Attachment 1 - Final SOW.pdf

PDF 97 KB Posted

Attached to
5680--657-21-710JC EHRM Cerner Admin Space Support Construction - John Cochran Federal contract opportunity
Solicitation number
36C77621B0015
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This statement of work outlines site preparation requirements for a modular building project at the VA St. Louis Health Care System in Jefferson Barracks, Missouri. The scope of work includes demolishing existing asphalt and fencing, grading and paving the site, installing 28 parking spaces and concrete curbs, erecting a perimeter chain link fence and gates, constructing a transformer pad, installing a distribution panel and site lighting, and providing security fencing around the project perimeter. Electrical and security systems will support approximately 1,800 square feet of modular buildings housing EHRM Cerner administration. The construction period is 90 days from notice to proceed.

View the file

Other files for this federal contract opportunity

Other files attached to 5680--657-21-710JC EHRM Cerner Admin Space Support Construction - John Cochran, newest first.
File Type Posted
36C77621B0015 0004.docx DOCX document
Attachment 8 - EHRM John Cochran - Technical Questions Tracking Spreadsheet.pdf PDF
36C77621B0015 0003.docx DOCX document
Attachment 7 - Drawings Full Set.pdf PDF
Attachment 6 - Full Specifications.pdf PDF
36C77621B0015 0002.docx DOCX document
36C77621B0015 0001.docx DOCX document
Attachment 5 - Site Map.pdf PDF
Attachment 2 - VA NOTICE OF LIMITATIONS ON SUBCONTRACTING.docx DOCX document
36C77621B0015_1.docx DOCX document
Attachment 4 - DBA Wage Rates.pdf PDF
Attachment 3 - Contractor Safety and Environmental Record Evaluation Form.docx DOCX document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

April 15, 2021

Modular Building Site Prep for EHRM - Cerner Admin Space

VA St. Louis Health Care System, Jefferson Barracks, St. Louis, Mo

657-21-710 JC EHRM Cerner Admin Space

15 April 2021

Statement of Work

Project Description: Exiting VA properties at 3635 & 3639 Windsor Place Dr. will be prepared to receive approx. 1800 SF of modular buildings to support on-site administration of EHRM at the Jefferson Cochran VA Medical Center. The referenced modular buildings will be provided and utilized by Cerner.

Existing Conditions.

1. The combined area of both sites is ~21,800SF

2. The existing sites are enclosed with a barbed wire fence that is open on the south edge. The western property consists of broken asphalt while the eastern property consists of compacted aggregate fill.

3. Both properties slope to the south and southwest. Currently around 50% drains to an existing storm inlet in the southwest corner while the rest drains south to Windsor Place Dr.

4. Existing power lines are located along the north side of both properties.

These lines service the nearby housing and businesses. There also appears to be existing communication cabling on these power poles as well. It is undetermined if the communication cabling is active.

Project Intent

The construction contractor will prepare the site for the 1800 SF of modular buildings to be placed by others including all final connections. The scope of work for this project shall include the following items:

1. Site Development:

a. Demo

April 15, 2021

i. Remove the existing broken asphalt, barbed wire fence, pipe bollards and existing vegetation.

b. Construct:

i. Grade existing site to slope to existing inlet in the southwest corner and south to Windsor Place Ave.

ii. Provide asphalt paving throughout site.

iii. Stripe 28 parking spaces and provide concrete parking blocks

iv. Concrete curbs at the west property line and a portion of the south property line

v. Perimeter chain link fencing with a double sliding gate with bollard protection and two swinging man gates.

vi. Concrete transformer pad.

2. Electrical & Lighting

a. Project will provide a distribution panel to support 1800 SF of modular buildings and pole mounted site lighting.

b. Project will provide and install pole mounted LED lights to achieve the minimum site lighting requirements.

3. Security

a. Project will provide new 6ft PVC coated chain link fencing and gates around the project perimeter.

Schedule

1. The length of construction services (Period of Performance) is 90 days after

NTP.