Attachment 1. Statement of Work - Van Vleck Bunkhouse.pdf

PDF 497 KB Posted

Attached to
127EAW23R0050 - Van Vleck Bunkhouse Roof Replacement
Solicitation number
127EAW23R0050
Issued by

About this file

This statement of work outlines the technical requirements for a roof replacement project on the Van Vleck Bunkhouse located within the Eldorado National Forest. The project involves removing the existing composite shingle roof and replacing it with a standing seam metal roof system to withstand heavy snow loads. There is also an optional item to install a 12-volt LED solar lighting system within the bunkhouse. The technical specifications provide details on the scope of work for both the roof replacement and optional solar lighting system installation. This includes requirements for the metal roofing materials and installation, as well as the solar panel array, battery storage, and interior lighting fixtures. The project location, schedules, site requirements and warranties are also defined. The solicitation number and agency for this opportunity are provided to allow interested contractors to respond with a proposal by the specified deadline.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Maps and Photographs

3.0 Technical Requirements / Tasks

4.0 Project Management

5.0 Specifications

6.0 Project Location

7.0 Schedule Of Work

8.0 Project Site Clean Up

9.0 Damage to Government Property

10.0 Installation Warranty

Project Van Vleck Bunk House Roof Replacement

General Information

1.0 Scope of Work

Base Bid The purpose of this contract is to remove the existing composite shingle roof and replace with a durable metal roof on the “Van Vleck bunkhouse” located within the Eldorado National Forest. Due to the high elevation, the new metal roof purpose is to withstand heavy snow loads due to extreme winter weather.

Option Item There is also an option for the installation of 12-volt, low wattage LED solar lighting system. The Van Vleck bunkhouse is a two room, plus one interior bathroom. The Bunkhouse is just approximately 600 square feet while the roof is approximately 800 Sq feet.

2.0 Maps and Photographs

For project location maps and photographs, see attachments. Any maps or photographs included in Section J are general in nature and are not to be considered as definitively identifying locations.

3.0 Technical Requirements / Tasks

Base Bid - Standing Seam Re-Roof

• Work will include installation of standing seam roofing system for Van Vleck Bunkhouse located in the Eldorado National Forest, Pollock Pines, CA.

• Remove the existing asphalt shingle roofing system down to the plywood deck.

• Inspect decking for damage or erosion. The replacement of eroded or damaged wood will be done only as required by the city, county, state, or OSHA standards.

• Installation of eave flashings at all eave locations.

• Due to heavy snow loads, “SNOW GAURDS” product will need to be installed to prevent dangerous snow/ice from falling suddenly off the roof.

• Install a layer of self-adhered synthetic asphalt underlayment over entire roof deck.

• Install new 24" pre painted 24-gauge metal valleys over layer of Grace “Ice & Water Shield” self-adhering rubberized asphalt membrane at all designated valley locations.

• Install Taylor Metal Products or similar grade/quality product, a “standing seam roofing system”.

o (Exact color specifications of metal roof will be selected by government C.O.R, after contract is awarded.

Government COR and contractor will meet to select specific colors) prior to installation.

• All panels will be 18" wide with striations. All panels with be mechanically installed with the use of factory supplied clips and screws pre manufactures recommendations.

• All rake, ridge, and valley locations will be installed pre manufactures recommendations with manufactures approved materials.

• Installation of roof jacks, roof penetrations, plumbing pipes, hot pipes, fan pipes, etc. painted to match roof shingle color.

• Installation of all flashing' with specialized steel rubber screws pre manufactures recommendations.

• Clean-up of project site and disposal of all project waste and debris.

• Provide a manufacture 20-30-year warranty (suggested industry standard) on labor and materials.

o Provide a Contractor limited 3-5year workmanship warranty (suggested industry standard)

Roof replacement work performed under the scope of this contract will be performed in accordance with the requirements set forth by the National Roofing Contractors' Association (NRCA) and the manufacturers of each component used.

Option Item - Solar Power Lighting In 2018, the decision was made to remove the old propane lighting system from The Van Vleck bunkhouse. A taller pole mounted solar lighting system was decided to replace the old propane lantern lights. The lighting system was designed to be for an off-grid remote location. The taller solar panel mount system was selected for the ability to operate and handle the high snow levels in the locations. At this project location in the summer of 2020, the USFS recreation staff installed a 17ft, 4-inch diameter steel pole in ground with concrete pad which is to be used as the support for the top of pole mount, however the project was never completed. The contractor is expected to finish the installation of a solar lighting system from this point on.

The system will be a 12-volt, low wattage led lighting system, consisting of solar panels, secured to a top of pole mount(outside). The power supply will lead inside the bunkhouse, into a large closet. Between the two rooms and bathroom, it estimated there will need to be approximately 5-10 various light fixtures to be installed.

The Forest Service will only purchase all interior lighting fixtures and compatible switches after contract is awarded.

These interior lighting fixtures will be supplied to the selected contractor to be installed by the contractor. All other necessary solar charging components such as modules, top of pole mount, batteries, charging controllers, wiring, tubing, conduit, fuses, installation hardware, breakers, circuits, fuses etc. and any other system components and installation hardware, will need be supplied and installed by the contractor. The only parts/components that will be purchased by the Government and then supplied to the contractor for installation will only be the lighting fixtures and any compatible switches.

Note that the number fixtures and specific style has not been finalized. Below is an estimated breakdown of approximately how many fixtures and the desired location.

Specification: Voltage: 12V DC Power consumption (60-Watt equivalent), Warm light and if possible, prefer dimming capabilities on all fixtures.

• Kitchen-1-2 qty. Ceiling fixtures and if needed separate wall switch (above sink and countertop)

• Living room-1-2 qty. Wall or celling mounted fixtures and if needed separate wall switch.

• Dining room-1-2 qty. Ceiling fixtures and if needed separate wall switch.

• Bedroom-1-2 qty. Wall or ceiling mounted fixtures and if needed separate wall switch.

• Bathroom-1-2 qty. Ceiling or wall mounted fixtures for bathroom/shower and if needed separate wall switch.

The system should be a solar charging system that has four solar modules (panels) that charges four large solar batteries to be the power source for all interior lighting. The work required would be to install approximately four solar modules(panels) to a “top of pole mount” style. Due to the heavy snow load during winters, the appropriate mounting style would be the top of pole mount. Refer to the drawing and picture below for the top of pole mount setup.

This sample drawing has a 4-module setup that is desired for the Van Vleck Bunkhouse.

The picture is a sample of the engineering plans from MT Solar. The company builds custom mounts to secure solar panel modules. These mounts are designed to withstand extreme weather and high winds.

The closet will house batteries, charging controller, fuses and all other necessary system charging components. The contractor will need to build a small “battery box” to safely store all charging components inside this closet. The purpose of the box is to keep all wiring and components free from rodents/protected from any other damage. The contractor shall notify the Contracting Officer in writing for further direction if any ventilation or safety measures need to be addressed. A similar battery box was built at Robbs Hut, Eldorado National Forest. The power supply will run from the box out of the closet and into ceiling/wall LED fixtures. The Van Vleck bunkhouse is approximately 600 square feet.

This system is only to provide power to operate several low watt LED celling /wall panel lighting fixtures. Power source is for lighting only, no power is needed for wall outlets or appliances. Installation of a similar solar lighting system at another rental cabin, Robbs Hut, was completed by Forest Service staff in 2019. This system is currently working/operating. The site, Robbs Hut, may be visited/surveyed by contractor before work begins on the Van Vleck Bunkhouse. The main objective is to have a safe and efficient lighting system that resembles the previous installed version at Robbs Hut. It is understood that certain installation details may vary from each site due to differences in site location, structures, materials, personnel differences etc.

4.0 Project Management

The contractor shall appoint a Project Manager to coordinate all Contractor’s activities during construction and to liaise with the Contracting Officer Representative (COR) and/or Contracting Officer (CO), and Project Engineer for the USDA Forest Service. Contractor shall designate in writing an on-site superintendent to be on-site at all times.

5.0 Specifications

The contractor shall follow The International Building Code (IBC) and The Construction Specification Institute (CSI)

• Section 070505.10 Selective Demolition

• Section 074113.16 Standing Seam Metal Roof Panels

• Section 077253.10 Snow Guard Options

• Section 263100 PV Collectors

• Section 265119 LED Interior Lighting

6.0 Project Location

The Van Vleck Bunkhouse is located approximately 14 miles northeast of Crystal Ranger Station along “Cheese Camp” road. The legal location is Section 32, Township 13 N, Range 15 E, M.D.M. Access is generally by paved road except for the last 0.5 mile which is a dirt road. To reach the bunkhouse: • Highway 50 east 21 miles from Placerville (8.5 miles east of Pollock Pines). Left on Icehouse Road north 23 miles. Right on Cheese Camp Road (13N22) 4 miles to fork in the road. Stay right for 1.5 miles to left turn at locked gate. The Bunkhouse is a half-mile past the gate on the left side.

7.0 Schedule of Work

The duration of the project shall be 14 calendar days from the Notice to Proceed.

Operations shall be scheduled so that work is completed between the hours of 7 a.m. and 8 p.m. Monday through Friday, except on Federal Holidays. Permission to work an alternate schedule or hours outside those designated may be requested from the Contracting Officer.

8.0 Project Site Clean Up

Project site cleanup includes the removal and proper disposal of all construction trash, debris, and residue off National Forest Land.

All spills of petroleum products including leak spots from parked vehicles shall be removed and properly disposed according to all Local, State, and Federal rules, regulations, and laws governing such disposal.

During the Work, the Contractor is required to furnish dumpsters or other trash receptacles and to empty such containers either as they become full or weekly, whichever is more frequent. The Contractor shall not place materials of any kind into private or Government trash bins or dumpsters.

9.0 Damage to Government Property

The Contractor shall notify the COR when damage to Government property is discovered. Any damage to Government property caused by the Contractor shall be repaired or replaced by the Contractor at the Contractor’s expense.

10.0 Installation Warranty

A. The Contractor shall be responsible for installing all materials and equipment in accordance with the original manufacturer’s specifications and requirements. All warranty documents shall be provided to the COR.

B. The Contractor shall warrant all labor for a period of one (1) year from the completion of the installation. The expiration or termination of the contract does not void the Contractor’s responsibility to perform diligent warranty work.

Project
General Information
1.0 Scope of Work
2.0 Maps and Photographs
3.0 Technical Requirements / Tasks
4.0 Project Management
5.0 Specifications
6.0 Project Location The Van Vleck Bunkhouse is located approximately 14 miles northeast of Crystal Ranger Station along “Cheese Camp” road. The legal location is Section 32, Township 13 N, Range 15 E, M.D.M. Access is generally by paved road except f...
7.0 Schedule of Work
8.0 Project Site Clean Up
9.0 Damage to Government Property
10.0 Installation Warranty