Attachment 1 Additional Info.pdf

PDF 138 KB Posted

Attached to
PIH, OGD and SLE Design-Build for Airport Traffic Control Towers
Solicitation number
697DCK-24-R-WSA01
Issued by

About this file

This document provides additional information for the Design-Build solicitation for Airport Traffic Control Towers in Pocatello, Idaho, Ogden, Utah, and Salem, Oregon. Key details include:

The selected contractor will be required to adapt the standard design to each site. Pocatello, Idaho is the guaranteed project, while Ogden, Utah and Salem, Oregon are bid options. The contractor is responsible for all permitting, coordination with local authorities, geotechnical investigations, and site-specific design work. The standard design provided is for information only and does not represent a full design. Deviations from the standard are allowed in certain areas. The estimated schedule includes completing the NEPA process by January 2024 and awarding the design-build contract in October 2024, with a 24 month performance period.

View the file

Other files

File Type Posted
Attachment 3 PIH Site Plans.pdf PDF
Attachment 3 OGD Site Plans.pdf PDF
Attachment 4 PAU Design.pdf PDF
Attachment 2 TFDS_V2.1.pdf PDF
Attachment 3 SLE Site Plans.pdf PDF
MARKET Survey WSA ATCT Towers.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEPA

The NEPA process has not been completed for these sites and must be complete to initiate land leases.

No physical work or early procurement of equipment and materials can be authorized without NEPA process completed and approved. The initial work is limited design and reversible work.

Key Site The selected DB Team (contractor) will be required to site adapt the PAU Standard Design specifically for the site. The Key Site is Pocatello, Idaho and is the guaranteed project. Ogden, Utah and Salem Oregon are the two additional potential sites listed as bid options. Future award of these sites is not guaranteed.

Permitting and Coordination

All local, State and Federal environmental permitting is the responsibility of the Design Build Team (the contractor). The contractor is responsible for coordination will the local Fire Department and Airport for the design and construction activities.

The Federal Government is not allowed to pay for building permits. Collaboration and implementation of local building codes is encouraged but limited. Internationally recognized codes and FAA Requirements such as but not limited to: IBC, IMC, IPC, IFC, ASCE 7, NPFA 101, NFPA 70, TFDS, ASHRAE 90, ASME 17.1, FAA-STD-19f, FAA-STD-002H, Executive Orders form the basis of the project. The Design Build Team and FAA will not be seeking a building permit.

The Design Build Team (the contractor) is responsible for all site-specific activities such as but not limited to:

• Site Development: access, foundations, security, Fire Department access

• All Environmental Permitting

• Site specific geotechnical site investigation and foundation design

• First responder coordination

• Local Utilities

• Mechanical

• Structural

• Civil

• Building enclosures

• High Performance Sustainable Building

• Assume the cab floor elevation for all three sites is 110 FT AGL

Standard Design

• FAA BIL ATCT Standard Design by PAU is progressed to ensure the design is compatible in multiple locations in the United States

• The progressed drawings are provided for information only. They do not represent full complete design.

• The design was progressed to ensure adequate code compliant space was available.

• Structurally seismic zone 3 was selected to address most locations.

Deviations Allowed from the TFDS

1. Where the TFDS refers to “Site Specific” information, Offeror is directed to the General Requirements above that the facility needs to be fully adaptable to any climate and loading conditions in the contiguous U.S.

2. Standard Drawings will not be provided as part of this SIR. This SIR requires new development of standard drawings that also comply with TFDS.

3. The use of Computer Access Flooring is not permitted.

4. Paragraph 3.3, Physical Security – Compliance is not applicable to the 10% design.

However, the successful Offeror must comply for future submittals.

5. Paragraph 3.8, Project Planning Document – The FAA will not provide a sample PPD.

6. Paragraph 5.2, General Design Criteria, Item F – 25% expansion is included for the electronics equipment space in Article 3.3.

7. Paragraph 5.2, General Design Criteria, Item G – Refer to Article 3.4.

8. Table 5-4, Amenities/Shared Support Spaces – Apply Breakroom/Kitchen finishes to the Controller Lounge/Locker Room finishes.

9. Table 5-7, Acoustic Design Criteria Matrix – Apply Training and Conference Room Acoustic Design Criteria to the Collaboration Room.

10. Paragraph 5.8.1, Lobby – Not applicable.

11. Paragraph 5.8.2, Connecting Link – A connecting link is not included, but the design must accommodate and be adaptable for connection of a future minimum six (6) foot wide (interior dimension) link to connect the ATCT to a potential future support building adjacent to the structure. Provide an accessible pathway for future cable access from the tower to a future link.

12. Paragraph 5.10.1, Breakrooms/Kitchen – Item 1 through Item 4 apply to the Controller Lounge/Locker Room. In Item 3, provide microwave oven and refrigerator only. In Item 4, provide accessible sink with garbage disposal only. Item 5 through Item 7 do not apply.

13. Paragraph 5.11.7, Electrical/Mechanical/Plumbing Chases – Dedicated mechanical and plumbing chases are not required.

14. Paragraph 5.11.9, Loading Dock – Loading dock/platform lift is not included in this part of the design.

15. Paragraph 5.12.1, TRACON Operations Rooms – Not included in this design.

16. Paragraph 5.12.2, NAS Electronic Equipment Rooms, Item A – Replace “TRACON” with “ATCT Cab.”

17. Paragraph 5.13.1, ATCT Tower Shaft Use and Occupancy, Item A – Not applicable.

18. Paragraph 5.13.2, ATCT Stairs, Item B.3 – A minimum 3 feet 8 inch wide stairwell is not mandatory unless required by code.

19. Paragraph 6.1, Exterior Wall Assemblies – Does not apply. Exterior wall assemblies must be code compliant.

20. Paragraph 7.1.4, Siting Study – Applicable only to Option A.

21. Paragraph 7.2.7, Cab Floor Hatch and Hoist – Do not include a floor hatch in the design.

22. Paragraph 8.7, Structural Systems and Materials, Item A – The prohibition on use of wood products does not apply.

23. Paragraph 8.10, Subsurface Investigation – Applicable only to Option A.

24. Paragraph 9.2, Life Cycle Cost Analysis – Applicable only to Option A.

25. Paragraph 9.5, HVAC System Requirement, Item C

a. Replace “Communication and Radar Equipment Rooms” with “Electronic Equipment Space.”

b. Provisions for the UPS equipment are included in the Electrical Space requirements in Table 3.4-1 and Appendix A. Redundancy must be provided in the room that contains in the UPS equipment.

c. The use of single cabinet air handling units with redundant fans are not permitted.

d. A separate air distribution system(s) must be provided to the critical spaces (mixing of non-critical with critical air is not permitted).

26. Paragraph 9.15, Air Distribution Requirements, Item A – Rooftop HVAC equipment is prohibited except for exhaust fans.

27. Paragraph 12.5, Construction and Finishes, Item A – Does not apply. Comply with the code.

28. Paragraph 12.6, Barriers and Openings Protection, Item B – A console access ring is not a mandatory requirement. National Fire Protection Agency (NFPA) 75 requirements still apply.

29. Paragraph 12.7, Means of Egress, Item A – Refer to Article 3.3, Item G.

30. Paragraph 12.14, Elevator Systems Features and Protection, Item B – Replace “Occupant evacuation elevators as defined by the IBC and NFPA 101 must only be provided where specifically directed by the FAA” with “Occupant evacuation elevators as defined by NFPA 101 are permitted.” An elevator in compliance with NFPA 101 is permitted to be used as a second means of egress from a tower.

31. Paragraph 12.16, Miscellaneous – Unless Offeror’s design dictates such, a separate room for the Fire Command Center is not required.

Paragraph 14.2, Planning and Design Requirements, Item I.3 – A TFDS deviation request is not required for use of machine-room-less elevators.

Locations:

• Pocatello, Idaho

• Ogden, Utah (Bid Option 1)

• Salem, Oregon (Bid Option 2)

Key Site Estimated Schedule – Pocatello, Idaho

• Programmatic EA FONSI by end of October 2023

• Site Specific EA 2-3 months, complete by Jan 2024 (NEPA approved)

• Lease initiation Jan 2024 – June 2024 (4–6-month duration)

• Solicitation June 2024

• DB award in October 2024

• DB Duration: 24 months

Attachments:

1. Terminal Facilities Design Standard 2.1

2. Site plans for Pocatello, ID; Ogden, UT and Salem, OR