The preferred methodology is the use of a weather calendar. If a method other than a weather calendar is proposed, discuss the reason during the SEKO meeting.

3.2.8 Calendars

Schedule activities on a Calendar to which the activity logically belongs.

Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.

If a weather calendar is used its implementation and execution is to be in accordance with AACE 84R-13

3.2.9 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the

SECTION 01 32 01.00 10 Page 5

Contractor's schedule.

3.2.10 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.

3.2.11 Added and Deleted Activities

Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.

3.2.12 Original Durations

Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.

3.2.13 Leads, Lags, and Start to Finish Relationships

Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb or create float, or to replace proper schedule logic.

a. Leads (negative lags) are prohibited.

b. Start to Finish (SF) relationships are prohibited.

3.2.14 Percent Complete

Update the percent complete for each activity started. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management, however, any progress reports shall reflect the actual percentage completed. Budgeted cost of activity is to be reduced by the amount needed to correct deficiency.

3.2.15 Remaining Duration

Update the remaining duration for each activity based on the number of estimated workdays it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete. The remaining duration for unstarted activities are not to be less than its original duration.

3.2.16 Early Completion Schedule and the Right to Finish Early

An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.

a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and hours) and the

SECTION 01 32 01.00 10 Page 6

Government agreeing that the schedule is reasonable and achievable.

b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.

3.3 PROJECT SCHEDULE SUBMISSIONS

Provide the submissions as described below. The data reports and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.

Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.

3.3.1 Preliminary Project Schedule Submission

Within 15 calendar days after the NTP is acknowledged, submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities.

3.3.2 Initial Project Schedule Submission

Submit the Initial Project Schedule for approval within ten (10) calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period.

No payment will be made for work items not fully detailed in the Project Schedule.

3.3.3 Periodic Schedule Updates

Update the Project Schedule on a regular basis, monthly at a minimum.

Provide a draft Periodic Schedule Update for review at the schedule update meetings. These updates will enable the Government to assess Contractor's progress. Update information including Actual Start Dates (AS), Actual Finish Dates (AF), Remaining Durations (RD), and Percent Complete.

Updated information is subject to the approval of the Government at the meeting.

a. AS and AF dates must match the date(s) reported on the Contractor's Quality Control Report for an activity start or finish.

SECTION 01 32 01.00 10 Page 7

3.4 SUBMISSION REQUIREMENTS

Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project, and as directed by the CO:

3.4.1 Electronic Scheduling Data

Provide electronic scheduling data containing the current project schedule and all previously submitted schedules in the format of the scheduling software (e.g. .xer). PDF format is also acceptable. Also include the Narrative Report and all required Schedule Reports. The electronic file is to identify the type of schedule (Preliminary, Initial, Update), full contract number, Data Date and schedule file name. Each schedule must have a unique file name and use project specific settings. The file naming convention is to be determined at SEKO meeting.

3.4.2 Narrative Report

Provide a Narrative Report with each schedule submission. The Schedule Narrative Report is a "stand alone" report in PDF or Word format. Title the report "Schedule Narrative Report". Show the Report date, schedule name, and contract number on the first page. Indicate who is responsible for the schedule update and narrative report. Provide a brief description of the Project Scope. The Narrative Report is expected to communicate to the Government the thorough analysis of the schedule output and the plans to compensate for problems, either current or potential, which are revealed through that analysis. Include the following information at a minimum in the Narrative Report:

a. Identify and discuss the work scheduled to start in the next update period.

b. Describe activities along the critical path in addition to activities on the next float path after the critical path.

c. Describe current and anticipated problem areas, delaying factors and their impact, and an explanation of corrective actions taken or required to be taken. Identify the party responsible for delay, if applicable.

d. Identify and explain why activities, based on their calculated late dates, should have either started or finished during the update period but did not.

e. Identify and discuss all schedule changes by activity ID and activity name including what specifically was changed and why the change was needed. Include at a minimum new and deleted activities, logic changes, duration changes, calendar changes, lag changes, resource changes, and actual start and finish date changes.

f. Identify and discuss out-of-sequence work.

g. If the longest path changes from a monthly update to the next, provide an explanation of the factors driving the change.

3.4.3 Schedule Reports

The format, filtering, organizing, and sorting for each schedule report will be as directed by the Contracting Officer. Typically, reports contain Activity Numbers, Activity Description, Original Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, SECTION 01 32 01.00 10 Page 8

Late Finish Date, Total Float, Actual Start Date, Actual Finish Date, and Percent Complete. Provide the reports electronically in .pdf format.

The following lists typical reports that will be requested:

3.4.3.1 Activity Report

List of all activities sorted according to activity number.

3.4.3.2 Total Float Report

A list of all incomplete activities sorted in ascending order of total float. List activities which have the same amount of total float in ascending order of Early Start Dates. Do not show completed activities on this report.

3.4.3.3 Scheduling and Leveling Report

Provide a Scheduling/Leveling Report generated from the current project schedule being submitted.

3.4.4 Network Diagram

The Network Diagram is required for the Preliminary, Initial and Periodic Updates. Depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The Contracting Officer will use, but is not limited to, the following conditions to review compliance with this paragraph:

3.4.4.1 Continuous Flow

Show a continuous flow from left to right with no arrows from right to left. Show the activity number, description, duration, and estimated earned value on the diagram.

3.4.4.2 Project Milestone Dates

Show dates on the diagram for start of project, any contract required interim completion dates, and contract completion dates.

3.4.4.3 Critical Path

Show all activities on the critical path. The critical path is defined as the longest path.

3.4.4.4 Grouping and Sorting

Group and sort activities as directed to assist in the understanding of the activity sequence. Typically, this flow will group activities by major elements of work, category of work, work area and/or responsibility.

3.5 REQUESTS FOR TIME EXTENSIONS

ASCE 67-17 provides delay analysis guidelines. If there is a conflict between the contract and guidance provided in ASCE 67-17, the contract will govern. Provide justification of delay to the Contracting Officer in accordance with the contract provisions and clauses for approval, within 10 days of a delay occurring. Also prepare a time impact analysis for each Government request for proposal (RFP).

SECTION 01 32 01.00 10 Page 9

3.5.1 Justification of Delay

Provide a description of the event(s) that caused the delay and/or impact to the work. As part of the description, identify all schedule activities impacted. Show that the event that caused the delay/impact was the responsibility of the Government. Provide a time impact analysis that demonstrates the effects of the delay or impact on the project completion date, or interim completion date(s). Evaluate multiple impacts chronologically; each with its own justification of delay. With multiple impacts consider any concurrency of delay. A time extension and the schedule fragnet becomes part of the project schedule and all future schedule updates upon approval by the Contracting Officer.

3.5.2 Changes That Do Not Cause Delay

If it is determined that a change does not constitute a schedule time extension, a fragment as described in paragraph FRAGMENTARY NETWORK, is to be created and inserted into the Project schedule.

3.5.3 Time Impact Analysis (Prospective Analysis)

Submit requests for time extensions based on a prospective analysis if the work involved or the impact identified has not already occurred. Where the impact is ongoing a prospective analysis may be considered. However, the Government reserves the right to require a retrospective analysis be prepared after the impact has ended.

Prepare a time impact analysis for approval by the Contracting Officer based on industry recommended practice…