Statement of Work (SOW)
Non-Complex Construction Basic Ordering Agreement (BOA) 20 October 2020
Table of Contents
| 1.0. PROJECT OVERVIEW | 3 |
| 2.0. Terminology | 3 |
| 3.0. General Information | 4 |
| 4.0. Key Personnel | 5 |
| 5.0. Task Order Proposal Preparation | 6 |
| 6.0. Task Order Performance | 7 |
| 7.0. Design Requirements | 7 |
| 8.0. Installation Requirements | 10 |
| 9.0. Runway & Flightline Operations | 12 |
| 10.0. Environmental & Utility Concerns | 14 |
| 11.0. Deliverables | 15 |
| 12.0. Project Completion | 17 |
1.0. PROJECT OVERVIEW
1.1. Description of Services: This Basic Ordering Agreement (BOA) is a written instrument of understanding, negotiated between the Government and Contractor to provide non-complex construction services to be competed among a pool of approved vendors. This agreement is not a contract. Work shall be defined in individual Task Orders and may consist of multiple disciplines in general construction categories. It may involve minimal design services for all aspects of general construction including construction, modifications, and renovations of existing facilities. Work may include but is not limited to: maintenance, repair, alteration, mechanical, electrical, heating/air conditioning, demolition, painting, flooring, paving, and earth work for industrial/office buildings and/or infrastructure. The Contractor shall furnish all design, labor, equipment, material, manufactured articles, transportation, supervision, and all necessary items to accomplish the design and/or repair/construction of each Task Order written under this agreement for all work that is defined for each project. Work locations include buy may not be limited to RAF Mildenhall, RAF Lakenheath, RAF Feltwell, RAF Molesworth, RAF Alconbury, RAF Fairford, RAF Croughton, RAF Welford, RAF Caversfield, RAF Barford St John, RAF Sculthorpe and RAF Blenheim Crescent. Task Orders will be completed as required per all BOA applicable specifications, referenced documents, and as identified on any attached Task Orders project documents as applicable.
1.2. Construction Drawings: All drawings required for completion of the task order, will be developed to the applicable stage of completion. The contractor is required to maintain a set of drawings on site at all times.
2.0. Terminology
2.1. Contracting Officer (CO): The Contracting Officer refers to a person with the authority to enter into, administer, change and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the Contracting Officer acting within the limits of their authority as delegated by the contracting officer.
2.2. Construction Inspector: The cognizant Base Civil Engineer Squadron will represent the CO while inspecting works being accomplished and accepting completed construction works. This designation in no way authorizes anyone other than the CO to commit the Government to changes in the terms and conditions of the contract.
2.3. Contract Clauses: Where Special Clauses or General Provisions are referred to in the specifications, reference should be to Contract Clauses.
2.4. Task Order (TO): A TO is an order placed against an established contract/agreement, which may contain the general requirements and parameters of a proposed project. Included with the TO may be a Statement of Work that defines specific technical requirements for the project or a Statement of Objectives that describes the required work in more general terms allowing the Contractor the ability to provide their own Statement of Work. A TO may also include information such as budget limitations, design certifications and drawings required to be prepared by the Contractor. Orders issued under this agreement will be considered a binding contract upon acceptance by the Contractor. Acceptance will occur by signature on the TO documentation.
2.5. Statement of Work (SOW): SOWs are written descriptions documenting work required by each Government TO. They may be provided by the Government or prepared by the Contractor, depending on the individual TO. Included in the SOW are the specific technical requirements for the project.
2.6. Statement of Objectives (SOO): A SOO is the initial document, with drawings where applicable, provided to the Contractor by the Government outlining the overall performance objectives to be completed. It is used in solicitations when the Government intends to provide the maximum flexibility to each offeror to propose an innovative approach.
2.7. Site drawings: Site drawings are plans and details as required by the task order.
2.8. Structural drawings: Structural drawings are plans, details, and connections as required by the task order.
2.9. AF Form 66 (AF66), Schedule of Material Submittals: An AF66 listing all required submittal items will be included with the project documents (drawings, specifications, submittals, reports, design analysis, etc.). The AF66 will identify when these items need to be submitted relative to the phases of construction (i.e. prior to the start of construction, during turnover, etc…). All submittals identified on the AF66 shall be electronically submitted on an Air Force Form 3000, Material Approval Submittal.
3.0. General Information
3.1. The scope of work for each project shall include all requirements defined herein as well as all work identified in the subject TOs.
3.2. The BOA will be utilized to execute a broad range of maintenance, repair and minor construction projects on real property at all Royal Air Force bases identified within this SOW. These projects may include tasks in a variety of trades such as demolition, site work, excavation, cast-in-place concrete, masonry, structural steel, electrical, mechanical (including HVAC), painting, millwork, flooring, and other specialty and general contracting work. Any order requiring design will at a minimum provide 35% specifications.
3.3. Implementation/Termination of Contractors: The government reserves the right to add or remove contractors to the approved list of vendors identified within the BOA. Any offeror capable of providing the technical and management capabilities necessary to execute orders for this BOA may be included at any time, given standard and statutory requirements are met. Inversely, offerors who regularly refuse to provide quotes, underperform, or fail to meet the terms of individual task orders may be removed from the list of vendors attached to the BOA.
3.4. The BOA program may include any and all offers who communicate interest and provide appropriate qualifying documentation. The Government reserves the right to utilize the same process in awarding the original BOAs to make additional awards. Subsequent agreements shall include ordering periods concurrent with the current BOAs.
3.5. Only a CO from the 48th Contracting Squadron is authorized to place individual orders under this agreement.
3.6. Orders issued under this agreement become binding contracts upon express written acceptance of the TO by an authorized representative of the contractor.
3.7. Ordering Limitations. Individual orders under the agreement shall not exceed $500,000.00.
4.0. Key Personnel
4.1. Superintendent. The Contractor shall have a Superintendent for each awarded TO in accordance with (IAW) FAR 52.236-6. The Superintendent shall be the Contractor’s assigned individual with the responsibility for quality and production for each TO. The individual must be familiar with the requirements of the Ministry of Defense JSP-375 Safe Systems of Work and have experience in the areas of hazard identification and safety/environmental compliance. The Superintendent should be able to obtain unescorted access to RAF locations.
4.1.1. Duties. The Superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project. The Superintendent is required to attend RAF meetings, partnering meetings, and quality control meetings. The superintendent must be on-site at all times during the performance of each TO issued until the work is completed and accepted.
4.2. Portfolio Manager. Assign a Portfolio Manager with the responsibility for the overall management of all TO projects under the BOA. The Portfolio Manager should be able to obtain unescorted access to RAF locations.
4.3. Non-Compliance Actions. The CO may issue an order suspending all or part of the work for any awarded TO until satisfactory corrective action has been taken in accordance with FAR clause 52.249-10, Default (Fixed-Price Construction). No part of the time lost due to such suspending orders is acceptable as the subject of claim for extension of time or for excess costs or damages.
5.0. Task Order Proposal Preparation
5.1. Task Order Request for Proposal (TORFP) projects will be non-complex performance-oriented tasks that may require minimal design. In rare cases, the TORFP may not have traditional plans and specifications as described herein, but may include sketches, and requests for catalog cuts, and other submittals.
5.2. Competition. TORFPs shall be provided to all BOA contractors. Any offers received shall be given fair consideration for award. Upon receipt of a TORFP, Contractors are encouraged to participate in site visits and submit offers. Failures by offerors to participate responsibly in site visits and submit offers may result in the Government cancelling the agreement and excluding the Contractor from further competition.
5.3. Unless the CO applies one of the exceptions noted below, each TO shall be awarded as a result of competition to the contractor who offers the best value to the Government considering the criteria specified. The CO’s decision as to the selection for award of a TO is not available for protest.
5.4. Proposal Preparation. A TORFP, issued under this agreement, shall be provided to all contractors and will, at a minimum, include a SOW/SOO defining the project requirements. The TO may require the contractor to produce a full design, partial design, or no design depending on the level of design already available and provided to the contractor with the SOW/SOO. All quotes prepared for work under this agreement will be made at no additional cost to the government.
5.5. Evaluation Criteria. Offers will be evaluated based on compliance with the TORFP requirements and the proposed price. The TORFP will indicate the minimum requirements that must be met in order for a proposal to be considered technically acceptable. The Government will identify from all evaluated offers, readily discernible value indicators that fall within the parameters of price, and technical capability. Therefore, the Government reserves the right to select an awardee that provides benefit to the Government that exceeds the minimum outlined standards, but is not obligated to do so. Additionally, the Government is not bound to select an awardee whose offer may exceed the minimum requirement, but whose additional value or benefit is not deemed substantial enough by the CO. Each TORFP will identify the evaluation factors or criteria necessary for award. The type of evaluation criteria will normally correlate to the complexity of the requirement, but will be at the sole discretion of the CO. Evaluation factors utilized are at the discretion of the Government but may include the following.
· Prior Experience – This includes performance for work on this BOA as well as any other contracts awarded
· Ability to meet schedule requirements
· Relevant experience
· Potential impact on other orders placed with the contractor
· Current workload
· Design
· Contractor’s technical understanding of the work
· Most efficient and effective plan to accomplish the work
· Safety/Accident Prevention Plan
· Rationale for proposed materials, types, and quantities
· Sustainable design features
5.6. Clarifications. The Government reserves the right to enter into clarifications with all Contractors who have submitted technically acceptable offers for the purpose of clarifying certain aspects, as well as to resolve minor or clerical errors.
6.0. Task Order Performance
6.1. Commencement of Work. No work under this agreement shall commence until such a time as the CO issues a written TO and a Notice to Proceed (NTP) under the TO. The CO reserves the right to determine the issue date of any NTP.
6.2. Task Order Performance Period. FAR 52.211-10, Commencement, Prosecution, and Completion of Work shall be incorporated into each TO identifying the construction schedule. The Government reserves the right to negotiate a performance period or impose a performance period for each TO.
6.3. The Government will not be obligated to reimburse the Contractor for work performed, items delivered, or any costs incurred, nor shall the Contractor be obligated to perform, deliver, or otherwise incur costs except as authorized by duly executed TOs.
6.4. To the maximum extent practicable, TOs will be firm fixed priced and clearly define the specific works to be performed or the performance desired. Each TO is subject to the terms and conditions of the BOA. In the event of a conflict between the TO and the BOA, the TO shall take precedence.
7.0. Planning, Design, O&M Requirements in Real Property Facilities. Documents and work produced by the Contractor shall comply with the following requirements specified within this section.
7.1. Department of Defense/United States Air Force Guidance.
· Unified Facilities Criteria Program (UFCP). The Department of Defense (DoD) initiated the Unified Facilities Criteria Program to unify all technical criteria (UFCs) and guide specifications (UFGS) pertaining to planning, design, construction, and operation and maintenance of real property facilities. The program streamlines the military criteria system by eliminating duplication of information, increasing reliance on private-sector standards, and creating a more efficient criteria development and publishing process. Contractor shall familiarize with Department of Defense’s (DOD) Specifications and Criteria categories within this program (https://www.wbdg.org/ffc/dod). Specific categories will be identified within individual task order’s design requirement section of the SOW.
· Air Force Guidance Contractor shall also review and familiarize with the Categories listed under the Air Force guidance within the UFCP (https://www.wbdg.org/ffc/af-afcec).
7.2 Industry Standards
· UK Building Control. Contractor shall abide by UK’s Building Regulation 2010 ( https://www.legislation.gov.uk/uksi/2010/2214/contents/made). Additionally, Approved Documents set out detailed practical guidance on compliance with the regulations (https://www.planningportal.co.uk/info/200135/approved_documents).
· Contractor shall follow all manufacturers’ installation instructions and work shall be IAW current British Standards.
· Contractor shall abide by the UK’s Health and Safety Executive (HSE), Construction Design Management (CDM) Regulations 2015 (https://www.hse.gov.uk/construction/cdm/2015/index.htm)
· Contractor shall abide by the Ministry of Defense’s Joint Service Publication (JSP) 375 Directive; Management of health and safety in defense: directive (https://www.gov.uk/government/collections/joint-service-publication-jsp)
· Contractor shall abide by National Fire Protection Association’s codes and standards (https://www.nfpa.org/Codes-and-Standards/All-Codes-and-Standards/List-of-Codes-and-Standards)
7.3. Drawings. If applicable, the Contractor shall prepare drawings, as specified in the TORFP, for Government approval prior to the start of construction. The Contractor shall submit, in accordance with 48th Contracting Squadron’s TORFP, contract technical specifications, and individual TO three (3) hardcopy and one (1) digital copies of the construction drawings, specifications, calculations, equipment schedules, and all other submittal data for each review submittal.
All completed drawings/construction shall clearly identify the work being performed under the TO. Unless otherwise identified in the TORFP, use of existing drawings provided by the government will be allowed provided the Contractor modifies the drawings to accurately reflect the project requirements. If applicable, each sheet shall have an approved title block and border. Basic design criteria utilized for each discipline will be included on the appropriate drawings as required by the TORFP. Examples would include wind and live/dead loads assumed for structural elements, function specific conditions such as lighting levels or future use considerations for electrical systems, site specific climatic design conditions for mechanical systems, and International Building Code analysis (performed to the same level as if being applied to a municipal building permit process). The following is a list of drawings which might typically be required under this agreement.
7.3.2. Construction Drawings. Contractor shall prepare construction drawings in accordance with contract and individual TO requirements and the US Army Corps of Engineers A/E/C Cad Standard (https://www.wbdg.org/ffc/army-coe/cad-bim-%20technology-center) for drawing requirements and standards. All drawings will also be made available to the government in .pdf format as requested.
7.3.3. Drawings Sequence. Arrange drawings by design discipline in accordance with the CAD/BIM Technology Center for facilities, infrastructure, and environment A/E/C CAD Standard Release 6.0 (or current release). All drawings provided by the contractor shall adhere to a logical file naming convention that incorporates the award and task order number.
7.5. Availability of Geographic Information (GIS) Data and Computer-Aided Drafting and Design (CADD) Drawing Files: After award and upon request, any electronic GIS and/or CADD drawing files (collectively referred to as electronic files within this section) will only be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions. Please note that drawings may not be available for every building. The contractor has a requirement to verify the condition of the workspace via a site visit/site investigation.
· Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
· Electronic files are not construction documents. Differences may exist between the electronic files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic files, nor does it make representation to the compatibility of these files with the Contractors hardware or software.
· In the event that a conflict arises between the construction documents prepared by the Government and the furnished electronic files, the construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these electronic files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
· If the Contractor uses, duplicates and/or modifies these electronic files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
· Mechanical and Electrical Drawings with complete schematics, shall show all heating, air conditioning, plumbing and electrical work as required by the task order.
· Fire Protection Drawings with complete schematics and showing all fire sprinkler system layout, pipe sizes, locations of heads, details, etc. as required for construction and to meet the codes.
· Fire Strategies shall be compliant with the UK’s Building Regulations 2010 and NFPA whichever is most stringent to meet the requirements of the UK MoD Defense Safety Authority and US Air Force 48 CES Fire Protection Office.
8.0. Installation Requirements
8.1. Contractor Access. Reference contract clause AFFARS 5352.242-9000, Contractor Access to Air Force Installations, and TO SOWs for details on obtaining base access passes for contractor personnel.
8.2. Base Pass Requirements. The contractor is required to submit a roster of all employees who will require access to the installation within 5 days of issuance of an agreement/award. The roster will include the full name, current address, date of birth of all contract personnel that will require access. Additionally, individuals must submit their United States Social Security Number (SSN) passport number or two other documents (i.e. driver’s license and national insurance number) with corresponding issue and expiration dates. Please note that unescorted base passes may take up to 90 calendars days to process.
8.1.1. Host Agency Check (HAC) Vetting. All local national contractor employees must undergo Host Agency Check (HAC) vetting prior to access to RAF installations. All employee information shall be relayed to the requiring activities’ HAC manager for processing. Required documents will be distributed with agreement/award and shall be completed and returned to the HAC Manager within five (5) days of award. Required documents include but are not limited to NAC Cover Sheet; AF Form 2583, Request for Personnel Security Action; USAFE IMT 19, Residency Check for Employment with the United States Air Forces in Europe; Basic Check Verification Record (BCVR); and Ministry of Defense Liaison Office (MODLO) Proforma Packet for Security Clearance. If MODLO Proforma Packet is required (for foreign nationals), contractor personnel will receive an online application link via the personal email address provided.
8.1.2. Contractor employees are required to complete online application for background check within five (5) calendar days of receipt. If contractor employees do not receive the email within seven (7) days, they shall notify the HAC manager. During processing of background check, Defense Vetting Agency (DVA) may contact the employee via email, phone or post to request further information. DVA may take up to eight (8) weeks to process so employees are responsible to be proactive in checking personal emails (to include junk mail).
8.1.3. Approved security clearance is valid for five (5) years. The Government will not accept any employee with a federal conviction (or host nation equivalent) in their background check. Contractor employees that are U.S. citizens will complete all required documents except MODLO Proforma Packet.
8.1.4. Security clearance will be processed with requiring activity’s Security Manager. All paperwork is approved by the HAC manager, then forwarded to the 48th Security Forces Squadron (SFS) for processing. The HAC manager will receive an email confirmation when 48 SFS submits the documents to MODLO. At that time, the employee may receive a “Red Top” escorted temporary installation pass. Upon completion of MODLO checks, the employee may receive a “Green Top” unescorted installation pass.
8.1.5. Project Superintendent and Portfolio Manager, at a minimum, shall obtain escort privileges to escort subcontractors required to access project sites.
8.1.6. The contractor is ultimately responsible to return all employee base passes to the CO or HAC manager if employees are terminated or no longer employed for this agreement. If base pass cannot be returned, the Contractor must report the First and Last Name, Date of Birth, and the reason they are no longer employed to the CO or HAC manager within three (3) calendar days of termination or absence of leave.
8.2. Physical Security. The Contractor shall be responsible for safeguarding all Government property in his/her work area. At close of each period, facilities and equipment shall be secured.
8.3. Key Control. Periodically the Contractor will be required to perform work in an unoccupied facility. The Contractor shall establish and implement methods of ensuring that all keys issued to the Contractor by the Government are not lost or misplaced, and are not used by unauthorized persons. No key issued to the Contactor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be provided to the CO not later than 5 days prior to the start of the contract. It is the responsibility of the Contractor to prohibit the use of keys issued by the Government by any persons other than the contractor’s employees. It is also the responsibility of the Contractor to prohibit the opening of locked areas by the contractor’s employees to permit entrance of persons other than contractors employees engaged in the performance of assigned work in those areas.
8.4. Conformance with Regulations/Directives. The Contractor shall conform to base regulations and directives pertaining to security, safety, traffic, fire and personnel clearances, insofar as they pertain to the Contractor's activities as directed by the CO. Contractor employees and visitors are subject to the same restrictions as government personnel. Some of these are noted in the following paragraphs.
8.4.1. Smoking. Smoking is permitted in designated, outside smoking areas only. No smoking will be allowed within any base facility or construction site except in designated, outside smoking areas.
8.4.2. Seatbelts. The use of seatbelts by all vehicle operators and passengers is mandatory on all RAF installations. On RAF installations, vehicle operator and passengers not wearing their seatbelt will be issued a traffic citation and may lose on-base driving privileges.
8.4.3. Firearms/Illegal Drugs. No firearms or illegal drugs are allowed to be brought onto RAF Installations. By accepting a vehicle pass, each person gives their consent to a search of their vehicle while it is entering, on or leaving RAF installations.
8.4.4. Cell Phones. Use of cell phones while driving on a RAF installation is prohibited unless utilizing a hands-free device.
8.4.5. Safety. The Contractor shall ensure they comply with JSP 375 Safe Systems of Work and all requirements annotated on the applicable Form Defence Infrastructure Organization (DIO) SDTFM USF 29 for each TO. This includes ensuring they obtain permits to work from the appointed RAF Lakenheath Authorized Persons (AP’s) for those system/components requiring a permit prior to initiating any work on those systems. This includes but is not limited to pressure vessels, HVAC and refrigeration units, gas systems, medical gases, fuels (Petroleum) installation, work on electrical switchgear and confined spaces.
8.4.6. Employee Certification. The contractor shall ensure all personnel working on mechanical or electrical system shall obtain a Skilled Persons Certificate from an RAF Lakenheath/Mildenhall or DIO AP prior to conducting any work on these systems. The requirements for these permits is contained in JSP 375. The contractor shall submit all works certificates at completion. The inspector for each TO shall be the DIO liaison for requests.
8.5. Schedule of Work may be negotiated between the CO and the contractor during solicitation. In the event of any emergency, intense operational demands, adverse wind conditions, and other unforeseen difficulties, the contractor may be required to discontinue all work at locations in the aircraft operational area. The contractor shall notify the CO or technical representative of any changes prior to the start time of each day's work.
9.0. Runway & Flight line Operations
9.1. Work performed under this section shall be coordinated with, and approved by, the CO. Due to the potential need to shut the airfield runway down to complete this work the contractor and the CO must agree on the dates and hours that work will occur. It is the contractor’s responsibility to ensure that the work begins and ends within the agreed to times. This work may involve having to work on weekends or night shifts to meet the runway outage requirements.
9.2. When the runway is open, no personnel or equipment will be allowed on the runway until radio contact has been made with the Control Tower and permission is granted by the Control Tower. A radio for this purpose will be made available by the CO. The Contractor shall be in contact with the Control Tower at all times during work or transportation of equipment or materials.
9.3. In a soft closure of the airfield, radio communications shall remain open between the contractor and the Control Tower, even if there is no one in the Control Tower. There is always someone on duty at the airfield and they can open the Control Tower at any time if there is an emergency or unscheduled flight.
9.4. Before anyone is allowed access to the airfield they must first have a background check and be added to the Controlled Area Entry Authority List (EAL). Provide names, driver’s license numbers and date of birth to the CO 14 calendar days prior to start of construction. Suppliers whose names cannot be provided must be escorted by a government employee. Notify the CO 30 days prior to start of construction. This government escort is for security reason not for communicating with the tower.
9.5. Foreign Object Debris (FOD). FOD is not allowed on the airfield. Remove rock and pebbles from your shoes and vehicle wheels and truck beds prior to entering the airfield. No hard hats, soft hats, lose clothing, scarf, and lose papers, drinking cups or cans, gum, cigarette butts, chew, trash…anything that can be picked up by the wind of a plane engine. A thorough sweep of your person and equipment is required prior to entering the air field.
9.6. In a soft closure of the airfield, all FOD must be removed regularly to ensure that if there is an emergency landing then all equipment, personnel and FOD can be removed within three (3) minutes. A thorough sweep of your person and equipment is required in the event personnel are notified of an emergency landing.
9.7. In a hard closure of the airfield, all FOD must be removed prior to leaving the construction site. A thorough sweep of your person and equipment is required prior to leaving the air field to mitigate the spread of FOD.
9.8. If it is found that FOD related to the construction site caused damage to an airplane or delayed the airfield usage, then the contractor will become liable for damages accordingly.
9.9. The operation of equipment and the performance of work on or in the vicinity of airfields shall be coordinated with the CO and with the Airfield Management. Neither equipment nor personnel shall use any portion of an airfield without permission of these agencies. In all cases, verbal communication shall be maintained with the air traffic control tower (ATCT) before and during work on any runway, taxiway or apron which is in operation for conducting flights or aircraft operations. The ATCT staff shall be advised when work is completed. A construction waiver will be obtained by the CO prior to the start of construction. The contractor does not have to do anything to obtain this waiver but they must be aware that it can take up to 90 days to get the waiver signed. The government will add days to the contract to make up for this government delay.
9.10. Comply with Occupational Safety and Health Administration (OSHA) 29 CFR 1910. Also, prior to beginning work on the airfield contractor must ensure that contractor personnel receive training on airfield safety and flight line driving from the government (Reference AFI 13-213). For airfield safety requirements contractor will coordinate with the CO at least 30 days prior to beginning work on the airfield via the Government Project Manager. For required flight line driving training contractor must contact the Vehicle Control Officer (VCO) at the appropriate RAF installation at least 14 days prior to beginning work.
9.11. If required, the contractor shall provide at least two (2) people per construction site who have taken the Airfield Operation provided driving course and have a current AF Form 483 Certificate of Competency. One of these persons must be on site at all times to communicate with the tower and to escort personnel who are on the Entry Authority List (EAL). This person may not escort anyone who is not on the EAL. Construction workers working on airfield sites must also take and pass various training requirements outlined in ETL 13-213.
10.0. Environmental & Utility Concerns
10.1. Digging permits must be obtained prior to any digging, drilling or any excavation work. Digging permit /utility locations are available by submitting the completed US Air Force Form 103. Contractor to allow 21 calendar days for Government review of digging permit requests. A digging permit for a specified area of excavation expires 30 days after the issue date; the Contractor must re-apply for a new permit to perform excavation in the area if the excavation was not started within the 30-day period. It should be noted that the AF 103 should not be relied upon as a design preparation aid or tool. All contractors are expected to conduct their own site investigations.
10.2. Permits will identify all underground utilities within 5 feet of the designated area. Contractor shall be responsible for all repairs, costs, and damages due to excavating without permit or damaging an identified utility. Applicable construction drawing(s), five hard copies
10.3. Utility Outage Permit. Contractor shall complete and submit a written request 21 days in advance of the requested utility outage to CES Customer Service through the 48 CES Construction Manager. The request shall include the utility service to be affected, proposed date, proposed time, and outage duration. Form 103 can also be used for the request. Provide CES Construction Manager a copy of the written Utility Outage request. After submitting the request to the government, the Contractor must receive approval from the government prior to schedule a utility outage.
10.4. Hot Work Permits. Contractor shall obtain a Hot Work Permit for any welding, burning, abrasive blasting, hot-riveting, or other fire-producing or spark-producing operations every 30 days. Contractor shall contact the appropriate RAF Fire and Emergency Services Fire Protection Element to request the permit. No form required for the request. Contact the CO/inspector for the cognizant CE squadron for additional information.
10.5. The Hot Work Permit will be issued by the appropriate RAF installation’s Fire and Emergency Services. Air Force Form 592, will be issued by the cognizant installation’s Fire and Emergency Services once the permit is approved. Permits expires in 30 days, so if work will be extended beyond 30 day period the Contractor must contact the cognizant installation’s Fire and Emergency Services to re-issue a new permit. Road Closure Approval Requests: Road closings or restrictions will not be permitted without approval. To get approval for a proposed road closure Contractor must submit a traffic control plan to the CO 30 days in advance, or a minimum set amount of time as stated in individual TO.
10.6. The Contractor traffic control plan will include each section of road that will be worked on or impacted as a result of this contract.
10.7. Contractor will provide traffic control signs, lights and barricades as needed for all street widening and extensions. At least one lane of traffic must be maintained at all times unless otherwise approved by the CO.
10.8. The Contractor shall minimize environmental pollution and damage during the course of the contract. The control of environmental pollution and damage requires consideration of land, water, and air resources. The environmental resources within the project boundaries and those affected outside the work area shall be protected during the entire duration of this contract.
10.9. Removal. Unless otherwise specified and insofar as is practicable, items and materials shall be removed in a manner inverse to that used in the placing of the items and materials in the structure(s). Care shall be taken during removal operations to prevent any unnecessary damage to the building. Any unnecessary damage to the building(s) resulting from the Contractor's operations shall be repaired at the expense of the Contractor and to the satisfaction of the CO. Equipment to be reinstalled shall be reinstalled after work called for under other sections of these specifications has been completed. All items which are to be removed and then reinstalled shall be carefully removed and protected until reinstalled.
10.10. Disposal. Rubbish and debris shall be removed from Government property daily, unless otherwise directed, to avoid accumulation at the site. Materials that cannot be removed daily shall be stored in areas specified by the CO. Concrete, masonry, and other noncombustible material, and combustible material, shall be disposed of off the site unless otherwise specified. Remove and transport debris in a manner that prevents spillage on streets or adjacent areas. Local regulations regarding hauling and disposal shall include the submission of Consignment/Waste disposal certificates for all waste removed from the worksite.
11.0. Deliverables
11.1. An AF66 – Schedule of Submittals, will be provided with each project package. Contractor is required to provide listed documents within the requested timeframes throughout project performance..
11.2. AF Form 3000 (AF3000), Material Approval Submittal: Each submittal shall be transmitted under an AF3000 and shall be prepared in accordance with the Instructions on the reverse of the form. Resubmittals will have a corresponding letter designation after last number, i.e., submittal 001 would be resubmittal 001A or 001B, etc. if rejected a second time.
11.2.1. Variance from contract requirements: Whenever materials or drawings are required to be submitted by the Contractor for approval on an AF Form 3000, and the material or drawings submitted are at variance with the specifications or Government drawings, but are approved by the Contracting Officer inadvertently and without consciousness of the variance, then the approval shall not be final unless the Contractor expressly noted on the submittal that "This material or drawing varies from specifications in the following aspects."
11.3. Safety Data Sheets. Any and all hazardous/toxic materials brought to the job site shall require manufacturer-specific Safety Data Sheets (SDS) or the UK equivalent of Control of Substances Hazardous to Health (COSHH) (FAR 52.223-3, Hazardous Material Identification and Material Safety Data).
11.4. Hazardous Materials/Chemical Management: Hazardous Materials/Chemical Management: All hazardous material use requires prior authorization before bringing the hazardous material on base. "Hazardous material" includes many materials for which there is a manufacturer SDS, such as cleaning supplies, paints, solvents, sealants, lead acid batteries, fuels, herbicides, etc.The Contractor shall submit an inventory list of all chemical products to be used, along with copies of the Safety Data Sheet (SDS) for each chemical product, for review before bringing any potentially hazardous material onto any RAF installation using the “HazMat Authorization Request Template”. The Contractor shall submit completed inventories and SDSs to the CO, at least 10 days prior to the date required to bring them on base.
11.4.1. Once approved, the Contractor shall maintain an inventory of all hazardous materials along with corresponding Safety Data Sheets (SDSs). The Contractor shall track and report actual hazardous material usage during the performance of the contract. Hazardous material usage for any contract that is less than one month in duration shall be reported at the end of the contract period. Hazardous material usage for any contract over a month in duration shall be reported no less than monthly. Hazardous material usage shall be reported IAW the cognizant US Government organization.
11.4.2. The Contractor shall not leave any excess hazardous materials or empty containers on site following completion of the project. The Contractor is responsible for the removal of all unused hazardous materials and proper disposal of all hazardous waste generated. Reference: AFI-32-7086, Hazardous Materials Management
11.5. Controls of other hazards. Contractors must coordinate with the CO at least 10 days prior to start of project, regarding all contracts with potential health impact to personnel (Example: Noise above 85 dBA, activities with potential airborne contaminants or particulates). Hazardous work areas/perimeters shall be established to control exposures and limit access to nearby facilities and personnel. Work shall be performed IAW all applicable occupational health and safety regulations.
11.6. Contractors must coordinate with facility managers and receive a safety brief of hazards present within work areas.
11.7. Documentation. The Contractor shall maintain current records providing factual evidence that required quality control activities and/or tests have been performed. These records shall indicate a description of trades working on the project; the number of personnel working; and any delays encountered.
11.9. The TO documents indicate the extent and requirements of the alterations and additions to the existing facilities. If any departures from the drawings or specifications are deemed necessary by the Contractor, details of such departures and the reasons therefore shall be submitted as soon as possible to the CO for action. No such departures shall be made without prior written approval of the CO.
12.0. Project Completion
12.1. Painting and Finishing. Existing surfaces where items and materials were removed shall be repaired and painted to match the adjoining surfaces. Surfaces remodeled shall be painted to match the adjoining surfaces. All new surfaces where specified or required to be painted shall be painted. Existing painted surfaces which are damaged by work under this contract shall be repaired to original condition and then repainted with one coat of paint to match adjacent surfaces. Where an existing painted wall or ceiling has been repaired or patched with new materials, the entire wall or ceiling containing the repaired portion shall be repainted as follows.
12.1.1. The repaired portion shall be painted to effect complete hiding and to blend with the adjacent surfaces, and then the entire wall or ceiling given one coat of paint. Preparation, Painting, and Protective coatings (Corrosion Control/all works) will require the contractor to submit a formal, completed, local CES Preparation/Painting & Coating Sheet on works competed as applicable to scope. The finished surfaces shall be free from runs, drops, ridges, waves, laps, brush marks, and variations of color, texture, and finish.
12.2. Alterations. Alterations to the structure(s) shall be in accordance with the arrangement indicated on the contract documents and as approved by the CO. All alterations shall be performed by workmen skilled in the work and in accordance with the best standard practices of the trades involved. All work shall be performed in accordance with the requirements for new work as specified under the applicable sections of these specifications.
12.3. Clean Up: Upon completion of the work all staging, scaffolding, and containers shall be removed from the site or destroyed as approved. Paint spots, oil or stains upon surfaces shall be removed and the entire job left clean and acceptable to the CO.
12.4. Government Possession of Work. The Government may take possession of any completed or partially completed work as provided for under FAR Clause 52.236-11, Use and Possession Prior To Completion. If the installed equipment and/or systems thereto, have not been accepted by the Government due to the Contractor's failure to submit the above specified items, the Contractor shall operate and maintain such plant or system at no additional cost to the Government until such time that the specified items have been received, approved and any subsequent testing, check-out and/or training has been completed.
12.5. Record Drawings. The Contractor shall provide complete detailed as-built drawings and applicable GIS data including survey information and files representing the entire project as constructed under the Contract. Drawings shall be developed in accordance with guidance provided in this SOW. Preliminary as-built drawings shall be submitted with an AF Form 3000 in blue line format for Government Approval.
12.6. Warranty of Construction. Warranty of Construction shall be executed in accordance with FAR 52.246-21, Warranty of Construction. If the Contractor fails to remedy any failure, defect, or damage within a time as specified in warranty call notice provided to the contractor by the CO, after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.
12.7. Warranty Service Calls. The Contractor shall furnish to the CO the names of local service representatives and/or Contractors that are available for warranty service calls and who will respond to a call within the time periods as follows: 4 hours for heating, air-conditioning, refrigeration, air supply and distribution, and critical electrical service systems and food service equipment, and 24 hours for all other systems. The names, addresses, and telephone numbers for day, night, weekend, and holiday service responses shall be furnished to the CO and also posted at a conspicuous location in each mechanical and electrical room or close to the unit.
12.8. Quality Control Records. The Contractor shall maintain current Quality Control (QC) records in an appropriate format (Microsoft Word document) of all inspections and tests performed. These records shall provide factual evidence that the required inspections or tests have been accomplished; indicate the results, the nature of any defects and causes for rejection, the proposed remedial action, as well as what corrective action(s) have been taken. The Contractor shall not build upon or conceal any feature of the work containing uncorrected defects. Quality inspection records shall be available for review by the Government throughout the life of the contract and shall be maintained a minimum of three (3) years after the contract has been completed.
12.9. Notice of Non-Conforming Work. Non-conforming work shall be immediately replaced or corrected. Immediately bring any disagreements to the attention of the Contracting Officer, in writing, for resolution.
12.10. Pre-Final Inspection Notification. The Contractor shall notify the CO and the Cognizant Civil Engineering Squadron at least seven (7) business days in advance of the desired pre-final inspection date so that there would be sufficient time to coordinate attendance of necessary personnel. Based on the inspection, the Government shall generate a punch list of contract items needing to be corrected or completed by the Contractor. This punch list may not necessarily be the final punch list. Additional items may be identified during the Final Inspection.
12.11. Final Inspection Notification. The Contractor shall notify the CO in writing at least five (5) working days in advance of the desired final inspection date. Final clean-up shall be made prior to a final inspection, and consist of cleaning the site and adjacent areas, as required by the this SOW. Soil disturbed by construction activity shall be left in a uniform, smooth, and compacted condition.
12.12. Declination to Inspect. The CO reserves the right to both decline the contractor’s request of a pre-final and/or a final inspection when it is evident that the project is not ready for inspection.
12.13. Prior to final acceptance, the Contractor is required to provide the Government with all required Operation & Maintenance manuals, warranty information, and all applicable training needed for users to safely operate and maintain equipment. These manuals will be specifically identified on the AF66 for each TO.
12.14. Acceptance. Final acceptance will not occur until all work, to include submittal items and clean-up, has been accomplished and no discrepancies remain. Final inspection and acceptance should be scheduled prior to or not later than the contract completion date.