This solicitation is seeking proposals for road repair services on Crooked Creek Road in Carbon County, Montana. The Bureau of Land Management (BLM) Montana State Office intends to award a firm-fixed price contract between $250,000 to $500,000 to furnish labor, equipment, materials and perform work including reestablishing 2.6 miles of road typical section and grade, establishing drainage ditches, providing soil moisture, furnishing and compacting aggregate base course, and removing and replacing culverts. The North American Industry Classification System code for this requirement is 237310. Proposals are due by September 13, 2021 with award anticipated by September 23, 2021. The successful contractor must begin work within 10 days of notice to proceed and complete all work within 125 calendar days, including final cleanup. Offerors should direct questions to the point of contact provided. All prospective contractors must be registered in SAM and able to submit invoices through the Invoice Processing Platform. This requirement is set aside for total small business and the applicable size standard is $39.5 million.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specifications for
Crooked Creek Road Repair Phase I
BUREAU OF LAND MANAGEMENT
5001 Southgate Drive
Billings, Montana 59101
June 2021
TABLE OF CONTENTS
TABLE OF CONTENTS
CONTRACT SPECIFICATIONS PAGES
General Information and Requirements ................................................................. 1 thru 12
CONTRACT DRAWINGS
Cover Sheet ................................................................................................................ 1 of 16 Vicinity Map ............................................................................................................... 2 of 16 Project Map ................................................................................................................ 3 of 16 Plan View ....................................................................................................... 4 thru 13 of 16 Road Section Details ............................................................................................... 14 of 16 Culvert Details ......................................................................................................... 15 of 16 Culvert Riprap Details ............................................................................................. 16 of 16
GENERAL INFORMATION AND REQUIREMENTS
CROOKED CREEK ROAD REPAIR
MT-01009-1
SECTION MT-01009
PART 1: GENERAL
1.01 SUMMARY
A. Description of Work: Furnishing labor, equipment, supplies, and materials, to:
• Re-establish road typical section, grade, shape and compact 2.6 miles of road.
• Establish road typical ditch where required to prevent stormwater run-on.
• Provide adequate soil moisture when and where natural conditions are not suitable to conduct road maintenance activities.
• Furnish, spread, and compact Crushed Aggregate Base Course as awarded and directed by the
Contracting Officer’s Representative.
• Remove and replace existing culverts as called out in the design drawings.
B. Location: Work under this Contract is located approximately 30 miles southeast of Bridger, Montana in Carbon County, Montana on Crooked Creek Road. The work location is shown in the design drawings attached.
C. Drawings and Maps: The drawings and maps designate the type and quantity of work required at the project location.
1.02 REFERENCES
A. Referenced Specifications/Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/standards referred to herein may be procured by the Contractor, from the following:
AASHTO American Association of State Highway and Transportation Officials
444 North Capitol Street N.W., Suite 225
Washington, DC 20001
ASTM American Society for Testing and Materials
1916 Race Street
Philadelphia, PA 19103
FP Standard Specifications for Construction of Roads and
Bridges on Federal Highway Projects
Superintendent of Documents
Government Printing Office
Washington, DC 20402
Fed. Spec. Federal Specification/Standard
General Services Administration
Specifications Branch
Room 6039, GSA Building
MT-01009-2
Seventh and D Streets, S.W.
Washington, DC 20407
MDT Standard Specifications for Road and Bridge Construction, 2014 Ed.
Montana Department of Transportation
Contract Plans Section
2701 Prospect Avenue
Helena, MT, 59620
MPWSS Montana Public Works Standard Specifications
1717 11th Ave.
PO Box 4519
Helena, MT 59604
MUTCD Manual on Uniform Traffic Control Devices for Streets and Highways
Superintendent of Documents
Government Printing Office
Washington, DC 20402
OSHA Occupational Safety and Health Administration's Standards
U.S. Department of Labor
Occupational Safety and Health Administration
Denver Area Office
333 West Colfax Avenue
Denver, CO 80204
*Federal Specifications and catalogs may be obtained at Business Service Centers of Regional
Offices of the General Services Administration. (Washington, DC; Boston, MA; New York, NY; Philadelphia, PA; Atlanta, GA; Chicago, IL; Kansas City, MO; Fort Worth, TX; Denver, CO; San Francisco, CA; and Auburn, WA.)
1.03 DEFINITIONS
A. Approvals: Approval of the submittal is an indication that the Contractor's submittal has been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer's attention in writing. After approval of an item, the Contractor may submit a substitute for approval when the approved item cannot be purchased or delivered in time to avoid delay in completion of the project.
B. Engineer: For all specifications incorporated into the work by reference, the Contracting Officer’s
Representative (COR) shall be the “Engineer”.
C. Department: For all specifications incorporated into the work by reference, the government shall be the “Department”.
MT-01009-3
1.04 SUBMITTAL
A. Scope: Submittals may include, but not necessarily be limited to, the following: design computations, shop drawings, manufacturers' literature, as-built drawings, samples, and maintenance manuals.
B. Requirements: Refer to specifications for submittals required. Allow at least 5 working days for review. Submittals shall be delivered to the Contracting Officer or his/her appointed representative.
C. Identification of Submittal: Completely identify each submittal by showing at least the following information: submit two copies of each submittal for approval.
1. Name and address of submitter, plus name and telephone number of the individual to contact for further information.
2. Name of project as it appears in these specifications.
3. Contract number, drawing number, and specification section number to which the submittal applies.
4. Whether this is an original submittal or re-submittal.
5. Each item shall clearly note the manufacturer's name and address, trade name, product, lot, style, color, catalog designation or model number, and locations of use.
1.05 CERTIFICATES OF CONFORMANCE:
A. Requirements: The Contracting Officer may permit use, prior to sampling and testing, of materials when accompanied by Certificates of Conformance. Materials used on the basis of a Certificate of
Conformance may be sampled and tested. Installation of materials on the basis of Certificates of
Conformance shall not relieve the Contractor of responsibility for incorporating materials conforming to the requirements of the drawings and specifications. Material not conforming to those requirements will be subject to rejection, whether in place or not.
B. Format: The form of the Certificate of Conformance provided by the supplier shall be as follows:
Submit two copies of the Certificate of Conformance for approval.
1. The certificate shall state that the named product conforms to the Contract requirements.
2. The certificate shall either be accompanied with a certified copy of the test results or certify that such test results are on file with the manufacturer and will be furnished to the Contracting
Officer upon request.
3. The certificate shall provide the name and address of the manufacturer, the testing agency, and the date of tests.
4. The certificate shall set forth the means of identification permitting field determination of the product delivered as being the product covered by the certification.
MT-01009-4
1.06 PROJECT SCHEDULE/SEQUENCE OF OPERATIONS
A. Submit a project schedule for review after the Notice to Proceed to illustrate the sequencing and time allotted for the road work, and each portion of the road work, in order to achieve completion of the work within the time limit specified in the contract. The schedule shall include the following:
1. Breakdown of grading to allow monitoring of progress of work.
2. Sequence of graveling, grading, and compaction operations with start dates, duration, and finish dates.
3. When requested, the Contractor shall submit an updated schedule within 3 working days.
1.07 VALUE SCHEDULE
A. The Value Schedule shall be presented at the Pre-work Conference. The Value Schedule shall contain similar itemization to the progress schedule, so that adherence to the work schedule, as well as appropriate progress payment amounts, can be readily determined. The Value Schedule shall indicate the dollar value of each major work item. Estimated quantities of major work items are shown on the Drawings and Bid Value Schedule, and at a minimum, the submitted Value Schedule shall include similar detail for all work to complete the project.
1.08 QUALITY ASSURANCE:
A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.
B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.
1.09 DELIVERY, STORAGE, AND HANDLING:
A. Delivery: The Contractor shall protect products, incorporated into the work, from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturer's name and brand designation and contents legibly indicated. The containers shall bear the referenced specification number, type, and class as applicable.
B. Storage: The Contractor shall provide temporary storage facilities for products complying with manufacturer's recommendations which will protect them from damage until installation on the project and final acceptance. The storage area shall permit access for inspection and handling.
C. Handling: The Contractor shall load and unload products in such a manner that protects them from damage until installation on the project.
MT-01009-5
1.10 PROJECT/SITE CONDITIONS:
A. Access to the Work: Access to the work is by state, county, and Bureau of Land Management
(BLM) roads. Provide 2 copies of a traffic control plan and schedule for the work to the COR at the prework conference. Do not begin work until receiving written approval of the Traffic Control Plan and Schedule from the COR.
B. Crooked Creek Road to remain open to one-lane traffic, including through-ditch detours, at all times during the construction timeframe within the existing right-of-way only. Submission of through-ditch detouring, and traffic control plan must be provided to COR for approval at least 7 days prior to proposed work commencing. Contractor shall be responsible to ensure no unauthorized vehicles access the work area during construction. After each day’s work, contractor shall clear the roadway of all hazards and open to traffic. Contractor to furnish all construction signage and traffic control for, but not limited to: Road closures signs and barriers, and construction signs according to the most current Manual on Uniform Traffic Control Devices (MUTCD) standards including signage on state highways if applicable. All construction traffic control shall comply with the most current
MUTCD standards. This work shall be included in the lump sum contract price for Traffic Control.
C. Environmental Considerations:
1. The aesthetic values of the sites and surrounding areas are of prime importance. The contractor shall take all care necessary to preserve all plant life and other natural features. Travel of motor vehicles and heavy equipment shall be limited to existing roads and parking areas. Soil disturbance shall be limited as much as practical. No off-road travel is permitted except for minimal turn-around areas. Any surface damage outside the project areas shall be corrected by the Contractor at his expense.
2. All vehicles and equipment shall be power washed before transportation to the sites, to prevent the spread of weed seeds.
3. While working along stream areas or wetlands, precaution shall be taken to avoid spilling materials into the stream.
D. Construction Facilities: Contractor shall be responsible for utility locations before starting work. All utility locations shall include public and private utilities on the site.
E. Repair of Underground and Overhead Utilities: Contractor is responsible for any damage to underground and overhead utilities such as but not limited to: water, electrical, phone, sewer, and main power lines. All damaged underground or overhead utilities will be the full responsibility of the Contractor and shall be repaired at the Contractors expense.
PART 2: PRODUCTS
2.01 Mobilization: Mobilization shall follow the requirements of “Measurement and Payment” within
Section 109 of the MDT 2014 Standard Specifications for Roads and Bridges.
2.02 Temporary Traffic Control: Traffic control shall follow MUTCD design standards. The Contractor is responsible for the design and implementation of the contracting officer approved traffic control plan. Submission of the Traffic Control plan shall be no later than seven days prior to the start of
MT-01009-6
construction. Traffic control shall be measured and be paid lump sum as per Part 4 of these technical specifications.
2.03 Clearing: Clear and Grub the area following the requirements of “Clearing and Grubbing” within
Section 201 of the MDT 2014 Standard Specifications for Roads and Bridges. Clearing and
Grubbing will only take place in conjunction with Road Conditioning where required and considered incidental.
2.04 Pipe Culverts: Furnish and install pipe culverts meeting the requirements of “Metal Pipes” within
Section 709 of the MDT 2014 Standard Specifications for Roads and Bridges. Materials shall conform to the kind, type, grade, and size specified in the plans. Material submittal is required for coated corrugated pipes and flared end treatments. Culverts shall be installed according to Section
207 MDT 2014 Standard Specification for Roads and Bridges.
2.05 Riprap, Class I: Furnish and install riprap meeting the requirements of “Riprap and Slope and Bank
Protection” within Section 613 of the MDT 2014 Standard Specifications for Roads and Bridges.
Materials shall conform to the kind, type, grade, and size specified in the plans and the proposal.
Material submittal required for riprap in accordance with the contract plans and Section 701.06 of the MDT 2014 Standard Specification for Roads and Bridges.
2.06 Separation Geotextile: Furnish and install separation geotextile meeting the requirements of
“Geotextiles” within Section 622 and Section 716 of the MDT 2014 Standard Specifications for
Roads and Bridges. Separation geotextile shall be nonwoven, high survivability, and meet the minimum requirement for permittivity referenced in Table 716-2 of the MDT 2014 Standard
Specification for Roads and Bridges. Material submittal is required for separation geotextile.
2.07 Road Conditioning: Road Conditioning shall follow the requirements of “Excavation and
Embankment” within Section 203 of the MDT 2014 Standard Specifications for Roads and Bridges.
All work necessary to prepare surfaces to the lines and grades of the project plans shall be included in this item. Work consists of smoothing, scarifying, processing, and shaping existing road to restore typical sections as designated on the drawings; and restoring proper drainage to the designated typical sections.
A. Scarification: Where potholes, washboards, or ruts are over 1” deep, scarify to a minimum depth of 3-4 inches below the road surface, process the material, and reshape the surface.
B. Road width: Road widths shall be those from the designated typical sections as shown on the project drawings.
C. Grades: Grades shall be maintained according to the designated typical sections as shown on the project drawings or maintained as uniform slopes where elevations change. Abrupt changes in slopes shall be rounded.
D. Blading: Blading of road surfaces will be done to minimize the loss of aggregate material. High blading, which is merely filling depressions with loose material, will not be acceptable. Berms or ridges shall not be left along the shoulders, except where required for safety. During the blading operation, material shall not be graded into cattleguard pits. All loose rock larger than 3 inches shall be removed from the roadbed.
1. Double land roads will be crowned at 3%, except on corners. Corners will be
MT-01009-7
superelevated per the direction of the COR. Make smooth transitions between the crown and superelevated cross sections.
2. Sections of roads constructed with roadside ditches shall be bladed and reshaped to drain the water from the roadbed. The cross section shall match the designated typical sections as shown on the project drawings.
E. The new road native surface and aggregate base course surface shall be compacted to 95% of the theoretical laboratory maximum density (as determined by ASTM D698) while the material is within 3% of the optimum moisture content. Density testing may be performed by BLM personnel at the Contracting Officer’s discretion using a Nuclear Densometer. Site drainage shall be of prime importance.
2.08 Watering: Distributing and applying water required for compaction of aggregate base course, for dust control, and when directed by the Contracting Officer’s Representative (COR) for achieving satisfactory moisture conditions during maintenance operations.
A. The Contractor is responsible for obtaining a water source for filling operations that complies with all federal, state, and local laws. Water sources located on Bureau of Land Management will be approved on a case by case basis by the COR.
B. Water shall be clean and free from deleterious materials.
C. Provide necessary pumping equipment and water trucks. Water trucks shall be equipped with a pressure pump and spray bar of adequate capacity and design to ensure uniform application of water in the amounts designated. Provide manufacturers certification of the storage volume of each water truck used on the project.
D. Water shall be applied in such a manner to ensure uniform moisture content. The amount of water added or applied shall be sufficient to obtain the percent relative compaction required. Water dry material to prevent dust on the project site, waste site and haul roads to the waste sites.
2.09 Salvaging, Stockpiling, and Placing Topsoil: Salvage, stockpile, and place all topsoil shall follow the requirements of “Excavation and Embankment” within Section 203 of the MDT 2014 Standard
Specifications for Roads and Bridges.
2.10 Crushed Top Surfacing: Furnish and install Crushed Top Surfacing meeting the requirements of
“Aggregate Surfacing” within Section 701 and Section 301 of the MDT 2014 Standard
Specifications for Roads and Bridges. Crushed Top Surfacing Type “A” shall be Grade 1. Material submittal required for Crushed Top Surfacing Type “A” shall include, but not limited to, gradation, Atterberg limits, and moisture/density proctor submittal.
The road native surface and aggregate base course surface shall be compacted to 95% of the theoretical laboratory maximum density (as determined by ASTM D698) while the material is within 3% of the optimum moisture content. Density testing may be performed by BLM personnel at the Contracting Officer’s discretion using a Nuclear Densometer. Site drainage shall be considered to be of prime importance.
2.11 Reclamation/Seeding: The contractor shall seed all disturbed areas with the seed mixture listed below.
MT-01009-8
A. There shall be no primary or secondary noxious weed seed in the seed mixture. Seed shall be tested, and the viability testing of seed shall be done in accordance with State law(s) and within six months prior to purchase. Commercial seed shall be either certified or registered seed. The seed mixture container shall be tagged in accordance with State law(s) and available for inspection by the contracting officer. Material submittal required for seed mix design
B. Seed shall be planted using a drill equipped with a depth regulator to ensure proper depth of planting where drilling is possible. The seed mixture shall be evenly and uniformly planted over the disturbed area. Smaller/heavier seeds tend to drop to the bottom of the drill and are planted first. The contractor shall take appropriate measures to ensure this does not occur. Where drilling is not possible, seed shall be broadcast, and the area shall be raked or chained to cover the seed.
When broadcasting the seed, the pounds per acre noted below are to be doubled. The contracting officer is to be notified a minimum of seven (7) days prior to seeding of the project.
C. Seed Mixture – Central & Southeastern Regions Sagebrush Seed Mix (All Application Rates Are lbs PLS/Acre
a. Grasses
i. Agropyron smithii – Western wheatgrass .75 for drill seed rate & 1.5 for broadcast
ii. Agropyron spicatum – Bluebunch wheatgrass 1.5 for drill seed rate & 3.0 for broadcast
iii. Agropyron trachycaulum – Slender wheatgrass .5 for drill seed rate & 2.0 for broadcast
iv. Stipa comata – Needle and thread 1.25 for drill seed rate & 2.5 for broadcast
b. Forbs
i. Achillea millefolium – Yarrow 0.025 for drill seed rate & 0.05 for broadcast
ii. Artemisia frigida – Fringed sagewort 0.025 for drill seed rate & 0.05 for broadcast
c. Shrubs
i. Artemisia tridentata ssp. Wyomingensis – Wyoming Big Sagebrush 3.0 for broadcast rate No Drill Seeding allowed
d. Related Info:
i. In general, shrub seed should originate from areas within 300 miles of the project to insure compatibility with local conditions. It is vital that seed suppliers provide the most consistent and reliable sources of locally produced seed in order to meet the standards for native seed mixes used for reclamation work.
ii. Seeding grass at a heavier rate than shown is likely to reduce sagebrush establishment.
iii. The species described in the seed mix must be used at the rates required.
iv. Fall seeding is recommended for cool season grasses. Sagebrush seed should be applied over light snow cover (1” to 4”) for best results.
v. Seeding depth should be 1/4 inch or less for drilled seed.
vi. For broadcast seeding double the amount of drilled PLS. The seed bed should be thoroughly worked and firm.
vii. The following steps/documents are required:
1. Report of Seeding
MT-01009-9
2. Certification of Seed Mixture from the Seed Company, and seed tags from bags or a copy of seed tags for all planted material must be submitted to the COR prior to seeding.
PART 3: EXECUTION
3.01 PROJECT MEETINGS:
A. Pre-Work Conference:
1. A pre-work conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date, and location. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
2. The Contractor, subcontractors, and the persons responsible for coordination of the work shall be present at the meeting.
3. The Contractor shall be prepared to summarize and explain procedures planned for the project and present the construction schedule and value schedule.
B. Progress Meetings:
1. Meetings shall be held at the project site, or as determined by the Contracting Officer.
2. Meetings may be called by either the Contracting Officer or the Contractor. Requests shall state who should attend and include an agenda.
C. Final Inspection:
1. Meeting shall be held at the project site, or as determined by the Contracting Officer.
2. The Contractor shall notify the Contracting Officer in writing at least 5 working days before the completion date so the Government can schedule final inspection.
3. The Contractor shall require the superintendent to be present during this inspection.
3.02 WORK LAYOUT:
A. Government Requirements:
1. General: The Government will set stakes for the work layout to give the Contractor measurements and lines necessary to perform the work required under the Contract. Baseline monuments, benchmark's, or reference points disturbed or removed during construction shall be reset by the Government at the Contractor's expense.
2. Surveying Time Allowed: The Government will require the Contractor to give 3 working days advance notice for all surveying required by the Government in order to accommodate the
Contractor's Work Schedule.
B. Contractor Requirements:
MT-01009-10
1. General: The Contractor shall, immediately upon entering the project site for the purpose of beginning work, locate slope stakes and reference points and take such action as necessary to prevent their destruction.
2. Contractor shall set control stakes at intervals not to exceed 3 feet in elevation differential on cut and fill slopes to guide earthwork operations at each station slope stake. Such lines, levels, and control stakes shall be marked and maintained for construction and inspection purposes.
3. Contractor shall set all construction stakes needed to perform the required work for vertical and horizontal control to guide earthwork operations, underdrains, and aggregate placement and installation, based off of the slope stake elevations set by the Government for each item for the
Contractors use.
4. Contractor to have a stake jumper on site at all times to set control stakes for cut and fill slopes.
5. Contractor shall prepare, maintain, and proceed in conformity with Storm Water Discharge
Permit/Storm Water Pollution Prevention Plan as required by the Montana Department of
Environmental Quality. Once the contractor prepares and submits the final permit to the
Government, the Government will obtain this permit and pay all fees associated with the Storm
Water Discharge Permit. During construction of the Contractor is responsible for all maintenance to the pollution prevention plan. When the Contractor has completed work on the project and has been issued the final payment, the Government will continue maintenance on the pollution prevention plan. When all criteria have been met, the Government will file the
Notice of Termination for the permit.
6. Contractor shall supply to the Government a draft Storm Water Discharge Permit within 10 days after issuance of the Notice to Proceed. The Government will have 10 days to review and provide comments back to the Contractor. The Contractor then has 10 additional days to submit the final Storm Water Discharge Permit to the Government. Work may proceed after the final Storm Water Discharge Permit has been returned to the Contractor with an acceptance letter from the Government. The Contractor shall perform all compliance testing required by all permits. Submit results of compliance testing directly to the appropriate review agency.
Provide copies of all results to the Government. Submit copies of any additional required permits to the Government when they are acquired.
3.03 CLEAN-UP:
A. Waste Removal: The Contractor shall at all times keep the premises free from accumulation of waste materials or rubbish caused by his employees or work. At the completion of the work, the
Contractor shall remove all such materials from the work site. The Government may remove all such materials and charge the cost to the Contractor, if the site is left untidy.
3.04 SAMPLING AND TESTING:
A. Independent Third-Party Testing Lab: Provide independent third-party testing and test results for all contract work as required per the Statement of Work and Specifications incorporated by reference from the 2014 MDT Standard Specifications for Roads and Bridges. Provide all material testing and lab results to demonstrate full compliance with requirements.
MT-01009-11
B. MDT Materials Manual: All sampling and testing requirements shall follow the latest edition of the
MDT Materials Manual, hereby incorporated by reference.
PART 4: MEASUREMENT AND PAYMENT
4.01 MOBILIZATION:
A. Measurement and payment will be made in accordance with Section 109 of the MDT 2014 Standard
Specifications for Roads and Bridges.
4.02 TRAFFIC CONTROL:
A. Measurement and Payment will be lump sum in accordance with Section 618 of the MDT 2014
Standard Specifications for Roads and Bridges.
4.03 CLEARING:
A. Any clearing is anticipated to be incidental and will be included in Reclamation/Seeding. No additional payment for this work will be considered.
4.04 PIPE CULVERTS:
A. Measurement and payment will be made by the linear foot in accordance with Section 207 of the
MDT 2014 Standard Specifications for Roads and Bridges.
4.05 RIPRAP, CLASS I:
A. Riprap will be measured and paid for by the ton of material transported and placed in the locations designated on the plans. Material quantities shall be determined by weighing at a certified scale and tickets given to the Government.
4.06 SEPARATION GEOTEXTILE:
A. Measurement and payment will be made by the square yard in accordance with Section 622 of the
MDT 2014 Standard Specifications for Roads and Bridges.
4.07 ROAD CONDITIONING:
A. Road Conditions will be measured and paid for by the linear foot as measured along the centerline of the roadway.
4.08 WATERING:
A. Water for road conditioning, compaction of crushed top surfacing, or dust control will not be measured for payment. Watering directed by the COR for achieving appropriate moisture during construction will be measured and paid for per gallon rounded to the nearest 1000 gallons.
B. No direct payment for watering road conditioning, compaction of crushed top surfacing, or dust control will be made. The Contractor shall include consideration for this item in the bid price for
MT-01009-12
other scheduled items of the Contract. For Watering directed by the COR the accepted quantities will be paid for at the Contract price per unit of measurement, respectively, for the pay item shown in the Bid Schedule. Price and payment shall be full compensation for furnishing and delivering all material, including source selection and approval, labor, equipment, tools, and incidentals necessary to complete the work described in this section.
4.09 SALVAGING, STOCKPILING, AND PLACING TOPSOIL:
A. Any salvaging, stockpiling, and placing topsoil is anticipated to be incidental and will be included in
Reclamation/Seeding. No additional payment for this work will be considered.
4.10 CRUSHED TOP SURFACING:
A. Measurement and payment will be made by the ton in accordance with Section 301 of the MDT
2014 Standard Specifications for Roads and Bridges. Material quantities shall be determined by weighing at a certified scale and tickets given to the Government.
4.10 RECLAMATION/SEEDING:
B. Measurement and payment will be made by the acre in accordance with Section 610 of the MDT
2014 Standard Specifications for Roads and Bridges.
END OF SECTION