This Statement of Work (SOW) outlines construction services required for Project 668-CSI-009 to renovate rooms C208F/G for IR/RF at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The project duration is 214 calendar days and involves renovation of control room and imaging room spaces, including removal of piping, drains, wall demolition, installation of lead shielded walls and windows, door relocation, and partial control room removal.
The scope includes HVAC modifications with a new unit for additional airflows, ducting, crane work, and electrical components; structural analysis; unistrut installation; floor replacement; asbestos abatement; and ICRA precautions. Work must be performed nights and weekends. The contractor must provide manufacturer's representative oversight, commissioning documentation, systems demonstration and testing, and training for VA personnel. No government-furnished equipment will be provided. All work will be evaluated by VA Engineering Service subject matter experts and requires final systems demonstration and validation in the presence of the Contracting Officer's Representative (COR).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 668-CSI-009 Specifications.pdf | ||
| 36C26025R0031_1.docx | DOCX document | |
| Attachment 3 668-CSI-009 Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project 668-CSI-009 Renovate C208F/G for IR/RF Page 1 of 2
STATEMENT OF WORK FOR CONSTRUCTION SERVICES
Renovate C208F/G for IR/RF Project No. 668-CSI-009
Mann-Grandstaff VA Medical Center Spokane, WA April 1, 2024
Attachments to this document include the following. Contact the CO if any items are missing.
• Project Drawings
• Project Specifications
1. General Provide construction services to include labor, materials, tools, equipment, transportation, supervision, and other services necessary for “Project 668-CSI-009, Renovate C208F/G for IR/RF” at the Mann- Grandstaff VA Medical Center, Spokane, Washington. Scope of work is indicated below. Total project duration shall be 214 calendar days.
2. Scope.
The Project includes but is not limited to the following renovation: control room and imaging room renovations including removing all piping, drains, wall demolition, lead shielded wall and window, and relocating door; removal of half of control room which will require lead shielded wall, and a door to be installed; HVAC to include a new unit for additional airflows, ducting, crane, and electrical; structural analysis; unistruts; floor replacement; asbestos abatement; nights and weekends, and ICRA precautions.
2.1. The contractor shall provide a qualified manufacturer’s representative to check complete installation for conformance to manufacturer’s recommendation, to place the system into service, to make all adjustments required for full conformance to design and specified requirements and to perform all demonstrations and testing.
2.2. An operating test shall be run in the presence of the Contracting Officer’s Representative (COR), in accordance with the commissioning specifications.
2.3. The contractor shall provide Commissioning documentation.
2.4. The contractor shall provide demonstration and training to VA personnel.
2.5. The contractor shall verify locations for space requirements.
3. Deliverables:
Inspection, testing documents, and manuals and warranty documents per Specifications.
4. Performance Monitoring The Spokane VAMC facility subject matter expert assigned to the Engineering Service will evaluate all work and testing performed. Items must be in a clean state and in a proper and acceptable working condition.
Project 668-CSI-009 Renovate C208F/G for IR/RF Page 2 of 2
5. Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI).
The Contractor will not have access to any Government-Furnished Equipment. All equipment and supplies used under the terms of this contract will be the responsibility of the Contractor.
6. Inspection and Acceptance Criteria.
As part of final system acceptance, a systems demonstration is required. Prior to start of this demonstration, the contractor is to perform a complete validation of all aspects of the Controls and Instrumentation System. System operation and calibration shall be demonstrated by the installer in the presence of COR.
7. Place of Performance.
VA Medical Center Spokane Washington, located at 4815 North Assembly Street, Spokane Washington 99205.
8. Period of Performance.
The Contractor has 214 calendar days to perform all described work.